INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

1 . General inspection status ( see the attached )

2.
2.1 Documents and drawing status

Documents type Total receive Approved Pending


Pipeline 39 32 `7
Material 2 2 0
Tel 20 4 16
Corrosion 16 14 2
PIP 2 2 0

2.2 critical Drawing and documents need urgent approve

No DWG . No Code

1
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

3. Inspection Activities (RFI If applicable)

No RFI No. closed Status Description


1.
2

No Total RFI open Ref. file


1. 2

4. Issues Identified During Today Surveillance

Item Description of the Issue Sub – action


1
2
3

5. Pending Issues followed up

Item Description of the Issue Open Date Status


1

2
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

Not qualification welder make tack weld


6 .Site progress

HDD activity
Line Status Remark
10 Condensate Done between j 350 and j360
4Fuel Gas Done between j 350 and j361
12 Fuel Gas Done between j 350 and j362
24Dry Gas Done between j 350 and j363
24Raw Gas Done between j 350 and j364
FOC cable Done between j 350 and j365
8 Condensate Done between j 350 and j365

3
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

1. PEG . Check welding activity in PEG workshop


1. Checked ID card for welder
2. Checked fit-up ( gap ; cleaning of side bevel , material type , Hilo.)
3. checked quiver temperature
4. check oven temperature and records of electrodes
4. Did VT inspection ( width of cap , reinforcement high, defects)
5. Check temperature and humidity for electrode room .
6. Checked welding material storage condition
7. checked distortion
2 PEG , did VT for 14 joints
3 PEG , review 8 RT films
4 PEG . wetness PWHT activity
5 NB. Review PWHT chart

4
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

7. Photos and Attached Documents

5
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

6
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

PEG , checked Welding activity

PEG . wetness PWHT activity

7
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

PEG . Review RT films

8
INSPECTION DAILY REPORT

Project: GPP-PIPELINE-5000 Project No.: 3800-5000


Location: NB site Report No.: F&C0940-0964- -15
Inspector: Nashaat Date: 22 3, 2023
Contractor/Sub: CPECC/NB

NB. Review PWHT chart

(End of
Report)