Professional Documents
Culture Documents
Prospectus
CHAPTER
4
Recall that there are three questions in corporate
finance.
The first regards what long-term investments the firm
should make (the capital budgeting question).
The second regards the use of debt (the capital structure
Capital Budgeting for question).
the Levered Firm This chapter considers the nexus of these questions.
4-2 4-3
1
4-4 4-5
The project would be rejected by an all-equity firm: NPV < 0. So, Pearson should accept the project with debt.
4-6 4-7
2
4-8 4-9
Step One: Levered Cash Flows for Pearson Step Two: Calculate rS for Pearson
Since the firm is using $600 of debt, the equity holders only have
to come up with $400 of the initial $1,000.
Thus, CF0 = –$400
B B
Each period, the equity holders must pay interest expense. The To calculate the debt to equity ratio, , start with
after-tax cost of the interest is B×rB×(1 – TC) = $600×.08×(1 – .40) S V
= $28.80
CF3 = $375 – 28.80 CF4 = $500 – 28.80 – 600
CF2 = $250 – 28.80
P V = $943.50 + $63.59 = $1,007.09
CF1 = $125 – 28.80
–$400 $96.20 $221.20 $346.20 –$128.80 B = $600 when V = $1,007.09 so S = $407.09.
0 1 2 3 4
4-10 4-11
Step Three: Valuation for Pearson 4.3 WACC Method for Pearson
Discount the cash flows to equity holders at rS =
11.77%
–$400 $96.20 $221.20 $346.20 –$128.80 To find the value of the project, discount the unlevered
cash flows at the weighted average cost of capital.
0 1 2 3 4 Suppose Pearson’s target debt to equity ratio is 1.50
3
4-12 4-13
4-14 4-15
4
4-16 4-17
4-18 4-19
4.6 APV Example: PV unlevered project 4.6 APV Example: PV depreciation tax shield
Turning our attention to the second term, Turning our attention to the third term,
APV = –$4,873,561.25 + PV unlevered + PV depreciation + PV interest APV = –$4,873,561.25 + $3,095,899 + PV depreciation+ PV interest
project tax shield tax shield tax shield tax shield
PV unlevered is the present value of the unlevered cash flows PV depreciation is the is the present value of the tax savings due to
project discounted at the unlevered cost of capital, 18%. tax shield depreciation discounted at the risk free rate: rf = 4%
PV depreciation
tax shield
5
4-20 4-21
4.6 APV Example: PV interest tax shield 4.6 APV Example: Adding it all up
Turning our attention to the last term, Let’s add the four terms in this equation:
APV = –$4,873,561.25 + $3,095,899 + $1,513,619 + PV interest APV = –Cost + PV unlevered + PV depreciation + PV interest
tax shield project tax shield tax shield
APV = $189,930
4-22 4-23
6
4-24 4-25
4-26 4-27
7
4-28 4-29
So, let’s find PV unlevered and borrow 3/5 of that value. PV = PV unlevered + PV depreciation + PV interest – PV flotation
project levered
project project tax shield tax shield costs
STEP ONE:
5 UCFt
PV unlevered =
project
S (1 + r )
t=1 0
t
4-30 4-31
8
4-32 4-33
Oh by the way, flotation costs are deductible. PV levered = PV unlevered + PV depreciation + PV interest – PV flotation
project project tax shield tax shield costs
3 0.01 3
PV flotation = – (1 – TC) × × × PV unlevered TC×rD× × PV unlevered
0.99 5 5 5
S
costs project project
+
t=1 (1 + rD)t
0.01 3
– (1 – TC) × × × PV unlevered
0.99 5 project
4-34 4-35
$4,547,238.71 $4,547,238.71
PVlevered = = = $4,920,563.66
project 1 – 0.08011 + 0.00424 0.92413
9
4-36 4-37
= –$2,147,662 –$20,875.11
LCF0 = –$2,168,536.92
4-38 4-39
10