Professional Documents
Culture Documents
The need to maintain good communications cannot be over emphasised. For situations not
covered by these procedures a plan/flowchart should be drawn up.
Uncommon types of operation should be approached in small steps so that there is always a
way back if a decision turns out to be incorrect. This can be summarised as:
High pressure/high bottom hole temperature (HPHT) wells are defined by the Health
and Safety Executive (HSE) in Continental Shelf Operations Notices (CSON’s) 11 and
59 as being:-
“Exploration and appraisal wells where the undisturbed bottom hole temperature at
prospective reservoir depth or total depth is greater than 300 deg. F and, either the
maximum anticipated pore pressure of any porous formation to be drilled through
exceeds a hydrostatic gradient of 0.8psi/ft or pressure control equipment with a rated
working pressure in excess of 10,000 psig is required.”
As such, a 15k well with a BHST of 280 deg.F would not be classified as HPHT by the
HSE.
However, in exceptional cases a revised low level minimum kick tolerance criterion of
25 bbl for drilling may have to be adopted.
The nature of HPHT operations means that different aspects of pressure control are
continually being recognised. For example:-
(2) Standard use of extended leak-off tests and the results thereof.
Such aspects have not been included in this version of the procedures.
Sections dealing with HPHT wells utilizing both top drives or a kelly have been
included.
PON 13 (formerly CSON 59 - Applications for consent to drill or re-enter high pressure
high bottom hole temperature exploration and appraisal wells), includes policies relating
to information about equipment requited for HPHT wells listed under the following
headings:
Circulating Subs.
(1) When running a core barrel, mud motor, or turbine, a circulating sub should
always be included in the bottom hole assembly.
(2) The circulating sub should be dimensionally checked and also drifted with the
tools that are expected to pass through is, eg:- setting ball, survey barrel, survey
barrel spear socket, etc.
Remark: It is important to ensure that the circulating sub sleeve doesn’t cause
the survey barrel spear socket to unlatch from the barrel when being
pulled back through the circulating sub. A method of getting round
this particular problem is to place the Totco ring in a Stabiliser
directly below the circulating sub so that the top of the barrel sits
above the sub. However, should it not be possible to retrieve the
barrel for whatever reason, the fact that the circulating sub is
straddled renders it inoperable.
(3) The circulating sub should be fitted with seals rated for high temperature.
(4) The HDIS should be drifted with the ball that will be used to shift the sleeve of the
circulating sub.
The temperature limitations of BOP rams and annular preventers are detailed in the
document included as Appendix 10.1.
Elastomers rated to high temperatures are required for the following; (in some cases
‘standard’ elastomers may be sufficiently rated):-
(1) Choke manifold valves and chokes intended to be operated under high pressure to
be fitted with hydraulic actuators.
(3) A 250 psi pressure relief valve fitted to the buffer chamber on the choke manifold
and venting to the overboard lines. This relief device when activated manually
can be used as the relief device (see 2.4 below) which protects the liquid seal in
the mud-gas separator.
The 250 psi setting is high enough to allow sufficient pressure drop
between the buffer chamber and mud-gas separator to avoid premature
actuation of the valve. Conversely, over-pressurisation in the event of
blockage in the vent line and dip tube.
In accordance with HSE Safety Notice 11/90, there must be a means by which the mud-
gas separator can be bypassed and isolated when approaching overload conditions or
blockage. (See also 2.3 above).
An aspect of the mud-gas separator capacity is the rate at which gas can be vented when
the seal is operating at its maximum pressure differential when the liquid seal contains
only associated liquids from the hydrocarbon influx. “A gradient of 0.3 psi/ft should be
assumed to determine the maximum pressure differential”. (Ref:- HSE Safety Notice
11/90).
As such, a device is required to protect the liquid seal, (and thereby also prevent
wellbore fluids being transmitted back to the mud system). The pressure setting of this
device shall be based on the height of the liquid seal (ie:- 18 ft.) multiplied by 0.3 psi/ft.,
(ie:_ 5.4 psi). It is acceptable to design for a higher mud seal gradient provided that
fresh mud is continuously circulated either into the tank (in the case of a dip tube seal),
or into the separator itself (in the case of a U-tube seal).
This bypass can be a fully automated device or simply a pressure induced alarm that
triggers a procedure whereby the bypassing and isolation of the mud-gas separator is
performed manually.
2.5 Instrumentation
The BOP kill line shall be permanently hooked up to the kill pump (cement unit).
At least two valves shall separate the kill line from the cement unit, (in order to
prevent any cement contamination of the kill line). Procedures shall be in place to
flush the surface section of the kill line after every cement job.
(2) Dedicated high pressure (15k) kill manifold and high pressure (15k) kill
(Coflexip) hose.
(3) High pressure kick single assembly to link the kill pump (cement unit) to the
drillstring through the high pressure kill manifold and (Coflexip) hose.
4. Sufficient 15k lBOP’s for the drilling stand, kick single assembly, and for stabbing
etc.
3. PREPARATION
The following is a checklist of items to be actioned at some time prior to entering the
high pressure section. The checklist is divided into three sections, namely:-
(1) Fixed ram high temperature elastomers shall be installed in the BOP.
(2) High temperature seals shall be installed in the kill and choke lines.
(3) The BOP and associated well control equipment shall be pressure tested and
accepted by the rig’s certifying authority. The frequency of such certification
shall be in accordance with the rig’s certifying authority’s requirements.
(4) The kill (cement) pump and manifold shall be pressure tested.
(5) The 15k kick single assembly shall be made up to the appropriate size/
weight/grade of drillpipe and pressure tested.
(6) The drilling stand complete with tested kelly cocks and saver-sub to be made up.
(8) All instruments and recorders shall be checked for calibration and cross checked
for consistency between locations.
(13) The kill (cement) pump remote control on the rig floor shall be function tested.
(21) Weighting-up rate (ie: psi/ft per ‘x’ bbls per hour) to be established.
(22) Additional 15k IBOP’s to be on board (for drilling stand and kick single
assembly). Provision for the rapid installation of the stab-in IBOP should be
provided.
(25) Service company tools (especially the elastometric content) such as jars,
retrievable packers, and electric wireline logging instruments (including pipe-
conveyed) should all be rated for high temperatures.
(26) Endure that all downhole tools have been checked with respect to casing ID’s
(including allowance for tolerances).
(27) Check that the dart for use with the Hydril drop-in sub will pass through all ID’s
of the drillstring (including the IBOP’s) and BHGA components.
(28) Check that in the event of a power failure, the emergency generator has the
capacity to allow well killing operations to continue.
(29) Check/test procedure/system for isolating mud-gas separator and venting wellbore
fluids overboard.
(30) Check/test pressure relief valve system fitted to choke/kill manifold buffer tank for
venting wellbore fluids overboard.
(31) Check/test system that changes direction of wellbore fluids being vented over-
board.
Note: If prolonged top-drive problems necessitate drilling ahead with the kelly, a
circulating elevator should be acquired for tripping operations.
3.2 Personnel
(1) Two mud engineers should be assigned to the rig for the duration of the high
pressure section.
(2) Mud logging crew should not contain any trainees, additional or otherwise.
3.3 Training
(1) All appropriate personnel to be proficient at well control drills (drilling and
tripping) utilising the ‘fast shut-in’ method, strip drills, and H2S drills.
(2) All personnel to have received onsite H2S/BA refresher training.
(3) A pre-spud (or pre-HPHT section) meeting shall be held and minutes recorded.
4.1 General
(1) The automatic MAASP control system shall not be used, and should be
disconnected.
(2) The minimum barytes stock shall be 100 MT and the minimum cement stock shall
be 80 MT. If stocks fall below this level operations will stop, therefore it is usual
to maintain stocks far in excess of these minimum levels. Cement additive stocks
shall also be maintained and if applicable shall include the appropriate level of
weighting material (haematite).
(3) The mud mixing (weighting up rate) capability of the rig should be established.
This information will assist in the planning of certain well control operations and
may even impact on the choice of well control method.
(4) Pressures at slow circulating rates shall be established for the kill pump/kick
single/choke line system.
(5) Circulation shall be broken through the kill and choke lines every twelve hours.
4.2 Drilling
(1) When drilling with a top drive, the composition of the drilling stand, (ie:- number
of drillpipe joints and quantity/position of string IBOP’s), varies between
Operators and Drilling Contractors.
(a) It should always be possible to disconnect the top drive yet leave the
drillstring closed-in on one accessible string IBOP.
Similarly, it should always be possible to disconnect the kelly yet leave the
drillstring closed-in on one accessible string IBOP.
A second IBOP can be installed once the top ;drive/kelly has been removed.
(b) It should always be possible to remove the drilling stand or part thereof yet
leave one accessible string IBOP in place in the drillstring.
(e) It should not be possible for the drillstring to heave into ‘bottom’.
(2) No special equipment that restricts the drillstring ID shall be run in the bottom
hole assembly, with the exceptions of the Totco ring, drilling jar, Hydril drop-in
sub, and nozzles in the bit. This is to limit the restrictions in the drillstring that
would increase the chances of blockage occurring in the case that the pumping of
LlCM and/or cement is required to cure severe losses when entering the reservoir.
(a) The Hydril drop-in sub shall be placed above the heavy-weight drillpipe.
(b) All nozzles shall be the maximum size possible for the particular bit in use.
If the largest nozzles available are less than 18/32”, contact Base. No nozzle
holes shall be blanked off. (The use of nozzles is primarily to protect the
nozzle orifices).
© Teledrift is not classed as having a restrictive bore because of its large flow-
by areas.
(3) The drilling rate should be restricted whereby the ROP does not exceed:
In order to prevent taking more than one influx in the case where the static
overbalance is not present, bottoms-up has to reach surface and be checked for the
presence of influx before stopping the pumps to add another joint of drillpipe, ie:-
before starting to drill a further 30 ft. However, if the pumps have to be stopped,
(to flowcheck for instance), prior to bottoms ups reaching surface, then the
possibility exists to take a second influx. Therefore drilling shall not continue
until bottoms up from the latter moment of stoppage has reached surface. This
ensures that the annulus is influx free and also prevents the possibility of a third
influx if the pumps have to be stopped yet again before the original connection
bottoms up has reached surface.
The 30 ft. value supersedes the 20 ft. value recommended by SIPM in Report EP
89-1500, section 2.3.14.2, item 1.
(4) Where small kick tolerances are involved, gas coming out of cuttings can have a
significant impact. For example:
(5) Drilling shall not continue if dynamic losses of greater than 10 bbls/hr persist.
4.3 Tripping
(1) Under no circumstances shall any string be pulled out of the hole if the hole is not
in a stable condition, ie:- no losses and/or no flow.
However, this does not preclude pulling back a short distance, (eg:- to the shoe), in
order to (for instance), set a cement/LCM plug.
(2) Prior to any trip out of the hole a ten stand wet check trip shall be made (pulled
not pumped) in order to check for overbalance prior to finally coming out of the
hole.
It is not allowable to pull less than ten stands even if the bottom of the drillstring
has already reached the casing shoe.
Refer also to Section 4.10, “Exemptions from HPHT Procedures”, item 4.10.1,
“Omission of Ten Stand Check Trip”.
(3) During the actual trip out of the hole, the drillstring shall be pumped out at least
until the bottom of the drillstring has reached the casing shoe. If a drilling liner
has been installed, then the drillstring shall be pumped out at least until the bottom
of the drillstring has reached the top of the drilling liner. (This is because in
general, annular clearances are smaller).
(4) On check trips, no heavy pills (slugs) shall be pumped. No heavy pills should be
pumped on any trip until the bottom of the drillstring has reached the casing shoe.
(5) If a survey is required using a MSS, drop the survey barrel after the flow check
(negative) that follows circulating bottoms up after the check trip. The survey
barrel shall not be recovered until the bottom of the drillstring has reached the
casing shoe.
On round trips it is usual to recover the survey barrel when the BHA is at surface.
(6) On all trips out of the hole, a Hydril drop-in dart shall be pumped down. Where
applicable, the dart will have to be dropped after retrieving the survey barrel at the
shoe. It shall be checked to be in place by hopefully noting a slight pressure
increase but at least ensuring that sufficient theoretical string contents have been
pumped. Seating can be checked when retrieving the dart at surface.
(7) On all trips in and out of the hole, excessive trip speeds should be avoided in order
to minimise surge and swab pressures to an acceptable level. The reduction in
bottom hole pressure for the drillstring and mud properties in use shall be
calculated.
(8) On all check trips and all trips out of the hole, the Contractor Toolpusher (Night
Toolpusher) and Company Representative shall both be present for at least the first
10 stands pumped/pulled. Furthermore, the contractor Toolpusher (or Night
Toolpusher) shall remain present for tripping out thought the whole open hole
section.
Under no circumstances shall a trip commence prior to the above personnel being
present.
(9) If the hole indicates that swabbing is taking place; but the well is not flowing, then
the drillstring shall be run back to bottom and bottoms up circulated. Note
however that when 75% of the annular contents have been circulated or as soon as
signs of a reduction in mud weight or hydrocarbons are observed, then circulation
shall continue over the choke manifold.
If any doubt exists at any time, bottoms up should be circulated out over the choke
manifold. The riser should then be circulated to clean mud prior to opening the
BOP’s.
(10) All assemblies shall be checked carefully for wellbore contact (wellbore offset
programme), because an undesirable effect of stuck pipe is that swabbing can
occur while jarring.
Notwithstanding the items above, if indications are that the well will swab, the
following options should be considered:-
(2) When check tripping and/or tripping out of the hole, regular flow checks shall be
conducted as follows:-
(b) On a check trip after pulling 10 stands. If the bit will be inside the shoe
when 10 stands have been pulled, flow check both at the shoe and after
pulling the 10th stand.
(e) At a point halfway between the casing shoe and the BOP stack.
(f) At a point just before the top of the BHA (ie:- HWDP) reaches the BOP
stack. Rotating the drillstring during flowchecks should prevent gels
developing and is a valuable anti-stick precaution.
4.5 Coring
When coring:-
(1) Only perforated core-barrels (ie: fitted with check-valve venting) should be used.
(2) The restricted drilling rate as detailed in Section 4.2.3 shall also apply, but can
also be lifted in accordance with the same procedure.
(3) For all sizes, the length of core-barrel run on any one trip shall not exceed 90 ft.
(4) The tripping and flow checking procedures as detailed in Sections 4.3 and 4.4
respectively shall also apply during coring operations.
(5) The first core taken in the reservoir shall be in rotary mode. Thereafter, motor
coring can be used but only in accordance with Section 4.10.2, “Use of
Thrusters/Motors/MWD’s etc. in the HPHT Section”.
(1) The shoe track of the casing set just above the HPHT section and the shoetracks
of all other casings/liners set in the HPHT section shall be magnetised.
(2) It is important to emphasise that overbalance must always be maintained at all
stages whenever cementing a casing/liner especially under static conditions.
(1) On the stump, test the BOP to its rated working pressures, typically 15k for the
rams and failsafes, and 10k for the annular preventers.
(2) Whenever running the BOP, test the wellhead connector to its rated working
pressure, usually 15k, and test the kill and choke lines to their rated working
pressure, typically 15k. In cases of a ‘split’ BOP, test the LMRP connection to
10k.
(3) Whenever subsequently testing the BOP, test the rams and kill and choke lines to
1000 psi above the maximum anticipated closed-in surface pressure for the
appropriate hole section. This pressure will be detailed in the drilling programme,
(because in some cases it may not be possible to cater for the full 1000 psi
margin). Test the annular preventers to 70% of their rated working pressure.
(4) Because the kick-single is an integral part of the well control equipment (in the
HPHT section), it shall be included in the subsequent (14 day) pressure testing of
the BOP from the start of the HPHT section.
The decision when to perform casing tests shall be advised by the Drilling Manager.
Subsequent testing of the seal assembly will be based on the same frequency as the
casing.
Pressure testing of the production casing involves the use of a retrievable packer in order
to isolate/protect:-
It may be necessary to make a scraper run, (for instance across a production packer
interval). However, casing scrapers shall not be ran in the same string as a retrievable
packer.
Severe loading forces are transmitted to the casing via the packer slips during testing,
and so in order to test the integrity of the slip area in the all important upper section of
the casing, it is necessary to perform the shallow test first so that the deeper test
incorporates coverage of the shallow test slip area.
Taking into account casing specifications of a combination string and also the
temperature considerations, it may be possible to use the same packer components for
both the shallow and deep tests. However, the severity of the shallow test may make it
prudent to pull the packer to surface in order to check its condition prior to running all
the way in hole only to find it is unable to perform the deeper test.
Casing wear should be minimised at the design stage by the use of smooth tooljoint
hardfacing, optimum well path trajectory, and film forming muds.
The burst, collapse, axial and triaxial capacities of worn casing are calculated and
compared to the anticipated loads. If worn casing will only have just sufficient strength
to with stand the design loads, casing wear will have to be monitored during drilling.
It is essential that only smooth hardfacing is used and that it is flush with the body of the
tooljoint. Also of prime importance is the need to minimalise drillstring rotary speed. In
addition, tong marks need to be removed from tooljoints. (Reducing the drillstring
rotary speed can have the added benefit of also reducing the ECD).
As mentioned in Section 4.9, a North Seeking Gyro is run in the casing prior to entering
the reservoir. This is an opportune moment in the operation to consider running a
Multi-Fingered Caliper Tool (MFCT). It is important to run the log immediately after
the casing is cemented, ie: before the drillstring is ran/rotated in the casing. Such a log
then forms the baseline to gauge any casing wear that may subsequently occur. Results
from subsequent MFCT logs can also be used to verify design stage predictions.
When the casing is inspected onboard it is important to have the OD as well as the ID
measured in order to aid wall thickness calculations.
One of, or a combination of the following criteria should be used as guidelines for when
to run a baseline MFCT:-
(1) If in accordance with the Casing Design Guide casing wear needs to be monitored.
Results of the casing wear log can be extrapolated and platted against the casing burst
line in order to determine on critical sections where any points of crisis occur.
Drillpipe protectors have been fitted retro-actively in response to metal particles in the
returns. In order to establish a consistent approach to monitoring the quantity of metal
returned, the parameter of grams per 1000 revolutions should be used by dividing the
total weight of metal returned by the total number of revolutions of the drillstring and
recorded (say) every two hours. The use of drillpipe protectors can be planned at the
design stage; their use can also reduce torque and drag.
‘Cansco’ (or similar) non-rotating drillpipe protectors should be fitted in areas of casing
wear derived from. The non-rotating type drillpipe protector overcomes the ‘grinding
wheel syndrome’ associated with the traditional type of drillpipe protector. The
protectors are usually fitted just above the tooljoint.
Remark: One of the reasons why drillpipe protectors are fitted just above the
tooljoint is so that as the tooljoint just passes below the wearbushing, the
protector, (which will still be in the wearbushing), will centralise the tooljoint,
thereby keeping it off the casing wall.
In the Well Planning section of the Deviation document it states that no more than 500
ft. of unsurveyed open hole is permitted. This is especially important if above top
reservoir. However, to be flexible, the (ideal) figure of 500 ft. can be extended at the
discretion of the Rig Superintendent; for instance, in order to coincide with a bit trip
after 600 ft. or thereabouts. As per the instruction from UEOW/35 dated 09 Dec ’92;
future HPHT well programmes shall include a North Seeking Gyro in the casing prior to
entering the reservoir.
Note that it is not within the scope of these procedures to discuss the cost/time
implications of the various methods of borehole surveying.
The use of the Teledrift tool as detailed by flowchart carries two important
qualifications, namely:-
(1) Because Teledrift only measures inclination, the horizontal displacement should be
determined using a single azimuth heading and the Teledrift inclination readings.
This will give the worst case scenatio. The single azimuth heading can be taken
from the last measured value. The tool uncertainty, (11 ft. per 1000 ft. for the
range 0-10 deg.; 13 ft. per 1000 ft. for the range 10-20 deg.), for the particular
depth should then be added to the horizontal displacement. This final
displacement figure becomes the radius of the circle anywhere in which the
position of the bottom of the hole could be located.
Remark: The tool uncertainties quoted above are the current levels of
uncertainty for unknown tool codes for the associated inclinations.
If this estimated ‘circle of uncertainty’ indicates that the target could be missed,
then the situation will have to be assessed in order to decide the most appropriate
safe course of action by which the target can be penetrated; see 4.9.2.
(2) Another important aspect of the Teledrift tool is its limited range to a maximum
inclination of 20 deg. Therefore in cases of higher inclinations an alternative
method of measurement is required; See 4.9.2.
Scientific Drilling Control (SDC) can provide the following magnetic survey probe to
measure inclination and azimuth:-
(1) The magnetic survey probe is ran through a side entry sub using a dedicated
(conductor) wireline unit. Reduced circulation and string reciprocation is still
possible.
(2) The magnetic survey probe diameter is 1.375/1.750 and maximum operating
temperature is 260/600° F respectively.
(3) The probe can be ran in tandem or ran singly in order to provide a surface readout
option. The procedure for running the probe would be as follows:-
(c) Run probe, take survey, then retrieve probe (circulating to avoid swabbing).
These are particular situations where it is acceptable to deviate from the standard HPHT
procedures and details of these are given below. Other circumstances may arise
necessitating other deviations and theses should be agreed by the Drilling
Manager.
It is possible to omit the ten stand check trip, (ref: item 4.3.2) provided that:-
(1) The bottom of the well’s position in the lithology column has been confirmed, (eg:
by core/cuttings samples etc.).
(2) Pore pressure measurements at the top of all exposed reservoirs in the well
indicate that an overbalance exists over the highest pore pressure value with the
riser in place.
(3) The first trip out through the exposed reservoir was preceded by a ten stand check
trip. (This proviso will have been satisfied because the first trip out would have
been to run the formation testing tool, ie:- RFT/FMT).
(4) Offset well data must indicate that stacked reservoirs (varying pore pressure
regimes) are no more than a remote possibility in the lithology column in question.
(1) Drill to the coring point and take the first core as per standard HPHT procedures
detailed herein. If there is no coring point as such, drill sufficiently into the
reservoir to allow the formation pressure to be measured using electric wireline
logging tools. Continue as per steps 3,4 and 5 below.
(2) Cut the first core in the reservoir section as per standard HPHT procedures
detailed herein. Sufficient core must be cut to allow the formation pressure to be
measured using electric wireline logging tools.
(3) Establish the formation pressure using electric wireline logging tools and adjust
the mudweight as necessary to give sufficient trip margin.
(4) Offset well data must indicate that stacked reservoirs (varying pore pressure
regimes) are no more than a remote possibility in the lithology column in question.
The items in this section are included because they are considered to be valuable
learning points.
It is not always possible to achieve and/or maintain the levels of overbalance widely
regarded as being minimal (ie:- 300 psi). In a loss situation it may not be possible to
even cater for a riser margin. Refer to Flowchart 8.10, “Drilling Ahead Without a
Riser Margin - Contingency Plan for Disconnection”.
However, closing the BOP when the riser is attached will entrap the pressure of the
hydrostatic head of mud in the riser provided that the BOP does not subsequently leak.
The decision to drill ahead without a riser margin must be sanctioned by the Head of
Well Operations. Similarly, the Head of Well Operations should be informed whenever
erosion of the overbalance (ie:- change of programmed mudweight) occurs.
There may be instances when narrow well control margins exist, such as minimal
overbalance, and that during such circumstances certain items take on greater
significance. An error of mud weight measurement of 0.005 psi/ft at 18000 ft equates to
90 psi on bottom. As such, when determining mud weights:-
Where narrow well control margins exists, the gradient and volume of formation fluids
being flushed into the well bore tae on greater significance. The implications therefore
of excessive continuous flushing should not be under estimated. As such, the decision to
run the MDT tool must be authorised by the SWE (operations).
Heavy weather is not within the scope of these procedures. However, mention is made
of a particular philosophy whereby a situation can start to escalate out of hand if one
problem (eg: well control) is exacerbated by a further two, as it should be recognised
that the second problem, namely the weather may be about to happen or is happening
already. Therefore, decisions should always take into consideration potential
interference from adverse weather.
5.1 General
Certain items in this section have been included because they are considered to be
valuable learning points:-
(1) It should not be assumed that a well control problem will always fall into a
particular text book category. Bullheading or an issue like exceeding MAASP
have traditionally been seen as last resorts, but options such as these should be
taken in context and not dismissed as a matter of course. The key issue is to
recognise then the text book does not apply and act accordingly.
(2) It should also not be assumed that there will always be sufficient warning (such as
background gas) when in a transition zone. Offset wells prove this not always to
be the case.
(3) When background gas reaches an arbitrary pre-agreed level (for instance 5%), all
work permits shall be withdrawn and the standby boat notified accordingly. It is
also usual to notify all on-shift personnel via the P.A. system of the situation.
(4) The ‘fast shut in’ method will be used throughout the high pressure section. As
such, the valve immediately upstream of each choke shall be kept closed during all
operations after cementing the 9.5/8” casing.
(5) Once a well is closed in following a kick:-
- Standby boat
- Drilling Superintendent
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crews should be mustered and all personnel to be informed of the status.
(6) During well killing operations, in order to prevent valves washing out when
closing them, the choke should be closed first followed by the valve immediately
upstream of the choke. Should this valve fail, the next upstream valve should be
closed. In all cases, the last valve to be closed will be the one furthest upstream,
nearest to the BOP.
(3) Configuration of ram type preventers in the BOP primarily with respect to:-
Although not specified in the note, the position of the kill and choke lines is
important, resulting in an overall configuration as follows:-
- Upper annular
- Lower annular
- Upper pipe rams
- Upper choke lines
- Shear rams
- Upper kill line
- Middle pipe rams
- Lower choke line
- Lower pipe rams
- Lower kill line
5.3 Bullheading.
(1) Due to an extended leak-off test having already established that the mud gradient
used was lower than the fracture propagation gradient, it was known that the
operation would not result in static losses.
(2) The open hole section was very short making it almost certain that the influx
would be squeezed back into the same formation from where it had come.
Therefore, bullheading may be the preferred option for one or more of the following
reasons:-
(1) As long as it is known that the ‘bottom won’t drop out of the hole’.
(2) To avoid getting hydrocarbons to surface, especially in cases where doubts exist
about the contents/volumes in the annulus.
(3) If erratic surface pressures are experienced whereby it may not be possible to
proceed with killing the well conventionally.
(4) If it has not been possible to strip-in all the way to bottom.
(6) If the open hole section is short. However, much depends on the length and
characteristics of the open hole section, if a situation is to be avoided whereby
fluid is being bullheaded higher up the hole above the point where flow may still
be occurring.
During killing operations when landed off on the upper pipe rams, be aware of the
temperature limitation of variable bore rams. This factor may necessitate having to also
close the middle pipe rams - and utilise the lower choke line.
When drilling the high pressure section, a drilling stand fulfilling the minimum
requirements as detailed in Section 4.2, item 1, will be used.
When a kick is first detected, close in the well as soon as possible in the following way:-
(1) Pick up off bottom until the string IBOP is above the rotary table and the upper
pipe rams can be closed below a tool joint. (This position should be determined
before drilling commences and updated as required).
(5) Record time and initial closed-in drillpipe and annulus pressures.
Remark: This isolates the system downstream of the drillstring against the risk
that the closed-in drillpipe pressure exceeds the setting of the mud
pump relief valve, thereby allowing uncontrolled flow through the
drillstring.
(8) Install and test the kick single assembly s detained in steps ‘a’ - ‘e’ below.
Remark: Even though the pressure integrity of the top drive system, (ie: the
standpipe pressure while currently drilling just before the kick),
suggests that the influx may be circulated out with the top drive still in
place, it is nevertheless considered necessary to install the kick single
assembly. This is because possibility exists that failure of the pressure
integrity of the drillstring, (eg.: H2S related stress corrosion cracking),
could result in very high annular pressures being communicated to the
top drive system. Installing the kick single after such an event and in
difficult circumstances is deemed highly undesirable.
(a) Set the string in the slips and close the string IBOP.
(b) Open the upper (remote controlled) IBOP and check the pressure integrity of
the closed string IBOP.
(d) Make-up the kick single assembly and pressure test the system against the
closed string IBOP to the initial closed-in drillpipe pressure plus 3000 psi.
If the flexible hose to the kick single assembly has been disconnected (eg:-
for racking back purposes), pressure test the connection against the plug
valve to 15k.
(9) Check the space out and close the upper pipe rams (using reduced operating
pressure).
(10) Land the drillstring on the upper pipe rams, (if necessary using reduced operating
pressure on the upper annular preventer), and close the ram-locks.
(11) Determine the influx volume and prepare to kill the well in accordance with
Section 6.3, “Circulating Out the Influx”.
- Standby boat
- Drilling Superintendent
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crew should be mustered and all personnel to be informed of the status.
When a kick is first detected, close in the well as soon as possible in the following way:-
(1) Stop rotating and raise the kelly until the lower kelly cock is above the rotary table
and the upper pipe rams can be closed below a tool joint. (This position should be
determined before drilling commences and updated as required).
(5) Record time and initial closed-in drillpipe and annulus pressures.
Remark: This isolates the system downstream of the drillstring against the risk
that the closed-in drillpipe pressure exceeds the setting of the mud
pump relief valve, thereby allowing uncontrolled flow through the
drillstring.
(8) Install and test the kick single assembly as detailed in steps ‘a’ - ‘e’ below:-
(b) Bleed off the pressure downstream of the closed lower kelly cock and check
the pressure integrity of the closed lower kelly cock.
(c) Break the connection above the closed lower kelly cock.
(d) Make-up the kick single assembly and pressure test the system against the
closed lower kelly cock to the initial closed-in drillpipe pressure plus 3000
psi.
If the flexible hose to the kick single assembly has been disconnected (eg:-
for racking back purposes), pressure test the connection against the plug
valve to 15k.
(e) Equalise the pressures and open the lower kelly cock.
(9) Check the space out and close the upper pipe rams (using reduced operating
pressure).
(10) Land the drillstring on the upper pipe rams, (if necessary using reduced operating
pressure on the upper annular preventer), and close the ram-locks.
Note: Remember to increase the operating pressures back to normal again
after landing.
(11) Determine the influx volume and prepare to kill the well as per Section 6.3,
“Circulating Out the Influx”.
- Standby boat
- Drilling Superintendent
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crews should be mustered and all personnel to be informed of the status.
To ensure that the limitations of the surface equipment are not exceeded, especially
when any gas reaches surface, the normal killing procedure must be modified as
follows:-
(1) On the well killing graph mark the point at which theoretical top gas reaches the
wellhead. Apply a safety factor to this point by reducing the time (strokes) by
(say) 25%. Stop the pump and closed in at this point then restart the killing
operation at a suitable displacement rate which will ensure that the mud-gas
separator is operated within its capacity.
Remark: For some rigs, the recommended kill rate detailed on the kill curve may
be acceptable to use for the complete circulation in that it is not too slow
and that it also complies with operating within the capacity of the mud-
gas separator. However, for other rigs, although time is not an issue, to
use the recommended kill rate for the complete circulation may be
undesirable, and hence the pre-requisite above, to ensure that at least
the recommended kill rate is not exceeded from when the gas reaches
the wellhead.
At the point when theoretical top of gas (including safety factor) reaches the wellhead,
the injection of glycol should commence. Once it has been determined that the situation
is outwith the range of hydrates forming, then glycol injection can cease. Thereafter, the
situation should be monitored in case as a result of changes in pressure and/or
temperature, injection becomes necessary again.
(a) The maximum temperature at the choke manifold should not exceed 230°F.
(b) The pressure in the choke manifold buffer chamber should not be allowed to
exceed 250 psi otherwise a relief valve on the buffer chamber will lift and
vent fluids to the overboard lines. (See section 2.3).
(c) The pressure in the mud-gas separator should not be allowed to exceed circa
5 psi, in order to protect the liquid seal, (and thereby also prevent wellbore
fluids being transmitted back to the mud system). (See section 2.4).
If any of these limitations are reached, the well should be closed in and corrective
action taken. Having resolved any problems, the killing operation should be
restarted in accordance with standard procedures
(3) Once the influx has been circulated out and kill mud circulated around, close in
and check that the pressures are zero.
(4) Depending on the reason shy the influx entered the wellbore, and increase in mud
weight is likely to be required. The amount of increase will be governed by
several factors including pore pressure, overbalance including riser and trip
margins, maximum allowable mud weight, and ECD.
Refer also to Section 7.1.1, “Mudweight Reduction in a Loss/Gain Situation”.
(6) Circulate the riser and BOP to the new mud weight in a controlled manner to
address the possibility of trapped gas. (EP 89-1500, section 2.3.4.18 provides a
general approach to coping with trapped gas below closed preventers).
6.4 Kick With Bit Off Bottom - Tripping: Rig With Top Drive
When a kick is first detected, close-in the well as soon as possible in the following way:-
If unable to do so due to heavy backflow, blear the vicinity of all personnel then
make-up the top drive. Continue as below but adjust for the fact that the stab-in
IBOP is not installed. If unable to even make-up the top drive, lose the shear
rams.
(7) Make-up the top drive and pressure test the system against the closed stab-in IBOP
to the initial closed-in annulus pressure plus 3000 psi.
Remark: It may seem anomalous to install the top drive at this point rather than
the kick single - mush however will depend on the closed-in annulus
pressure. The main difference between the situation off bottom
compared to that on bottom is that the plan is to land-off then strip-in
rather than land-off and circulate out the influx; the latter case
requiring the kick single as explained in section 6.1, item 8, Remark.
(8) Equalise the pressures (using the closed-in annulus pressure as a guide) and open
the stab-in IBOP.
(9) Check the space out and close the upper pipe rams (using reduced operating
pressure).
(10) Land the drillstring on the upper pipe rams, (if necessary using reduced operating
pressure on the upper annular preventer), and close the ram-locks.
(11) If the HDIS dart is in place, record time and ‘initial’ drillpipe pressure by slowly
pumping down the drillstring while observing the closed-in annulus pressure. The
‘initial’ drillpipe pressure should be recorded as the HSID valve opens, ie: just as
the annulus pressure begins to rise.
(12) Determine the influx volume and prepare to strip-in. Note however that the
difference between the buoyant string weight in the hole and the upward force
exerted on it by the closed-in pressure will determine the way in which to kill the
well. Remember that once a well is closed in following a kick:-
- Standby boat
- Drilling Superintendent
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crews should be mustered and all personnel to be informed of the status.
6.5 Kick With Bit Off Bottom - Tripping: Rig With Kelly
When a kick is first detected, close-in well as soon as possible in the following way:-
If unable to do so due to heavy backflow, attempt to stab the kelly and make the
connection. Continue as below but adjust for the fact that the stab-in IBOP is not
installed. If unable to even make-up the kelly, close the shear rams.
(7) Install and test the kick single assembly as detailed in steps ‘a’ - ‘c’ below:-
(b) Make-up the kick single assembly and pressure test the system against the
closed lower kelly cock to the initial closed-in annulus pressure plus 3000
psi.
(c) Equalise the pressures (using the closed-in annulus pressure as a guide) and
open the stab-in IBOP.
(8) Check the space out and close the upper pipe rams (using reduced operating
pressure).
(9) Land the drillstring on the upper pipe rams, (if necessary using reduced operating
pressure on the upper annular preventer), and close the ram-locks.
(10) If the HDIS dart is in place, record time and ‘initial’ drillpipe pressure by slowly
pumping down the drillstring while observing the closed-in annulus pressure. The
‘initial’ drillpipe pressure should be recorded as the HSID valve opens, ie: just as
the annulus pressure begins to rise.
(11) Determine the influx volume and prepare to strip-in. Note however that the
difference between the buoyant string weight in the hole and the upward force
exerted on it by the closed-in pressure will determine the way in which to kill the
well. Remember that once a well is closed in following a kick:-
- Standby boat
- Drilling Superintendent
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crews should be mustered and all personnel to be informed of the status.
Methods by which to proceed to kill well when the bit is off bottom are determined by
whether or not the drillstring can be stripped in. This aspect is expanded in the two
explanatory notes below:-
(1) If the upward force (closed-in pressure multiplied by the cross-sectional area of
the closed-end drillpipe) exceeds the buoyant weight of the drillstring it will not be
possible to strip in. Further action will depend on the gas migration rate.
(2) If the buoyant weight of the drillstring exceeds the upward force (closed-in
pressure multiplied by the cross-sectional area of the closed-end drillpipe) exerted
on it by the closed-in drillpipe pressure, the drillstring should be stripped back to
bottom as per Section 6.8, “Stripping-In Procedures”. Furthermore, it should be
noted that:-
(a) Once the bit is on bottom, install the kick single assembly and land-off as
detailed in steps i. to v. below:-
(ii) Make up the kick single assembly and pressure test the system against
the closed kelly cock on the bottom of the kick single to the initial
closed-in drillpipe/annulus pressure plus 3000 psi
If the flexible hose to the kick single assembly has been disconnected
(eg:- for racking back purposes), pressure test the connection against
the plug valve to 15k.
(iv) Check the space out and close the upper pipe rams (using reduced
operating pressure).
(v) Land the drillstring on the upper pipe rams and close the ram-locks.
Circulate out the gas (using the original mud weight) from where the bit is
positioned, maintaining constant standpipe pressure. Thereafter, continue
stripping in until gas reaches surface again or the bit reaches bottom.
Once the bit is on bottom, install the kick single assembly and land off as
detailed above in Section 6.6.2a, steps i. to v.
(1) Close the shear rams, and close the (shear) ram-locks.
- Standby boat
- Drilling Superintendent)
- Rig Manager
The OIM will also have responsibilities about whom to inform (eg:-
coastguard) in accordance with his own emergency procedures.
(c) Crews should be mustered and all personnel to be informed of the status.
- Stripping in, taking into account heave, pressure, buoyant weight of BHA in
riser, etc.
- Volumetric method
- Bullheading
From the closed-in pressure readings measured against time, the migration rate can
be estimated as follows:-
If the estimated migration rate is less than 1000 ft/hr, then the well may be
bullheaded dead after confirmation with Base.
If the estimated migration rate is more than 1000 ft/hr, the gas will be allowed to
migrate to surface.
= 15 psi
For each barrel of mud bled off, an additional 15 psi should be applied and
maintained on top of the closed-in pressure.
Once the gas reaches surface the reverse applies. For every 15 psi pressure bled
off, 1 bbl of mud should be pumped into the well to compensate for the reduction
in pressure.
Rig specific stripping procedures should be in place as part of the Drilling Contractor’s
own standard operating procedures. Check that there are agreed:-
This section can also apply to combined losses and gains situations.
Even given a formation strength at the deep intermediate casing shoe that is capable of
containing the expected overpressures, it is still possible that fluid losses occur.
Losses could start while drilling through a weak zone between the formation at the
casing shoe and the objective.
Once drilling through the objective, the overbalance over the formation pressure will
increase with depth, due to the large difference between the mud and formation fluid
gradients. This increasing overbalance could subsequently be the cause of losses deeper
in the well.
Losses can also be induced by surge pressures; mainly when running in and especially
when using highly viscous, heavy muds. If losses occur in this situation, it is difficult to
establish where the loss zone is, and, depending on the position of the drillstring in the
hole, it may be difficult to place curing material across the loss zone.
Drilling ahead shall not continue if dynamic losses of greater than 10 bbl/hr persist.
(1) Where the ECD is a contributing factor to a loss situation, experience has shown
that drillstring rotation can cause the ECD to increase, thereby exacerbating the
situation.
For the same reason, this exercise should be repeated at the shoe. Being at the
shoe is seen as the best compromise in case losses are actually induced; the
drillstring is not in open hole, and the bit should be close enough to bottom for the
placement of cement.
Planned reductions of mud weight shall be carried out in stages in a controlled manner,
and shall include a short trip for each stage to confirm that sufficient overbalance exists.
For each stage, the (static) bottom hole pressure that existed with the mud weight being
circulated out shall be maintained when circulating in the new (lower) mud weight by
taking returns through the choke. While maintaining bottom hole pressure, dynamic
losses should be avoided and much will depend on the circulating rate (ECD) and
pressure drop across a fully open choke when determining appropriate back pressure (if
any).
It may be necessary at the end of each stage prior to commencing the short trip to
observe the well closed-in in order to check for any pressure build-up. If pressure is
registered it could be due to supercharging. To ascertain if this is so, the pressure should
be bled back (possibly to zero) by ensuring that an equivalent safe (manageable) influx
volume of say 5 bbls. Is not exceeded. This volume should then be circulated out again
maintaining bottom hole pressure yet avoidi8ng dynamic losses. The influx can be
checked at surface for the presence of hydrocarbons. This process of bleeding back and
circulating out the volume may have to be repeated several times to reduce to zero any
pressure due to supercharging. If it becomes apparent that the pressure is caused by
being underbalanced, the well shall be killed.
A situation involving losses may necessitate the performing of a cement squeeze through
the bit. A combination of fluids to spot may comprise:-
As an option an LCM pill can be included after the mud, but this has to be taken into
account when spotting the fluids.
An outline of the method (for a short open hole section) would be as follows.
Appropriate variations may be required dependent on the rate of losses incurred before
and during execution:-
(1) With the bit inside the shoe, spot the fluids in such a way that the pipe is pulled
back further while the cement is filling the void below the bit.
(2) Pull back an additional stand (say) to ensure that the bit is above the top of the
cement.
(3) Make sure the drillstring bore is clean by circulating partial or even full string
contents at a high rate. The resultant ECD during this circulation will provide
some squeeze pressure and therefore the rate of circulation may have to be
adjusted to suit.
Remark: It is important to remove all the cement from the drillstring before
closing in and applying squeeze pressure in case the string becomes
plugged as a result.
(4) Close-in on the upper annular preventer: (ideally the annulus below the BOP
should be full).
Note: Any cement that has strayed above the bit needs to be circulated out
conventionally while keeping the string moving. Again, the resultant
ECD during this circulation will provide some squeeze pressure and
therefore the rate of circulation may have to be adjusted to suit.
Additional squeeze pressure can be achieved by circulating over the
choke.
(5) Apply squeeze pressure. The annulus pressure can be monitored via the kill or
choke line in order to monitor the squeezing process.
(6) Check for losses and /or imbalance, then open up well. Ensure that the drillstring
is kept free and clear by movement/circulation.
In a long open hole section or in a situation of sudden severe losses it may not be
possible to pull the bit back to the shoe. Again though, cement should be spotted in
such a way that as the pipe is pulled back cement fills the void below the bit.
In all cases where a well control situation in deteriorating, the Emergency Response
Procedures (which recognise the OIM as being the ultimate level of responsibility on the
rig) must be adhered to.
(1) A well should always be closed-in initially using the upper annular preventer. The
lower kill line should not be used to take returns and the inner and outer failsafe
valves on the lower kill line should be kept closed. This will allow the bottom
(pipe) rams to be a last line of defense, whereby if they are closed, any leak that
may have developed in the choke line will be isolated. (See overall stack
configuration in section 5.2.3).
In the event that this occurs, a decision will be made in conjunction with Base
regarding the options, including:-
(b) Continuing well killing operations utilising the lower kill line.
(Although not recommended, the well kill could be very near to completion
of phase 3 or 4).
(c) Pump cement down the drillpipe with returns via the lower kill line.
(2) At some point it may become necessary due to loss of control to abandon the
situation and move the rig off the well. The exact method of how the situation is
abandoned will depend upon the circumstances whereby loss of control occurred,
but well containment should obviously take precedence. In b terms:-
(c) The rig pulled in an optional direction (ie: upwind/up-current) off location
using the anchors.
(d) In consultation with the OIM consider further/total evacuation of the rig.
Note: In order to give the shear rams the best possible chance of shearing the
pipe, regulated pressure to the shear rams should be increased to the
full 3000 psi accumulator pressure (by opening the by pass valve). On
some systems the act of closing the shear rams may automatically apply
the full unregulated accumulator pressure. The remote panels at the
evacuation points should be checked to determine whether they are able
to operate the shear rams on full unregulated accumulator pressure.
Consider for example the following situation:- if the lower pipe rams are closed to
protect a failed choke line and then the pipe is sheared, the drillstring will slip through
the lower pipe rams and the well will blow out through the failed choke line. In such an
instance it may be better to land off on the lower pipe rams, close the middle pipe rams,
pull string tension with the tooljoint against the bottom of the close middle pipe rams,
then close the shear rams.
The message being conveyed is that there may be preferable ways of abandoning
the situation. Remember, closing the shear rams does not automatically secure the
well.
Bear in mind that with the drillstring set in the slips on a heaving rig, the mechanism
(especially if not circulating) for swabbing exists. Developing procedures to cover
every possible scenario is virtually impossible. As such, the following precautions are
listed and can be applied wherever necessary:-
(3) If unable to circulate, continuously monitor the fluid level in the drillstring and
annulus.
(4) Consider closing-in the well with the drillstring hung off in the BOP, and monitor
closed-in pressures.
(5) The Company DSC should ensure that all relevant personnel are briefed on the
potential for well control problems, and that the drillfloor is manned constantly by
personnel capable of taking the appropriate action.
(6) Especially after completing an extended period of repairs, circulate the drillstring
plus annulus volume to check for hydrocarbons.
Note 1 By filling the hole with a measured amount of light fluid, and estimation of
the formation strength can be made and used to possibly reduce the mud
gradient, depending on formation pressures. Water, KCL-premix or oil can
be used as light fluid, depending on the mud system in use.
Note 2 After filling up the annulus with light fluid, the well could be flowing because
of the loss of overbalance due to the lighter column, or due to the influx that
entered the well before the annulus was filled up.
Note 3 By squeezing LCM down the annulus the light fluid below the BOP’s will be
displaced into the loss zone followed by the LCM.
Note 4 In case the losses cannot be reduced by LCM, a cement squeeze should be
tried. To increase the chances of success the string should be as close as
possible to the loss zone, hence strip in to the casing shoe. If there are any
indications that gas is migrating up, contamination of the complete annulus
should be avoided by squeezing mud down the annulus at a rate equivalent to
the migration rate.
Note 5 If the loss zone is below the producing zone, any influx that may have entered
the well will be squeezed away and given that the losses are cured, full
balance has been restored.
Note 6 If the well is still presurised after the losses are cured, this could mean that
there is still an influx in the well bore ie. The loss zone was above the
producing zone. To remove this influx from the well, the string needs to be
stripped in to below the influx to circulate the influx out.