er Recor Farin fetes Rail Vikas Nigam Limited HIGH STRAIN PILE DRIVING ANALYZER TEST REPORT ON RCC PILES FOR CONSTRUCTION OF NEW RAILWAY BRIDGE NEAR TANGRIAPALA ,KEONJHAR AT BRIDGE NO-367 FOR DKB RAILWAY PROJECT. CONTRACTOR: ARSS Infrastructure Projects Ltd. SUBMITTED TO: RAIL VIKAS NIGAM LIMITED JULY-2019 a 7 TESTED BY: a geen ARKITECHNO wa ARKITECHNO Consultants (India) Pvt. Ltd mr ISO 9001-2008 Certified Company & = ~ Plot # N-3/91, IRC Village,Nayapalli, Bhubaneswar-751015,0disha Phone:+91-674-2554205, Telefax:+91-674-2553689 Email: business@arkitechno.com, Web: wwwarkitechno.com Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project PREFACE The Report on conduct of High Strain Pile Driving Analyzer test for determination of load carrying capacity & settlement of bored cast in situ RCC pile for construction Railway Bridge at Bridge-367, on Pile SP-15, Abutment-2 near Brahmanipal vilage Railway Project is presented in this volume. “eoeh Resident Engin Tushar Ranjan Paride MIS SM Consutton's ~ Project Manager PMC, Kendujhaigarh M/S SM Consultants PMC. Kendujharoar ARKI TECHNO CONSULTANTS (INDIA) PvT.tto. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project CONTENTS SLNo Description « INTRODUCTION. * METHODOLOGIES OF PILE DRIVING ANALYZER TEST. * PILE AND TEST PREPARATION. * RESULTS OF PILE DRIVING ANALYZER TEST. « RECOMMENDATIONS REFERENCES APPENDIX-1 PILE DRIVING ANALYZER TEST GRAPHS APPENDIX-2 CALIBRATION CERTIFICATE PHOTOGRAPHS SHOWING EXECUTION OF PILE DRIVING ANALYZER TEST/ this Tushar Ranjan Parige i Project Manager PMC, Kendujhar'.2" M/S SM Consultants PMC. Kendujha-: ARKI TECHNO CONSULTANTS (INDIA) PvT.to. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project INTRODUCTION ARSS Infrastructure Projects Ltd.Bhubaneswar assigned the Pile Driving Analyzer test on test pile at Bridge No-367 for construction Railway Bridge near Tangriapal, Keonjhar Project to M/s ARKITECHNO Consultants (India) Pvt.Ltd Bhubaneswar. M/s ARKITECHNO Consultants (India) Put. Lid Bhubaneswar conducted the test on 24.05.2019 for working pile no-SP-15 for Abutment-2 in presence PMC and dlient. The test was conducted using Pile Driving Analyzer TM (PDA) by obtaining and analyzing records of force and velocity under drop weight impacts. The field results are further analyzed with a signal matching technique (Case Pile Wave Analysis Program— CAPWAP) to refine the soil parameter assumptions, METHODOLOGIES OF PILE DRIVING ANALYZER TEST High strain dynamic testing like a static load test can be used to evaluate pile capacity. The test procedure is standardised as per ASTM D4945-2000. PILE DETAILS (From site) Design load Pile type na Bored cast in situ RCC Pile SP-6 at Bridge no-43 PILE AND TEST PREPARATION The testing is conducted by fixing strain sensors and accelerometers to the sides of the pile at a depth of at least 1.5 x pile diameters from top of pile and then connecting them to the PDA. The Sensors are attached diagonal opposite on the pile shaft at a depth of 1.5m below the top surface. The PDA Is connected to the sensors. After the top face of the pile is prepared to receive the blow from the drop hammer, testing is started by applying blow by the drop hammer & recording data received by the sensors through PDA. Figure: A shows the setup arrangement for the test. RQ nt Engineer (Civil) Tushar Ranjan Paricz if Consultants Project Manager \C, Kendujhargarh M/S SM Consultants PMC. Kendujharaam ARKI TECHNO CONSULTANTS (INDIA) PvT.to. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project Figure: A SKETCH SHOWING SETUP DETAILS FOR DYNAMIC PILE TEST ‘Srgie sne of crane or inp Drop Hammer tor ree tat (1-2% of test load or 7-10% of the dead waght of ne ple whichever is nigher) | ee Stee! netmet (25mm tk.) NOTE: GUIDE FOR HAMMER NOT SHOWN IN SKETCH AND MAY BE FABRICATED AS. “eh S.KRATH : Resident gnginecr (Civil) Tushar Ranjan Paria. MIS SM Consultants Project Manager PMC, Kendujnargarh MIS SM Consultants PMC Kenduihargarh ARKI TECHNO CONSULTANTS (INDIA) PvT.to. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project RESULTS OF PILE DRIVING ANALYZER TEST On completion of field work the data being analyzed by CAPWAP analysis and the output in the form Force- velocity curve and Load Settlement curve plotted and presented in appendix-1 The final results of the Pile driving analyzer test are tabulated below. Test results Parameters Ultimate load ‘Safe load Pile Capacity 596.25 tons 238.5 tons Pile Displacement Pile top 10.99 mm Net Displacement Pile bottom 5.22mm RECOMMENDATION It is concluded from the PDA test that the ultimate load carrying capacity & safe load carrying capacity of the pile tested are 596.25 & 238.5 tons respectively. ‘Sukanta Kumar Jaysingh Jajati Ke. Rout Asst Engineer (Geotechnical) ‘Manager (Geotechnical and Material) ARKI TECHNO Consultants (India) Pvt. Ltd Bhubaneswar Oe ~ 1 SEER 4 (civil) Resid Tushar Ranjan Paria: is SM Consultants Project Manager Pic, Kendujhargar MIS SM Consultants ARKI TECHNO CONSULTANTS (INDIA) PvT.LTo. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project APPENDIX-1 PILE DRIVING ANALYZER TEST GRAPHS ay awe Tushar Ranjan Paina Project Manager M/S SM Consultants PMC, Kendujharaarh ARKI TECHNO CONSULTANTS (INDIA) PvT.to. ARKITECHNO 00524 ae i Beets ae el 3 os s a age ‘sae coon § 2 SOUR SISOY RUS cas eae e382 Boo §ag e = Mossy — — pen eaeg — NH cooot LZ 6002 GavMdvo BIT Vd (eypu) sIUEYTIAUOD OUNORRY zboz-unr-zo. (86:60 610z-Unr-Gz 3801) z MoIG ‘296 JOAIIG'9'dS NO VAd 'b “B6Z-6PLPXVd ‘id 'SSUV PMC, Kendujhargain Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project APPENDIX-2 CALIBRATION CERTIFICATE AND PHOTOGRAPHS SHOWING EXECUTION OF PILE DRIVING ANALYZER TEST AT SITE | : Oa : Tushar Ranjan Paride 5 Cui Project Manager iG, Kendulh M/S SM Consultants Paes PMC, Kendujhargarh ARKI TECHNO CONSULTANTS (INDIA) pvt.to. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project Pile Dynamics, Inc. certifies that the Pile Driving Analyzer®, Model PAX Serial Number. 4149 LA was calibrated on_D2 FEL 201% Using a PDA Calibration Box whose output was calibrated with test equipment traceable to NIST. This certificate is valid for 2 years from above date, ‘ So Wf Tushar Ranjan Paride WIS < . Project Manager PMC, on M/S SM Consultants PMC. Kenduinaeaarh ARKI TECHNO CONSULTANTS (INDIA) PvT.to. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project Tushar Ranjan Paride : ; Project Manager PMC. Kena. M/S SM Consultants ARKITECHNO PMC, Kendujhargarh CONSULTANTS (INDIA) PvT.TO. ARKITECHNO Report on Pile Driving Analyzer Test on Top of Working pile on Construction of Railway Bridge Near Tangriapal .Keonjhar at Bridge No-367 for DKB Railway Project + pe, Tushar Ranjan Fa il) Project Manag... is M/S SM Consulten'= at —— sitesi — ARKI TECHNO CONSULTANTS (INDIA) PvT.LTD. ARKITECHNO aaa ee Mov) BALDY WHKELECHI CoMeArLWLe ( WeKI LECHUO ViO-32\ 49k DKB KSINR bye ou Covenncnor pBuads Yost psuBusbs Yeborys ov BS DUNUA yuDIrs

You might also like