EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

CaR Nr. 1798-R1


i Sender of Document HYUNDAI-MITSUBISHI-CC1 PMB2
ii Covering Letter No & Date QT1-HDH-PMB2-VT-0167 3647/EVNPMB2-KTAT
iii Doc Ident No & Rev QT1-1-AHS-J-ETG-33-00002 QT1-1-AHS-J-ETG-33-00002
### Title of Document
iv Analog loop logic diagram for Fly Ash Handling System (IFA, Analog loop logic diagram for Fly Ash Handling System
Rev.A) (IFA, Rev.A)
v Date Doc Rec'd by EVN/Consultant 24Aug2022
vi Reviewed by & date completed 08Sep2022
viiDate & No CaRs iss. to PMB2 08Sep2022
Date & No CaRs iss. to Contractor
viii by E&CI Group of EVNPMB2
Contract / Doc Cls/Page CONTRACTOR's
No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES

STATUS AFTER ROUND 1 COMMENTS:


RETURNED FOR CORRECTIONS (RFC)
General Comments
1 Noted and to be closed.

In this regards, the Contractor would like to request the


Owner’s comments based on the technical aspects for each
Refer to 1.1.1.2 deliverables. The other commercial issues, such as the
“Document and Drawings for Construction will only be reviewed for schedule delay caused by TDR, shall be discussed via the
Scope of the
approval after the Technical Design is approved.”. separate offical letter, not in the CaRs.
Project:

2
Please add the title block, table of contents and reference documents. Noted and added.
3 Control logic diagrams in accordance with Standard. A complete write Noted.
up of the operations of the controls shall accompany the logic diagrams.

4 The time setting or expected range for timing blocks should be provided Noted and revised.
on the drawings

5 KKS NO: Please add explain identification of signals Noted.

Detailed Comments

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 1
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

Contract / Doc Cls/Page CONTRACTOR's


No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES
1

Sheet 103 Noted and revised.

Please add time setting for block


2

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 2
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

CaR Nr. 1798-R2


i Sender of Document HYUNDAI-MITSUBISHI-CC1 PMB2 HYUNDAI-MITSUBISHI-CC1
ii Covering Letter No & Date QT1-HDH-PMB2-VT-0167 3647/EVNPMB2-KTAT QT1-HDH-PMB2-VT-1061
iii Doc Ident No & Rev QT1-1-AHS-J-ETG-33-00002 QT1-1-AHS-J-ETG-33-00002 QT1-1-AHS-J-ETG-33-00002
### Title of Document
iv Analog loop logic diagram for Fly Ash Handling System (IFA, Analog loop logic diagram for Fly Ash Handling System Analog loop logic diagram for Fly Ash Handling System (IFA,
Rev.A) (IFA, Rev.A) Rev.A)
vDate Doc Rec'd by EVN/Consultant 24Aug2022 21Jun2023
viReviewed by & date completed 08Sep2022 by Dung, 03Jul2023
vii
Date & No CaRs iss. to PMB2 08Sep2022 03Jul2023
Date & No CaRs iss. to Contractor
viii by E&CI Group of EVNPMB2
Contract / Doc Cls/Page CONTRACTOR's CONTRACTOR's
No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES ROUND 2 COMMENTS ROUND 2 REPLIES

STATUS AFTER ROUND 1 COMMENTS: STATUS AFTER ROUND 2 COMMENTS:


RETURNED FOR CORRECTIONS (RFC) RETURNED FOR CORRECTIONS (RFC)
General Comments General Comments
1 Noted and to be closed.

In this regards, the Contractor would like to request the


Owner’s comments based on the technical aspects for each
Refer to 1.1.1.2 deliverables. The other commercial issues, such as the
“Document and Drawings for Construction will only be reviewed for schedule delay caused by TDR, shall be discussed via the
Scope of the
approval after the Technical Design is approved.”. separate offical letter, not in the CaRs.
Project:

2 Noted.
Please add the title block, table of contents and reference documents. Noted and added.
3 Control logic diagrams in accordance with Standard. A complete write Noted. Noted.
up of the operations of the controls shall accompany the logic diagrams.

4 The time setting or expected range for timing blocks should be provided Noted and revised. Noted.
on the drawings

5 KKS NO: Please add explain identification of signals Noted. Noted.

Detailed Comments Detailed Comments


1 Noted.

Sheet 103 Noted and revised.

Please add time setting for block


2

Sheet 101

Please check again, signal monitoring (Low) and (High)


3

Please add measuring range for output


4 The document QT1-1-AHS-J-ETG-33-00002_Analog loop logic diagram
for Fly Ash Handling System submitted Rev.A and rev.B is different

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 3
NOTES on USING CaRs

3.1

5.1

5.2

ii

iii

iv

vi

vii

viii
NOTES on USING CaRs

PURPOSE:

To allow ALL of the Owner's Engineers comments and ALL of the Contractor's replies to be kept in one
single file in an organised, presentable, and clear way so that the history can be easily traced.

ROUND 1 CaRs:
Following submission by the Contractor of a document/drawing for approval, the Owner's Engineer will
give his first comments on the ROUND 1 CaRs sheet.
(These are automatically transferred to the ROUND 2 CaRs and ROUND 3 CaRs sheets.)
Thereafter, the Contractor replies will be inserted in the "Contractor's Round 1 Replies" column.
On receipt of the Contractor's reply, the Owner's Engineers will decide whether or not Contractor's
reply meets the requirement of the Contract.

ROUND 2 CaRs:

If the Owner's Engineers is not satisfied that the Contractor's reply is in accordance with the Contract,
the Owner's Engineers shall enter his further response on the "ROUND 2 CaRs" sheet ……., etc.

ROUND 3 CaRs:
Shall follow 3.1 and 3.2 above

ISSUES IN DISPUTE:
In the event that the Parties to the Contract cannot close issues using this written CaRs sheet after two
rounds, the issue shall be referred to the monthly Project Meeting for further discussion which may
require the attendance of the Supplier's representative.

If the Parties attending the monthly Project meeting cannot reach agreement, the issue shall be placed
on the Owner's Engineers Engineering Punchlist for checking during erection, commissioning, or
testing or for final resolution before PAC, after PAC/before FAC, or before Contract closure.

NOTES ON COMPLETING THE CaRs:


"Sender of Document": for the Quang Trach 1 TPP Project, this shall be HDH. The Supplier/Sub-
Contractor's name may be added.
"Covering Letter No & Date": this shall be the letter or document transmittal that the Contractor has
sent his document to the Owner's Engineers.
"Doc Ident (Identification) No & Rev": this shall be the number AND REVISION of the Contractor's
document project control number.
"Title of Document": shall, as far as practicable, be EXACTLY the same name as the document sent
by the Contractor
HOWEVER it may be necessary to shorten the Contractor's title.
"Date Doc (Document) Rec'd (Received) by Engineer": shall be the date the document has been
received by PECC1 from Contractor.
"Reviewed by & date completed": here the name (e.g. Hans-U. Rechsteiner) shall be inserted, initials
(HUR), or skill (DSM, CE) of the person(s) making the comments together with the date the comments
were completed.
"Date CaRs issued to Owner": shall be the date the comments are sent to PMB2
"Date CaRs sent to Contractor": shall be the date, provided by PMB2, when PMB2 send its comments
to the Contractor.
"General Comments": shall be comments applicable to all or the majority of the document.
For example: "Pagination (page numbering) shall be added to the document".

"Detailed Comments": shall be specific comments related to the Contractor's document with
sufficient detail to ensure that the Owner's Engineers comment is clear, unambiguous and can be easily
understood by the Contractor.
"Contract / Spec (Specification) Ref (Reference)": shall be a reference to the Contract where the
Owner's Engineers considers that the Contractor is not compliant with the Contract, if applicable
It is NOT mandatory to complete this.
"Doc Cls (Clause)/Page Drg (Drawing) Ref (Reference) etc": shall be a clear reference to the
Contractor's document against which the Owner's Engineers is making its comment so that the
Contractor is clear on what part/point of the document the Owner's Engineers is making his comment.