EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

CaR Nr. 1598-R1


i Sender of Document HYUNDAI-MITSUBISHI-CC1 PMB2
ii Covering Letter No & Date QT1-HDH-PMB2-VT-0137 3185/EVNPMB2-KTAT
iii Doc Ident No & Rev QT1-1-AHS-J-ETG-36-00001 QT1-1-AHS-J-ETG-36-00001
iv
### Title of Document Control system Configuration Drawings for AHS (IFA, Control system Configuration Drawings for AHS (IFA, Rev.A)
Rev.A)
v Date Doc Rec'd by EVN/Consultant 29Jul22
vi Reviewed by & date completed by Dung, 12Aug2022
vii Date & No CaRs is issued to PMB2 12Aug2022
viii Date & No CaRs is issued to Contractor by E&CI Group of EVNPMB2
Contract / Doc Cls/Page CONTRACTOR's
No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES

STATUS AFTER ROUND 1 COMMENTS:


RETURNED FOR CORRECTIONS (RFC)
General Comments
“Document and Drawings for Construction will only be reviewed Noted and to be closed.
for approval after the Technical Design is approved.”.
In this regards, the Contractor would like to request the Owner’s
comments based on the technical aspects for each deliverables. The
other commercial issues, such as the schedule delay caused by TDR,
1
shall be discussed via the separate offical letter, not in the CaRs.
Refer to
1.1.1.1
Scope of the
Project:
These configuration drawings shall be updated to fully reflect Ash Handling System already has been reflected on ‘QT1-0-J-010-36-
ICMS configuration of the whole Plant 00001 Overall Control Configuration Diagram
2

Distributed control system must 20% spare I/O for each card, Noted and revised.
3 20% spare space for each system cabinet and 20% spare
terminal for each marshalling cabinet.
Please add the title/cover, table of contents and reference Noted and revised.
4
documents.
Please add note.

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 1
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

Contract / Doc Cls/Page CONTRACTOR's


No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES
Noted and revised.

The contractor is required clarify connect point of EtherNet/IP


CABLE
Noted and revised.

The contractor is required clarify different connect point to LCP


and field instrument of unit 1, unit 2
3

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 2
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

CaR Nr. 1598-R2


i Sender of Document HYUNDAI-MITSUBISHI-CC1 PMB2 HYUNDAI-MITSUBISHI-CC1
ii Covering Letter No & Date QT1-HDH-PMB2-VT-0137 3185/EVNPMB2-KTAT QT1-HDH-PMB2-VT-1061
iii Doc Ident No & Rev QT1-1-AHS-J-ETG-36-00001 QT1-1-AHS-J-ETG-36-00001 QT1-1-AHS-J-ETG-36-00001
iv
### Title of Document Control system Configuration Drawings for AHS (IFA, Control system Configuration Drawings for AHS (IFA, Rev.A) Control system Configuration Drawings for AHS (IFA,
Rev.A) Rev.B)
v Date Doc Rec'd by EVN/Consultant 29Jul22 21Jun2023
vi Reviewed by & date completed by Dung, 12Aug2022 by Dung, 04Jul2023
vii Date & No CaRs is issued to PMB2 12Aug2022 04Jul2023
viii Date & No CaRs is issued to Contractor by E&CI Group of EVNPMB2
Contract / Doc Cls/Page CONTRACTOR's CONTRACTOR's
No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES ROUND 2 COMMENTS ROUND 2 REPLIES

STATUS AFTER ROUND 1 COMMENTS: STATUS AFTER ROUND 2 COMMENTS:


RETURNED FOR CORRECTIONS (RFC) RETURNED FOR CORRECTIONS (RFC)
General Comments General Comments
“Document and Drawings for Construction will only be reviewed Noted and to be closed.
for approval after the Technical Design is approved.”.
In this regards, the Contractor would like to request the Owner’s
comments based on the technical aspects for each deliverables. The
other commercial issues, such as the schedule delay caused by TDR,
1
shall be discussed via the separate offical letter, not in the CaRs.
Refer to
1.1.1.1
Scope of the
Project:
These configuration drawings shall be updated to fully reflect Ash Handling System already has been reflected on ‘QT1-0-J-010-36- Noted.
ICMS configuration of the whole Plant 00001 Overall Control Configuration Diagram
2

Distributed control system must 20% spare I/O for each card, Noted and revised. Noted.
3 20% spare space for each system cabinet and 20% spare
terminal for each marshalling cabinet.
Please add the title/cover, table of contents and reference Noted and revised. Noted.
4
documents.
Please add note. Please add note.
Noted and revised. Noted.

The contractor is required clarify connect point of EtherNet/IP


CABLE
Noted and revised. Noted.

The contractor is required clarify different connect point to LCP


and field instrument of unit 1, unit 2
3 Please description detail for PLC component specification and
peripheral specification.

4 Please description protocol architecture


5 Dual-redundant fiber optic cable shall be connected to the DCS
system. Please check the line connected.

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 3
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1

Contract / Doc Cls/Page CONTRACTOR's CONTRACTOR's


No Spec Ref Drg Ref etc ROUND 1 COMMENTS ROUND 1 REPLIES ROUND 2 COMMENTS ROUND 2 REPLIES
6

Please check again numbered technical instruction.


7 Please add specification for control cable, instruments cable,
power cable.

EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 4
NOTES on USING CaRs

3.1

5.1

5.2

ii

iii

iv

vi

vii

viii
NOTES on USING CaRs

PURPOSE:

To allow ALL of the Owner's Engineers comments and ALL of the Contractor's replies to be kept in one
single file in an organised, presentable, and clear way so that the history can be easily traced.

ROUND 1 CaRs:
Following submission by the Contractor of a document/drawing for approval, the Owner's Engineer will
give his first comments on the ROUND 1 CaRs sheet.
(These are automatically transferred to the ROUND 2 CaRs and ROUND 3 CaRs sheets.)
Thereafter, the Contractor replies will be inserted in the "Contractor's Round 1 Replies" column.
On receipt of the Contractor's reply, the Owner's Engineers will decide whether or not Contractor's
reply meets the requirement of the Contract.

ROUND 2 CaRs:

If the Owner's Engineers is not satisfied that the Contractor's reply is in accordance with the Contract,
the Owner's Engineers shall enter his further response on the "ROUND 2 CaRs" sheet ……., etc.

ROUND 3 CaRs:
Shall follow 3.1 and 3.2 above

ISSUES IN DISPUTE:
In the event that the Parties to the Contract cannot close issues using this written CaRs sheet after two
rounds, the issue shall be referred to the monthly Project Meeting for further discussion which may
require the attendance of the Supplier's representative.

If the Parties attending the monthly Project meeting cannot reach agreement, the issue shall be placed
on the Owner's Engineers Engineering Punchlist for checking during erection, commissioning, or
testing or for final resolution before PAC, after PAC/before FAC, or before Contract closure.

NOTES ON COMPLETING THE CaRs:


"Sender of Document": for the Quang Trach 1 TPP Project, this shall be HDH. The Supplier/Sub-
Contractor's name may be added.
"Covering Letter No & Date": this shall be the letter or document transmittal that the Contractor has
sent his document to the Owner's Engineers.
"Doc Ident (Identification) No & Rev": this shall be the number AND REVISION of the Contractor's
document project control number.
"Title of Document": shall, as far as practicable, be EXACTLY the same name as the document sent
by the Contractor
HOWEVER it may be necessary to shorten the Contractor's title.
"Date Doc (Document) Rec'd (Received) by Engineer": shall be the date the document has been
received by PECC1 from Contractor.
"Reviewed by & date completed": here the name (e.g. Hans-U. Rechsteiner) shall be inserted, initials
(HUR), or skill (DSM, CE) of the person(s) making the comments together with the date the comments
were completed.
"Date CaRs issued to Owner": shall be the date the comments are sent to PMB2
"Date CaRs sent to Contractor": shall be the date, provided by PMB2, when PMB2 send its comments
to the Contractor.
"General Comments": shall be comments applicable to all or the majority of the document.
For example: "Pagination (page numbering) shall be added to the document".

"Detailed Comments": shall be specific comments related to the Contractor's document with
sufficient detail to ensure that the Owner's Engineers comment is clear, unambiguous and can be easily
understood by the Contractor.
"Contract / Spec (Specification) Ref (Reference)": shall be a reference to the Contract where the
Owner's Engineers considers that the Contractor is not compliant with the Contract, if applicable
It is NOT mandatory to complete this.
"Doc Cls (Clause)/Page Drg (Drawing) Ref (Reference) etc": shall be a clear reference to the
Contractor's document against which the Owner's Engineers is making its comment so that the
Contractor is clear on what part/point of the document the Owner's Engineers is making his comment.