Project name: ATB-PU TANJUNG BIN, PONTIAN, JOHOR. TRANSFORMER (TESTING) Revision 0
Prepared by – Work Contractor Reviewed by: Approved by:
Organization HQC ENG. MALAYSIA HQC ENG. MALAYSIA HQC ENG. MALAYSIA SDN BHD
Name Md Hizam Mohd Ariff Sinnathamby kannoo Razali
Position Commissioning supervisor Commissioning Lead Safety and Health Officer Commissioning Manager
Date 04/08/2021 04/08/2021 04/08/2021 04/08/2021
Signature
P4 B B4 Carry out pre-use inspection to ensure all cables, B1 B B1 Switch off the Respective
Exposed cable Personnel injury connectors and clamps are in good condition electrical supervisor
(Electrical shock)
All DB shall be equipped with ELCB and to be inspected and equipment
have a valid “Safe for Use” stickers, and adequately during any
protected from weather emergency
All electrical cables must hang above head