BUKR1

TNB Electrical Meter Target Dates (Contractor - Voon Electrical)

No Form Ref. No. Description Original Target Duration Action Remarks


1 PIAT Handover TNB room for Precommissioning Inspection and Testing (PIAT) Q3 2021 1 month PPC/LiZ PIAT defects/comments rectification

2 Contribution Obtain contribution charges amount and pay


charges
3 Equipment Mobilization of equipment and installation 6-18 months LiZ/PPD
delivery
4 Bulk meter Obtain the bulk meter deposit amount and pay
deposit
5 Energization Energization and installation of bulk meter Q1 2023 At least 1 month before Bomba for
T&C
6 Unit meter Obtain the unit meter deposit amount and pay PPD
deposit
7 Unit meter Installation of unit meter PPD At least 1 week (depends on meter
installation delivery)
8

TIME Target Dates (Contractor - Voon Electrical)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Testing & Q1 2023
inspection
2 Handover MDF Q2 2023
room

Street Lighting Target Dates (Contractor - Voon Electrical)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Testing & Q1 2023 After energization of TNB
inspection
2
BUKR1

BOMBA Target Dates (Contractor - Menang Technic)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Bomba inspection Passive & Active inspection April 2023 PPC/LiZ/BEP

IWK Target Dates (Contractor - SYP)

No Form Ref. No. Description Original Target Duration Action Remarks


1 PDC 6 Notice of commencement of sewerage works/septic tank works Q1 2023

2 PDC 7 Notice of intermediate inspection of sewerage works Q1-Q2 2023

3 PDC 8 Notice of final inspection Q2 2023

JKKP Target Dates (Contractor - Shinyou Elevators)

No Form Ref. No. Description Original Target Duration Action Remarks


1 Bomba lift Obtain PMA no. for bomba lift Q3 2022 3 months for 1 nos lift installation 2-4
weeks for 1 nos PMA
2 Passenger lift Obtain PMA no. for passenger lift Q1 2023 1 month for T&C + JKKP inspection

MPK Target Dates (Contractor - )

No Form Ref. No. Description Original Target Duration Action Remarks


1 R&D Road & drainage Q2 2023

2 Landscape Softscape & hardscape Q2 2023


BUKR1

SYABAS Water Reticulation Target Dates (Contractor - How Thong)

No Form Ref. No. Description Original Target Duration Action Remarks


1 QT1 Application for test and inspection TYLIN Target award by September 2021

2 QT2 Response on application for test and inspection of external water reticulation SYABAS Start work by March 2022
system
3 QT3 Material inspection reports TYLIN

4 QT4(a) Hydrostatic pressure test & leakage test report TYLIN/HT

5 QT4(b) Hydrostatic pressure test report for external pipeline complete with ferrule & N/A
communication pipe
6 QT5 Water tightness test report for reservoirs N/A

7 QT6(a) Final joint inspection report for external pipelines TYLIN/HT

8 QT6(b) Final joint inspection report for reservoirs & pump houses N/A

9 QT7 Notification for submission of bank guarantee for defects liability period TYLIN/PPD
(external reticulation system/supply mains)
10 QT8 Support letter from district O&M department for tapping connection works TYLIN

11 EPS16 Application for sterilizing/flushing/water quality SYP

12 EPS16A Notification fof sterilizing/flushing/water quality TYLIN/HT

13 EPS17 Sterilizing/flushing/water quality pipeline report TYLIN/HT

14 EPS17A Forms for sterilizing/flushing for tapping connection works TYLIN/HT

15 QT9 Support letter from district water quality department for sterilization, TYLIN Completion by September 2022
dewatering, flushing and water quality testing activities
16 QT10 Application for handing over external water reticulation system/supply main to TYLIN/PPD Approval by Dec 2022
a water distribution license/services license
17 KA1/1 Handing over of water reticulation system TYLIN/PPD

18 SYA/F1A/Ver2.0 Water meter application form PPD

19 QT11 Acceptance of handing over of external water reticulation system/supply main May 2023 TYLIN/PPD