o Total: 34 nos.

o Construction sequence
o Establish monitoring checking points and take initial reading
o Carry out predrilling works for each bored pile
o Submit predrilling records to Building Authority upon completion

Construction of proposed bored piles


o Set out bored pile by total station, at least 2 offset reference pins to be installed approx. 2-3m from the
center of pile
o Oscillate down the casing to the level where hard stratum is reached
o Check the position and verticality of the casing after driven down the 1 st section of casing before
connecting casing. (tilting not more than 1:75, offset not more than 75mm)
o Connect 2nd section of casing by welding and oscillate down
o Excavate pile shat by a grab and subsequently by RCD for rock socket
o Water head inside pile shaft be maintained at least 1m or above the existing ground level to prevent
ingress of soil
o Temporary casing at least 2m deeper than excavation
o Reach founding level, carry out Koden test to check the verticality of the pile shaft
o Cleaning of pile base by air-lifting, connect water sample
o Prefabricate reinforcement cage (Fix stiffener steel ring (Y40) inside the main bar at 2m c/c to prevent
distortion of the cage)
o Lift reinforcement cage into pile shaft, splice the main bars by U-bolts
o 75mm concrete cover (fitting circular roller concrete spacers at 4m c/c in four directions.)
o Final air lifting
o Mild steel reservation tubes 3nos. of 50mm dia. for sonic logging test and 3nos. of 150mm dia. for
interface core test
o Pour of concrete by tremie method (45/20D 200mm, slump 133-266)
o 300mm tremie pipe rest on the base of the pile with 100-300mm clearance and with a minimum
immersion of 2m
o Submit as built drawing and piling record to Building Authority

o Carry out post install proof drilling


o Submit BA14 for complement of bored piles