RENOVATION PROGRESS REPORT

PROJECT NAME : ZAPORT SERVICES INC. 36TH FLOOR BURGUNDY CORPORATE TOWER
CONTRACTOR : BAUER ENTERPRISE
PROJECT MANAGER : Christopher Rey Rualo Morando
TENANT : ZAPORT SERVICES INC. 36TH FLOOR BURGUNDY CORPORATE TOWER

Progess Summary STATUS


I. Electrical works
Feeder line from LP-Admin 36F/MDP Admin to Units are 100% complete. This units are
1. Feeder of Units Wire laying/pulling (A,B,C,D,E,F,G,H,I,J,K,L,M,N,O,P,Q and R)

All VA Meter for ampere reading of units at EE room are 100% Complete
2. VA Meter Installation

-Units with 100% complete Electrical installation works insdie unit


Unit M
Unit N
Unit O
Unit P

- Units with less than 80% Electrical installation works inside unit
Unit A
Unit B
Unit C
3. Wire Pulling, Unit Panel circuit completion and device Unit D
installations Unit E
Unit F
Unit J
Unit K
Unit L
Unit Q
Unit R
-Units on clearing stage
Unit G
Unit H
Unit I
II. Design Revision/ As built
Units M,N,O and P has final revision and already implemented on the complete installation
Load schedule For units Finalization
Other units are subject to finalization upon completion of device instalaltions.

As built Plan Design will be completed on the Final As built upon Completion of units G,H and I. Included on the final revision is the
load schedule for LP-Admin 36 F and MPD Admin

Notes.
Please see Attached file for the final Load schedule on the accomplished units.