Professional Documents
Culture Documents
BEST PRACTICES
1
DRILLING PRACTICES
Prevention of Stuck Pipe During Routine Operations
Reaming and Backreaming
A high risk operation that accounts for a large proportion of stuck pipe incidents.
Solids can be introduced into the circulating system faster than the hole is being cleaned.
2
DRILLING PRACTICES
GENERAL GUIDELINES.
PLANNING
• Have singles ready in case a need arises to work pipe after a connection.
Break-out stand and use singles to cock jars etc.
3
DRILLING PRACTICES
ORGANIZATION
• When drilling or reaming problem area’s have two people at the console.
• Mud loggers report all parameters and report any significant trend changes.
4
DRILLING PRACTICES
PARAMETERS
• Use consistent parameters for reaming operations.
• Circulate hole clean if indicators show the hole loading up during reaming.
• Adjust reaming speed and circulation time if cuttings volume rate is excessive.
• Stop reaming and circulate the hole clean if, torque becomes erratic, rotary
stalls out, cave-in rate increases or torque and pressure readings increase.
5
DRILLING PRACTICES
PARAMETERS CONTINUED
• Prior to heavy reaming, slow rotation <80 rpm should be used to walk pipe past ledges.
• Reaming operations should be conducted with the same flow rate as drilling.
• To reduce chances of sidetracking and damage to drill string keep reaming weight
and speed low.
• Maximum reaming speed should not exceed (as a rule of thumb) four stands an hour.
• Due to large volume of settled cuttings or new cavings introduced into the hole.
It is critical that this material be circulated out of the hole.
6
DRILLING PRACTICES
GENERAL OPERATION
• Follow FIRST ACTIONS for solids induced pack-off.
• When reaming problem formations, the hole may need to be wiped at regular intervals.
• After drilling or reaming down, circulate cuttings above BHA prior to picking up.
• Always try to work the string past a tight spot as a first option.
• Work overpull limit up in stages and ensure free movement in both directions.
7
DRILLING PRACTICES
GENERAL OPERATION CONTINUED
• If a stall out occurs during reaming release the torqued up drill string slowly.
• When back reaming, do not overpull the pipe into the slips to connect the top drive.
• When washing in with a motor in the BHA, rotate the entire drill string at low rpm.
8
DRILLING PRACTICES
Tripping in Deviated Hole
PLANNING
• Record depth of top of BHA while circulating prior to tripping and take extreme care when
the top stabilizer reaches this point and for the following two stands. This is the point the
BHA could encounter a cuttings bed if one exists.
• Where the well inclination is 40o-65o take care as this is the point that cuttings will settle
after avalanching down steeper sections of the well.
9
DRILLING PRACTICES
PARAMETERS
• Initially do not pull more than half the BHA weight or 30,000 lbs..... when POOH.
Used for initial overpulls while tripping out of the hole. Initially do not pull more than half
the BHA weight or 30,000 lbs..... when POOH
• If overpulls exceed 30,000 lbs..... or half the BHA weight then go back down one stand
and circulate bottoms up at full drilling flow rate while reciprocating and rotating the string.
10
DRILLING PRACTICES
GENERAL/OPERATION
• Before tripping circulate the hole using the recommended number of fluid circulation's.
• Reciprocate and rotate the drill string while circulating bottoms up.
• Be aware that the BHA can become stuck in a cuttings bed inside the casing.
• Use paper mud log model of the well and BHA to help identify and forecast problem depths.
11
DRILLING PRACTICES
Connections
12
DRILLING PRACTICES
CONNECTION PROCEDURES
• If erratic or high torque is experienced prior to connection take time to ensure cuttings are
above BHA.
13
DRILLING PRACTICES
• If differential sticking is experienced.
14
DRILLING PRACTICES
Surveying
PLANNING
(3) The amount of circulating and reaming prior to and during surveys.
15
DRILLING PRACTICES
GENERAL/OPERATION
• The amount of presurvey working, reaming or circulating should be discussed with the
toolpusher and company rep prior to drilling the hole section.
• Company rep may recommend more circulating before surveying. He may also want to
drill a few extra feet then pick back up to survey depth. These are the sort of things that
should be discussed at presection meetings.
• Do not take surveys with the kelly completely down or after a connection is made as this
may result in too little space to cock the jars and work the pipe.
• Position pipe to compensate for stretch and compression of the string so that jars can
be properly operated.
16
DRILLING PRACTICES
• Ensure correct handling procedures are in place when using drillpipe screens.
(a) Drilling.
(b) Tripping.
(c) Surveying.
• If dropping a survey prior to tripping. Consider time intervals for surveys if having to
back ream through open hole section.
• Be aware of mud additives like LCM and its possible effect on survey tools.
17
DRILLING PRACTICES
Drilling Parameter Trends
• Monitoring trends will give an indication of the hole condition and provide information
as to whether the hole condition is improving or deteriorating.
• On some rigs trends may be monitored when doing drilling and reaming operations
every fifteen minutes and if significant changes occur then corrective action should be
taken immediately.
18
DRILLING PRACTICES
Running Casing or Liners
• Perform Torque and Drag analysis to predict the limiting friction factor that will still
allow the casing or liner to get to bottom.
• Friction factor can be measured on the last trip out of the well, but is best determined
from experience over the duration of the well.
• If significant deviation is experienced from the predicted down weights then remedial
action can be taken before sticking occurs.
• If overpulls are experienced on the last trip out of the well, consider performing a
wiper trip. This is even more critical if the casing being run is too heavy to be removed
from the hole.
19
DRILLING PRACTICES
Logging
• Logging companies have their own procedures for attempting to free a stuck logging
tool. Procedures may involve opening and closing calipers and other moving parts.
(2) Mechanical sticking of formation test tools and side wall core tools.
* A procedure with recommendations for stripping in over wireline can be found in the
stuck pipe handbook .
20
DRILLING PRACTICES
Coring
• If the rig is fitted with a top drive it is recommended that the core is broken every 90 ft
where differential sticking is a risk.
Well Control
21
DRILLING PRACTICES
Lost Circulation
When intermediate to severe losses occur, cuttings can settle around the BHA and
mechanically stick the pipe. The cuttings act like a packer and can make the losses worse.
• As a rule have enough open hole volume below the bit to accommodate the whole treatment.
KEEP IN MIND:
• Reactive clays may become unstable if exposed to uninhibited fluids.
22
DRILLING PRACTICES
Air and Foam Drilling
Although there is little reliable material available on the subject of stuck pipe while air
drilling. Problems are similar to those encountered in conventional drilling operations.
23
DRILLING PRACTICES
Air and Foam Drilling
24
DRILLING PRACTICES
Air and Foam Drilling
When freeing the pipe always follow good drilling practices.
• In the event of mechanical sticking ALWAYS jar in the opposite direction to the direction
the pipe was travelling when it became stuck.
• In the event of a pack-off, torque made help break up the packed material.
25
DRILLING PRACTICES
Air and Foam Drilling
Good drilling practices for mud still apply with Air or Foam
• The same stuck pipe indicators apply for Air or Foam as with mud.
• If problems are encountered prior to a connection, pick up a single to work the string.
• Try to use a low energy approach with connections. No reaming or back reaming
unless absolutely necessary
• Keep drilling as low energy as possible (low rpm) to prevent pipe lash
degrading the formation integrity.
26
DRILLING PRACTICES
Air and Foam Drilling
Drilling Parameters
Drilling indicators are different from those in mud.
• Differential pressure gauge at the air manifold can be an excellent indicator of what
is going on downhole .
• Trends may occur over a longer period. Two or four hourly printouts on mud loggers
monitors can often identify slow building trends.
27
DRILLING PRACTICES
Air and Foam Drilling
Check Valves
• Drill to a maximum of 500 ft before pulling back to reposition upper check valve.
• Use only flapper type with springs removed to allow access for wireline tools.
• A bit float or check valve must always be run while air or foam drilling.
Air Rates
• Experience indicates the need to keep foam as dry as possible at maximum air rates.
28
DRILLING PRACTICES
Air and Foam Drilling
Casing Design
Cement
• Do not use bentonite in a foam water mix if you have drilled a cement plug. Reaction
with the cement and bentonite will cause mud rings and possible pack-off.
Communications
29
DRILLING PRACTICES
Air and Foam Drilling
Freeing Techniques
Generally different from those used in mud operations and are area specific.
Two cardinal rules apply if sloughing, caving, tight hole, packing-off or mud
rings occur.
(1) Remember you are working with a compressible fluid. If returns are lost do
not bypass the air.
(2) Do not overpull more than 30,000 lbs..... if returns are lost , air or foam
can behave unexpectedly under such conditions.
Overpulling will increase the tightness of the pack-off and make it more
difficult for air to percolate into it and undermine its integrity.
BE PATIENT
30
DRILLING PRACTICES
Drilling with Coiled Tubing
Working the string under pressure is a risk. (Limited number of cycles before failure)
POTENTIAL PROBLEMS
• High circulation pressures.
• Large annulus.
• No rotation.
31
DRILLING PRACTICES
Preventing Drill String Failures
• Handle all tubulars carefully.
• Always fit thread protectors.
• Prevent slip and tong damage by correct use.
• Stab pipe with care to prevent shoulder damage.
• Follow inspection routines and make additional inspections if pipe is subjected to heavy use.
32
DRILLING PRACTICES
Preventing Drill String Failures
BHA Connection Fatigue Prevention
(1) Put the WOB limits used to design the BHA in the drilling program.
(2) Check bending strength ratios (BSR) of the drill collars and try to match.
(4) If pin failures then BSR too high if box failures then raise BSR.
(5) Specify bore back box and stress relieve grooves in all drilling equipment contracts.
(6) Do not allow OD change of more than 2 inches at any one connection.
33
DRILLING PRACTICES
Preventing Drill String Failures
drillpipe Fatigue Prevention
(1) Use heavy-walled drillpipe as transition pipe. Do not run HWDP buckled.
(2) Check stiffness ratio. 5.5 or less for low and less than 3.5 for high complex wells
(3) SR = (Z lower)
(Z upper)
(4) Use correct makeup torque.
(5) Check pipe for slip damage after any rotating of pipe in slips.
(6) In slip stick situations reduce torque limit by 50%.
(7) Cycle the bottom stand of drillpipe out of the string every trip.
(8) Check for shoulder damage before making up.
(9) Minimise dog legs at shallow well depths.
(10) Rotate breaks.
34
DRILLING PRACTICES
Secondary Freeing Procedures
Drilling Fluid and Acid suppliers must be involved in the early planning stage.
Unlike U tubing restrictions do not apply when using pipe release agents.
Any PRA should be spotted within 4 hours of sticking for best results.
If after 16 hours the pill has not been spotted then consider another method.
35
DRILLING PRACTICES
Pipe Release Agents (PRA)
80
70
As a rule of thumb soak for
60 a minimum of 20 hours and
a maximum of 40 hours.
50
%
40
30
20
10
0
0 10 20 30 40 50
SOAKING TIME (hours)
36
DRILLING PRACTICES
Pipe Release Agents (PRA)
SPOTTING A PIPE RELEASE PILL
Plan for how and where the pill will be mixed and start as soon as possible.
Try and design the spacer so that turbulent flow is created across the stuck zone.
To prevent channelling of the PRA into the drilling mud the viscosity value of
the spacer using the 100 rpm reading on a fann VG meter should be higher.
Include spacer and PRA formulation in the mud program document for each well.
37
DRILLING PRACTICES
Pipe Release Agents (PRA)
PRA PROCEDURE
(1) Volume of PRA pill should be 1.5 times larger than the volume of the area in
which the pipe is stuck.
(2) Prepare low YP spacer and check compatibility with mud and PRA pill.
(4) Allow pill to soak until the pipe is free or timed out on effectiveness of pill working.
38
DRILLING PRACTICES
Secondary Freeing Procedures
Acid Pills
39
DRILLING PRACTICES
Secondary Freeing Procedures
(1) Pill should cover zone plus 20 bbls extra in pipe to displace into annulus during soak.
(2) Use spacer ahead of pill if using OBM (Get mud company advice).
(3) Work pipe while pill and spacer are being mixed and maximise overpull while soaking.
40
DRILLING PRACTICES
Free Point Indicators
FREE-POINT DETERMINATION
• If jars are still operating, minimise stretch and torque readings above jars to
necessary calibration runs only.
• Once preliminary free point is established verify torque can be worked down to
back-off point.
41
DRILLING PRACTICES
Free Point Indicators
FREE-POINT DETERMINATION
(1) If jars not firing then rough free-point estimated from stretch calculations prior to
wireline unit arriving on location.
(2) If jars are not stuck then fire up and uncock jars prior to RIH with wireline tool. Do
not go below weight required to recock jar during free point determination and back
off.
(3) Run FPI tool to maximum depth possible if jars are operational. If jars are not
operational 500 ft below estimated free point obtained from stretch calculations. Run
a CCL log to 500 ft above suspected stuck point. Correlate BHA and formation
depths using a paper BHA model.
(4) After CCL begin running FPI stretch tests. Initial stretch test should be in a
known free point in order to obtain baseline reading.
Procedure from stuck pipe handbook
42
DRILLING PRACTICES
Free Point Indicators
FREE-POINT DETERMINATION
(5) Once preliminary free point is determined from stretch test commence torque test
procedure.
(7) Utilise the FPI tool to accurately determine the neutral point.
43
DRILLING PRACTICES
Free Point Indicators
KEEP IN MIND THE FOLLOWING POINTS ABOUT BACK-OFFS
(1) In a high proportion of wells, stuck point has always been joint of pipe below jars.
44
DRILLING PRACTICES
Information Required Before Freeing Operation Starts
RIG READINESS
• Safety- especially potential for falling objects.
• Ton miles on block line.
DRILL STRING INFORMATION
• drillpipe:
• Yield of drillpipe tube.
• Yield of drillpipe tool joint - combined torque and pull calculations .
• Make-up torque used.
• BHA:
• Weight of BHA below jars.
45
DRILLING PRACTICES
Information Required Before Freeing Operation Starts
• Jars:
• Maximum pull while jarring with hydraulic jar.
• Jar firing force envelope.
WELLBORE INFORMATION
• Hole condition.
• Up, down and free rotating weights.
• Drag chart.
46