Ref: PO 4515005294
2. Lean gas line of under firing system could not be handed over to M/S
Hindustan Steelworks Construction for want of gas shut down and
accordingly the repair job related to lean gas line of Battery 1A could
not be taken up. Going by the operational dynamics and ongoing
repair job of battery 1B, it is expected that some more time will be
required for getting shut down of lean gas line for carrying out the repair
work.
3. Contractor has completed all the jobs, except the jobs for which site
could not be handed over within scheduled time period .
8. GM (COR ) may kindly approve the para 9(I) of the note 1 ante and
recommend the proposal 9(II) for kind approval of CEO DSP.
COR/1A/Final/4515005294/01
Dt: 26.08.2014
T.K.Chaudhury
DGM(COR)
GM(COR)
GMI/C (CO&CC)