You are on page 1of 5

Application for Extension of time limit

1 Name of contractor Sh Atul Gupta Contractor R/O Lower Dhalpur Kullu


2 Name of work: Design supplying Installation testing and commissioning of
200 KLD STP Based on MMBR Technology I/C sewer network
at Mathi in Tehsil Manali And Distt, Kullu HP (SH;-
Excavation laying jointing and testing of DI Pipe for sewer
network C/O RCC Manehole chamber providing and fixing of
SFRC manehole cover with frame.
Agg No- 161 for 2018-19
3 Amount put to tender 13,33,333 /-Only

4 Date of comm. put to Tender 12.10.2018


5 Period allowed for comp Four month
6 Date of completion as per 12.02.2019
Agreement
7 Date of actual completion 30.09.2019
8 Period for which extension
Has already been given vide Letter no__________________
dated_________upto_________
no__________________________
dated_________upto________
9 Reason on which extension
Is previously granted
10 Period on which extension is
Previously granted
11 Nature of hindrance for which Due to dispute at site for selection of STP at Marhi
Extension is apply with date
On which these are likely to last
12 Total period for which extension 13.02..2019 to 30.09.2019
Now applied for on account of hindrance
Mentioned above
13 Extension of time required on 0 year 6 months 17 Days

Account of extra work


14 Detail of extra work and
The amount involved
15 Proper extension periods on
Account of extra work
16 Total extension of time required 0 year 6 months 17 Days
Part 2nd
1 Name of work Design supplying Installation testing and commissioning
of 200 KLD STP Based on MMBR Technology I/C
sewer network at Mathi in Tehsil Manali And Distt,
Kullu HP (SH;- Excavation laying jointing and testing
of DI Pipe for sewer network C/O RCC Manehole
chamber providing and fixing of SFRC manehole
cover with frame.
2 Name of contractor Sh Atul Gupta Contractor R/O Lower Dhalpur Kullu
3 Acknowledgement of application
From the contractor vide
no________dated_________
4 Recommendation of Assistant Engineer,
Whether the reason given
By the contractor are correct
Extension if any recommended
5 Date of receipt of application
In division office Recommended if contractor dose not claim for
10cc

Assistant Engineer

Nature of hindrance Date of Period for Extension Period


Occurrence, which applied
Hindrance for
Is to last
1 2 3 4 5

______________________________________________________________________
Net Period of which extension Remarks of hindrance occurred and justification
Is recommended/granted for extension recommended/ granted
6 7

The preset progress of the work should be stand and whether the work is likely to be complete
by the date up to which extension has been applies for it, extension for time not recommended
what completion to be levied clause of the agreement
Application for Extension of time limit

1 Name of contractor:- Sh Amar Chand Negi Contractor Vill and PO Raison Kullu
2 Name of work: Providing Sewerage Scheme kullu town (S.H Connectivity of house
connection beyond 6 mtr in Zone in zone No-I Kullu (S.H:- L/J of D.I Pipe ,C/O Man holes cover
Deep) Job No-II Agg No-91 for 2013-14
3 Amount put to tender 3157072 /-Only
4 Date of comm. put to Tender 13-9-2013
5 Period allowed for comp One Year
6 Date of completion as per 12-9-2014
Agreement
7 Date of actual completion WORK IS IN PROGRESS (Tentative on 31-3-2016)
8 Period for which extension
Has already been given vide Letter no__________________
dated_________upto_________
no__________________________
dated_________upto________
9 Reason on which extension
Is previously granted
10 Period on which extension is
Previously granted
11 Nature of hindrance for which Due to dispute at site
Extension is apply with date
On which these are likely to last
12 Total period for which extension 1 year 6 months 19 Days
Now applied for on account of hindrance
Mentioned above
13 Extension of time required on
Account of extra work
14 Detail of extra work and
The amount involved
15 Proper extension periods on
Account of extra work
16 Total extension of time required
Part 2nd
1 Name of work Providing Sewerage Scheme kullu town (S.H Connectivity of house
connection beyond 6 mtr in Zone in zone No-I Kullu (S.H:- L/J of D.I Pipe ,C/O Man holes cover
Deep) Job No-II Agg No-91 for 2013-14

2 Name of contractor Sh Amar Chand Negi Contractor Vill and PO Raison Kullu
3 Acknowledgement of application
From the contractor vide
no________dated_________
4 Recommendation of Assistant Engineer,
Whether the reason given
By the contractor are correct
Extension if any recommended
5 Date of receipt of application
In division office Recommended if contractor dose not claim for
10cc

Assistant Engineer

Nature of hindrance Date of Period for Extension Period


Occurrence, which applied
Hindrance for
Is to last
1 2 3 4 5

______________________________________________________________________
Net Period of which extension Remarks of hindrance occurred and justification
Is recommended/granted for extension recommended/ granted
6 7

The preset progress of the work should be stand and whether the work is likely to be complete
by the date up to which extension has been applies for it, extension for time not recommended
what completion to be levied clause of the agreement

You might also like