If solids get past the shale shaker and into the system, they
are much harder to remove.
Pipe Rotation:
Slide drilling
When drilling high angle wells without rotary steerable tools,
slide drilling with motors is required.
It is important to acknowledge that when slide drilling in high
angle wells cuttings transport will be very poor, even with high
flow rates.
Hole cleaning pills may assist to a certain degree, but solids
removal will not be efficient unless pipe rotation is applied.
Hole Cleaning cont’d
Some hole cleaning rules of thumb.
Minimize hole size where possible to maximize hole cleaning.
Plan for high flow rate (large diameter drill pipe)
Maximize the use of rotary drilling which helps stir up cuttings
bed
Select bit nozzles to balance ROP optimization Vs annular
velocity to clean hole
Avoid high instantaneous ROP to avoid overloading annulus
with cuttings
Conduct wiper trip after prolonged periods of slide drilling
Some hole cleaning rules of Thumb cont’d
Use viscous pills only when essential. Take special care with
lo-Vis pills to maintain high flow rate.
Use Dense Pills only when essential. Limit Volume to avoid
fracturing formation.
Back ream only when essential.
Prior to trip circulate hole clean with rotation. A single bottoms
up is not sufficient.
If Pumps fail, stop drilling until capacity is restored.
If you encounter over pull on trip, stop, circulate and rotate at
least one bottoms up then attempt to pull.
Is the hole talking to you?
Drilling High angle wells in any area benefit from basic good
drilling practices being understood and executed by all drilling
personal involved, regardless of personal opinion!
Every field in the world has specific drilling problems that need
to be addressed when documenting drilling procedures for all
crews. The procedures required to work with field specific
drilling problems need to be agreed by the drilling team and
implemented.
Connection guidelines for High Angle wells
All drillers should be familiar with outlined connection
procedures.
At “kelly down” allow weight to drill-off prior to picking up
drill string.
Wipe at least one stand prior to making connection.
Allow cutting to be circulated above BHA prior to making
connection.
Minimize the period without circulation during connection.
Connection should only be made if hole is in good shape never
make a connection with any over pull.
Connection guidelines for High Angle wells cont’d
If any erratic or high torque is experienced prior to a
connection stop and clean the hole.
If differential sticking is suspected to be a risk; maximize pipe
motion, rotate pipe in slips while making connection.
Confirm circulation prior to moving pipe.
Set slips high enough to allow downward motion after
connection.
Always begin pipe motion downwards once slips are pulled.
Mechanically moving the cuttings bed
Rotation of the drill string after each single that is slid will
enable the Cuttings Bed Mobilizer to agitate cuttings off the
low side of the hole.
Cutting Bed Mobilizer
CBM
Prior to Tripping