Professional Documents
Culture Documents
Distributed control system must 20% spare I/O for each card, Noted and revised.
3 20% spare space for each system cabinet and 20% spare
terminal for each marshalling cabinet.
Please add the title/cover, table of contents and reference Noted and revised.
4
documents.
Please add note.
EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 1
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1
EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 2
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1
Distributed control system must 20% spare I/O for each card, Noted and revised. Noted.
3 20% spare space for each system cabinet and 20% spare
terminal for each marshalling cabinet.
Please add the title/cover, table of contents and reference Noted and revised. Noted.
4
documents.
Please add note. Please add note.
Noted and revised. Noted.
EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 3
EVNPMB2 QUANG TRACH I TPP PROJECT COMMENTS AND REPLIES PECC1
EVNPMB2/ PECC1's review of the subject document does not relieve the Contractor of his responsibilities under the Contract. 4
NOTES on USING CaRs
3.1
5.1
5.2
ii
iii
iv
vi
vii
viii
NOTES on USING CaRs
PURPOSE:
To allow ALL of the Owner's Engineers comments and ALL of the Contractor's replies to be kept in one
single file in an organised, presentable, and clear way so that the history can be easily traced.
ROUND 1 CaRs:
Following submission by the Contractor of a document/drawing for approval, the Owner's Engineer will
give his first comments on the ROUND 1 CaRs sheet.
(These are automatically transferred to the ROUND 2 CaRs and ROUND 3 CaRs sheets.)
Thereafter, the Contractor replies will be inserted in the "Contractor's Round 1 Replies" column.
On receipt of the Contractor's reply, the Owner's Engineers will decide whether or not Contractor's
reply meets the requirement of the Contract.
ROUND 2 CaRs:
If the Owner's Engineers is not satisfied that the Contractor's reply is in accordance with the Contract,
the Owner's Engineers shall enter his further response on the "ROUND 2 CaRs" sheet ……., etc.
ROUND 3 CaRs:
Shall follow 3.1 and 3.2 above
ISSUES IN DISPUTE:
In the event that the Parties to the Contract cannot close issues using this written CaRs sheet after two
rounds, the issue shall be referred to the monthly Project Meeting for further discussion which may
require the attendance of the Supplier's representative.
If the Parties attending the monthly Project meeting cannot reach agreement, the issue shall be placed
on the Owner's Engineers Engineering Punchlist for checking during erection, commissioning, or
testing or for final resolution before PAC, after PAC/before FAC, or before Contract closure.
"Detailed Comments": shall be specific comments related to the Contractor's document with
sufficient detail to ensure that the Owner's Engineers comment is clear, unambiguous and can be easily
understood by the Contractor.
"Contract / Spec (Specification) Ref (Reference)": shall be a reference to the Contract where the
Owner's Engineers considers that the Contractor is not compliant with the Contract, if applicable
It is NOT mandatory to complete this.
"Doc Cls (Clause)/Page Drg (Drawing) Ref (Reference) etc": shall be a clear reference to the
Contractor's document against which the Owner's Engineers is making its comment so that the
Contractor is clear on what part/point of the document the Owner's Engineers is making his comment.