Professional Documents
Culture Documents
No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
PAINTING PROCEDURE
Page 1 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
TABLE OF CONTENTS
1. GENERAL..........................................................................................................................4
2. REFERENCES ..................................................................................................................4
3. DEFINITION ......................................................................................................................5
4. SURFACE PREPARATION ...............................................................................................5
4.1. GENERAL ..............................................................................................................5
4.2. SOLVENT CLEANING ............................................................................................6
4.3. HAND TOOL CLEANING ........................................................................................6
4.4. POWER TOOL CLEANING ....................................................................................6
4.5. TECHNIQUE AND CONSTRAINTS ........................................................................7
5. APPLICATION OF PAINTING............................................................................................7
5.1. CONTROL PAINTING MATERIAL ..........................................................................8
5.2. PRE APPLICATION PROCEDURES ......................................................................8
5.3. MIXING AND THINNING OF PAINT .......................................................................9
5.4. BRUSH APPLICATION.........................................................................................10
5.5. ROLLER APPLICATION .......................................................................................10
5.6. THICKNESS OF COATING ..................................................................................11
5.7. WET FILM THICKNESS .......................................................................................11
5.8. DRY FILM THICKNESS ........................................................................................11
5.9. MULTIPLE COAT APPLICATION .........................................................................11
5.10. DRYING AND CURING ........................................................................................12
6. INSPECTION AND TESTING ..........................................................................................12
6.1. GENERAL ............................................................................................................12
6.2. ENVIRONMENT CHECK ......................................................................................13
6.3. VISUAL FINISHED PAINTING ..............................................................................13
6.4. FILM THICKNESS MEASUREMENT ....................................................................13
6.5. ADHESION TEST .................................................................................................14
7. PAINTING SYSTEM AND COLOURS CODE ..................................................................14
7.1. GENERAL ............................................................................................................14
7.2. APPROVED PAINTING SYSTEMS ......................................................................14
7.3. COLOURS CODE .................................................................................................17
8. PATCHING OR TOUCH-UP AFTER DAMAGE ...............................................................19
9. COATING APPLICATION ................................................................................................20
9.1. GENERAL ............................................................................................................20
Page 2 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 3 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
1. GENERAL
This procedure covers the control of materials and the procedure to be followed in the
course of surface preparation, painting application, inspection and safety requirements
for painting procedure to be used for Block A Gas Development Project Aceh,
Indonesia.
2. REFERENCES
The requirements contained in the latest editions of the following codes and standards
shall form an integral part of this method:
ASTM (American Society for Testing and Materials)
ASTM A-123 Zinc (Hot Galvanized) Coating on Products Fabricated
from Rolled Pressed and Forged Steel Shapes, Plates,
Bars and Strip
ASTM D-714 Method for Evaluating Degree of Blistering of Paints
ASTM D-3359 Standard Test Methods for Measuring Adhesion by
Tape Test
ASTM D-4541 Standard Test Methods for Pull-Off Strength of Coating
Using Portable Adhesion Tester
ASTM D-5162 Standard Practice of Discontinuity (Holiday) Testing of
NonConductive Protective Coating on Metallic Substrate
ASTM A780 Repair of Damaged and Uncoated Areas of Hot-Dip
Galvanized Coatings
BS (British Standard Institute)
BS-381C:1980 Colors for Identification, Coding and Special Purposes
ISO (International Organization for Standardization)
ISO 12944 Paint and Varnish - Corrosion protection of steel
structures by protective paint systems.
ISO-21809 Petroleum and Natural Gas Industries – External
Coatings for Buried of Submerged Pipelines Used in
Pipeline Transportation Systems
ISO 8502-3 Preparation of steel substrates
NACE (National Association of Corrosion Engineers)
TM-01-70/75 Visual Surface Preparation Standards
NACE SP0188 Standard Recommended Practice for Discontinuity
(Holiday) Testing of New Protective Coating on
Conductive Substrate
OSHA (Occupational Safety and Health Cleaning)
RAL (Color Chart Standard)
SSPC (Steel Structure Painting Council)
PA-2 Measurement of Dry Film Thickness
Page 4 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 5 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 6 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
paint be removed by this process. Mill scale, rust, and paint are considered
adherent if they cannot be removed by lifting with a dull putty knife. Before power
tool cleaning, remove visible oil, grease, soluble welding residues, and salts by the
methods outlined in SSPC-SP1.
Methods are described in SSPC-SP3, Power Tool Cleaning, SSPC-SP11, Power
Tool Cleaning to Bare Metal and SSPC-SP15, Commercial Grade Power Tool
Cleaning and typically the level of preparation should be to ISO 8501-1:2007
grade St3-B, C or D. SSPC-SP11 and SSPC-SP15 describe a degree of surface
profile which can be achieved by power tool cleaning
4.5. TECHNIQUE AND CONSTRAINTS
The CONTRACTOR may select one of the below surface preparation methods to
suit the type of work, environmental controls and level of access. Prepared
surfaces shall meet the criteria outlined at each preparation method below.
Prior to commencement of surface preparation, the CONTRACTOR shall uniquely
number each individual section of the structure that is treated separately as one
work lot. Surface preparation requirements below apply to each selected work lot.
A work lot shall be defined as each section of the structure that can be prepared,
dried and coated with the first coat in one continuous operation.
If the surface preparation process exposes surface defects such as rough,
undercut and porous welds, sharp edges, weld spatter, fins, rolled-in slivers,
laminations, pits and craters that may be detrimental to the performance of the
protective coating system, they shall be brought to the attention of the COMPANY
Representative immediately. The COMPANY Representative shall discuss with
the CONTRACTOR how the defects shall be dealt.
Any exposed defects that are repaired by grinding or welding, shall comply with
the specified surface cleanliness and surface profile standards. Any such repairs
shall therefore be conducted prior to final cleaning.
5. APPLICATION OF PAINTING
Coatings shall be uniformly applied without runs, sags, solvent blisters, dry spray or
other blemishes. All blemishes and other irregularities shall be repaired or completely
removed and repainted. Special attention shall be paid to crevices, corners, edges, weld
lines, bolt heads, nuts and small brackets to apply the specified minimum dry film
thickness by brush application if spray will not completely cover all surfaces.
Edges of existing coating shall be feathered towards the substrate minimum 2 inches
prior to over-coating Primers should not be over-coated with the second coat paint until
the specified minimum over-coating time is achieved
Inter-coat contamination shall be minimized by maintaining proper cleanliness and by
applying the intermediate and finish coats within the over-coaing time recommended by
the paint manufacturer. If contaminants are present, they shall be removed before
applying succeeding paints. Contrasting colour shall be used for each coat of paint.
Page 7 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 8 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 9 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
o. All painting materials shall be ready – mixed unless otherwise specified. Where a
2 pack system is supplied by the paint manufacturer, it shall be mixed at the
painting shop or at site in the manner prescribed by the manufacturer, not more
than the amount which can be applied during the stated pot life shall be
prepared.
5.4. BRUSH APPLICATION
Brush application should always be undertaken using an appropriately sized, good
quality synthetic or natural fibre brush compatible with the product being applied.
This application technique is relatively slow and is generally used for painting
small areas for surface tolerant primers, where good penetration of rusty steel
substrates is required. It is particularly suitable for the application of stripe paints
and for painting complex areas where the use of spray methods would lead to
considerable losses due to overspray and associated dry spray problems.
Note that most high build paintings are designed for application by airless spray;
high film build will generally not be achieved by brush application. In general, twice
as many paints will have to be applied by brush to achieve a similar build when
compared to airless spray.
Brush application requires considerable care when applying non-convertible
paintings over one another, e.g. chlorinated rubber over chlorinated rubber, or
vinyl on top of vinyl. In these cases, the solvents in the wet paint readily redissolve
the previously dry bottom paint. Even a mild degree of the brushing out normally
given to top paints will cause pick-up of the previous paint and result in a very poor
finish. Even, light strokes should be used in these circumstances, covering a
particular area with one or two brush strokes, and on no account working the
bristles into the previous paint.
Brush application may be used under the following circumstances :
a. Brush application shall be done in areas which cannot be properly sprayed
and for touch up maintenance where spray application is not practical.
b. Brush shall be of a type and size which permits proper application of paint.
Round or oval brushes are most suitable for irregular surfaces such as bolts,
weld, pitted steel, etc.
c. Wide flat brushes shall be used for large flat areas.
d. Paint shall be worked into all corners and crevices.
e. Rugs and sags or other defects will not be permitted
5.5. ROLLER APPLICATION
Roller application shall be discouraged and shall be subject to the specific
approval of COMPANY. If allowed, it will only be used on relatively large surface
areas provide the first primer paint of paint is applied by brush and its use in
accordance to Paint manufacturer's instructions.
Where application by roller, the paint shall be spread evenly over the entire area
with a minimum practical amount of rolling. A uniform method of application shall
be adopted when painting large areas to minimize paint joint build up. Roller
application shall not be used on irregular surface such as rivets, bolts, crevices,
welds, corners or edges unless otherwise specified and permitted. The rollers and
Page 10 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
paint trays shall be suitable for the purpose intended and shall be maintained in
good order and condition.
Roller application is faster than brush on large, even surfaces and can be used for
the application of most decorative paints. However, control of film thickness is not
easily achieved. As with brush, high film build will generally not be attained. Care
must be taken to choose the correct roller pile length, depending on the type of
paint and degree of roughness of the surface.
Typically, phenolic core rollers should be used, fitted with a smooth to medium pile
roller cover and the roller cover should be pre-washed to remove any loose fibres
prior to use.
5.6. THICKNESS OF COATING
The minimum painting thickness shall be as specified for each paint system. The
maximum thickness in any one application must not exceed that recommended by
the paint manufacturers.
5.7. WET FILM THICKNESS
a. The wet film thickness of each paint and the exact percentage of thinner used
in its application shall be as specified by the paint manufacturer.
b. Operator shall be issued with a film thickness gauge and shall use it to do
frequent checks on the applied wet film to achieve required dry film thickness.
c. WFT and DFT measurements shall comply with ASTM D 4414 and SSPC-PA2
respectively
5.8. DRY FILM THICKNESS
a. The thickness specified are, in every case the minimum required.
b. The painting section or operation shall maintain at the site or shop, a dry film
thickness gauge which has been proven as accurate. DFT gauge shall be
calibrated prior to using.
c. After each painting has cured, its thickness shall be tested by SC QC inspector
and may be tested by inspector in accordance with the standard and
application.
5.9. MULTIPLE COAT APPLICATION
a. Where more than one painting is specified, each painting shall be tinted
differently from the others so that missed areas will be usually apparent.
b. Immediately before each painting after the first (except those prescribed by the
paint manufacturer as ‘wet on wet’) the surface shall be examined to
determine its need for cleaning.
c. If grease or oil is present, it shall be removed by a suitable solvent. Salt and
dirt adhering to the surface shall be removed by scrubbing with a solution of
non-ionic detergent and then pressure – hosed. The same treatment shall be
given to areas from which grease or oil has been removed.
d. Except for painting designate by the paint manufacturers as ‘wet on wet’,
painting shall be applied only under the following conditions:
- The surface has been cleaned and is dry.
Page 11 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 13 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Acceptance Record
Method *10
criteria Item *1
Min.
ASTM D3359: Test Methods for Measuring Form No.1
Classification
Adhesion by Tape Test
4B.
Test panel : Test panel shall be prepared by Vendor / Subcontractor during the
actual painting work at shop / field.
Extent : All painting system work at shop / field.
Frequency : 3 times (Initial, mid, and last term of painting schedule at shop /
field)
7. PAINTING SYSTEM AND COLOURS CODE
7.1. GENERAL
The same Painting manufacturer shall manufacture all protective-painting
materials for each painting system. If there is a requirement to use alternative
supplier products the SUBCONTRACTOR shall inform COMPANY, in writing, of
the proposed supplier change and reasons for the change. COMPANY will
respond to the SUBCONTRACTOR, in writing, of their decision.
The SUBCONTRACTOR shall ensure that the proposed painting system complies
with the Painting System Specification and the requirements of the contract in
regard to the specified system and colour.
7.2. APPROVED PAINTING SYSTEMS
Approval may be given for painting systems not included in ITP for special
application areas where an approved system does not provide adequate
protection. The SUBCONTRACTOR shall submit full details of any proposed
system to the COMPANY for assessment.
If a painting system is not specified in the works, ITP shall be used to select an
appropriate painting system, subject to the approval of the COMPANY prior to
use.
Page 14 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE Date : 07 Mar 2017
AKZONOBEL
Generic Description (International PPG HEMPELS CHUGOKU JOTUN KANSAI PAINT DNT
Paint)
Inorganic zinc silicate
GALBON S-HB
primer (Shall have Interzinc 2265 Sigmazinc 158 Galvosil 15790 Resist 78 ZINCTECT 1500 Zettar OL-HB
100 PZ
minimum 65% Zinc)
Modified Silicone (Shall be Hempel’s
THERMOTECT
able to cured at Ambient Intertherm 50 Sigmatherm 540 Silicone Alu Silicon HR Silver Solvalit V-Silicone HR
600 SC
Temperature) 56914
High Temperature Silicone Hempel’s
THERMOTECT
(Shall be able to cured at Intertherm 50 Sigmatherm 540 Silicone Alu Silicon HR Silver Solvalit V-Silicone HR
600 SC
Ambient Temperature) 56914
Hempathane HS
Aliphatic polyurethane Interthane 990 Sigmadur 550 Unymarine HS Hardtop XP RETAN 6000 V Top HB
55610
Sigmaprime 200
Hempadur Penguard EPOMARINE
Inhibitive epoxy primer Intergard 269 or Sigmacover Univan NT Eponics #20 U/C
15300 Special PRIMER GREY
280
Hempadur Multi KANSAI
PERMAX 3000
Epoxy Glass Flake Interzone 505 Sigmashield 460 Strength GF Marathon SUREGLASS Resilining EP
S
35870 VE
Sigmacover 410
Hempadur Umeguard SX Penguard
High solid epoxy Intergard 475HS or Sigmacover EPOTECT HB Eponics #20 U/C
Mastic 45881 HS Midcoat
620
High solid epoxy (tank Hempadur EPOMARINE
Interline 850 Sigmaguard 720 EPICON T-500 Tankguard HB Eponic PH
lining) 15460 PC 100
Epoxy Phenolic (for Intertherm 228 Sigma Hempadur
Epicon T-800 Epoxy HR - Eponic PH
Insulated Material) HS Phenguard 85671
Epoxy Phenolic (tank Sigma Hempadur Tankguard
Interline 850 Epicon T-800 - Eponic PH
lining) Phenguard 85671 Storage
Sigma Hempadur
Epoxy Novolac (tank lining) Interline 399 - Tankguard Plus - Eponic PH
Novaguard 840 85671
Page 15 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE Date : 07 Mar 2017
Epoxy Novolac ( up to
Hempadur
320oF intermitten Interline 994 - - = - Eponic PH
85671
condition)
High solids, polyamine Hempadur
Interline 984 Sigmacover 630 Epicon T-500 Jotamastic 90 Epotect GX Eponics #20
cured epoxy 15460
High solids, self priming
Hempadur Umeguard SX
epoxy (Surface Tolerant Interseal 670HS Sigmacover 630 Jotamastic 90 Esco NB Epoall HS
Mastic 45881 HS
Epoxy)
Antirust Primer
Hempalin Primer
Alkyd primer Interprime 198 Sigmarine 24 LZI Primer JotaQD Primer Grey or SD ZP Primer QD
12050
Marine Primer
Hempalin JotaQD Top Ftalit or SD
Alkyd enamel (top coat) Interlac 665 Sigmarine 48 Evamarine-I V-Enamel
Enamel 52140 Coat Marine TC
Page 16 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
P&ID Fluid
Fluid Service Color Standard
Service OSHA Color RAL Standard
Definition Reference
Code
DW Demin Water
High Pressure
HC
Condensate
Low Pressure
LC
Condensate
BS 381C: 1980 RAL 5015
Safety Blue Designation Light French
LS Low Pressure Steam (Sky Blue)
Blue 175
PW Potable Water
RW Raw Water
UW Utility Water
Middle Pressure
MC
Condensate
Page 17 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
WW Produced Water
DC Closed Drain
DF Diesel Fuel
DA Atmospheric Drain
AM Amine
AD Amine Drain
GL Glycol
PA Process Air
UA Utility Air
FG Fuel Gas
VN Vents
RAL 8007
HO Hot Oil Brown BS 381C : 1980
Designation Golden (Fawn Brown)
Page 18 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Brown 414
B. STRUCTURAL
Page 20 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 21 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
c. When primers coat are applied, the pigment shall be kept in suspension. The
spray equipment shall have a continuous mixing device.
d. Primer coat shall be applied to all friction, faying surface and flanges.
e. Primer coat shall be applied to within 1 inch of the edge of a field weld bevel or
field splice as applicable. The topcoat(s) shall be applied up to 6 inches from
the field weld bevel.
f. Brushing of primer coat is not recommended and shall be avoided where
possible. COMPANY will determine if brushing may coat an area. The
Manufacturer recommended thinner may be used if brushing must be
performed. The proper size of brush shall be used to ensure that the coating is
worked into all crevices and corner.
g. Application method of primer coat shall be complying with Manufacturer
specification. All edges, corners, fillet welds and other areas where grinding is
not possible and all other sharp edges and protrusions shall be coated with
one additional coat of brush applied primer.
9.3. FINISH COATING
a. Primed surfaces that have been contaminated with dirt, grease, oil or other
foreign material shall be re-cleaned in accordance with Section 5 of this
Specification.
b. The COMPANY standard color code is defined in Table 3. All top coats shall
comply with this color code. Because of variations in colors among different
Manufacturer, CONTRACTOR is required to submit to COMPANY a color
chart for the particular products proposed. COMPANY must approve the
selected colors prior to coating application.
c. Application method of finish coat shall comply with Manufacturer’s
specification including time interval between primer application and finish coat.
Small areas or hard-to-spray areas as determined by COMPANY may be
brushed to the required maximum dry film thickness. When airless spray is
used, the fan pattern shall not exceed 1 foot when sprayed.
9.4. FIELD JOINT COATING
a. The field joint coating shall only be applied to steel and iron surfaces that have
been prepared by proper surface preparation as per Section 5. Prior to surface
preparation by blast cleaning, parent coating shall be shielded if required to
avoid any detrimental effects of this work.
b. The field joint coating shall be compatible with the plant-applied coating and
ensure continuity of corrosion protection.
c. The weld geometry and structure shall be taken into consideration during the
selection of the field joint coating system.
d. The maximum design temperature of field joint coating shall be greater than
the maximum operating temperature of equipment.
e. The temperature of the substrate shall be at least 30C above the dew point.
Pre-heating of substrate is required if the initial temperature of surface is less
than 30C above the dew point.
f. The coating shall be applied symmetrically and with approximately equal
Page 22 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 23 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE Date : 07 Mar 2017
Total
Surface Compan
Minimum Company Dry Touch Up
Operating y
Coating Service Surface Coating Film Coating Final Color
Temperature Coating
Preparation Designation Thickn System
Range System
ess
Up to 320Of Abrasive
Exterior for piping drain line 11 mils, Epoxy Use This
(intermitten Blast to 11 Mils 8B Mnfr Std
from licensor package Novolac System
condition) SSPC-SP-10
Page 24 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 25 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 27 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 28 of 29
BLOCK A GAS DEVELOPMENT Doc. No
PROJECT BLA-P-WP-00-000-ISM-508
Rev. 1
PAINTING PROCEDURE
Date : 07 Mar 2017
Page 29 of 29