Daily Activity Report (PT.

JURONG ENGINEERING LESTARI)


Project : LOTTE INDONESIA NEW ETHYLENE COMPLEX Project Contractor No : - Work Work stop
Working
Discipline : UNDERGROUND PIPING WORK Date : July 25, 2023 Time (H) From To Hour Reason

Subcontractor : PT. JURONG ENGINEERING LESTARI Report No : 7:00 18:00 1:00 Rest = 1H

Work Activity : FIT-UP, WELDING, WRAPPING & HOLIDAY TEST, POST Today Work : 10:00 Hour
INDICATOR VALVE INSTALLATION AND WRAPPING

1. WORK DESCRIPTION

TODAY / DONE TOMORROW / PLAN (MONDAY)


1. FIT-UP 1. FIT-UP
1U11-FW-00003-03 Joint No. 02-1A 6 " 1U41-OWS-90404-01 Joint No. 20 4 "
1U21-OWS-90212-01 Joint No. 13 6 " 1U81-OWS-90805-03 Joint No. 1 6 "
1U21-OWS-90212-03 Joint No. 13 4 " 1U81-OWS-90805-03 Joint No. 2 6 "
1U41-FW-00012-01 Joint No. 05 16 " 1U81-OWS-90805-03 Joint No. 5 6 "
1U41-ISW-60007-01 Joint No. 06 46 " 1U81-OWS-90805-03 Joint No. 7 6 "
1U51-FW-00108-01 Joint No. 01-1' 6 " 1U81-OWS-90805-03 Joint No. 11 6 "
1U51-FW-00108-01 Joint No. 11 6 " 1U81-OWS-90805-03 Joint No. 12 6 "
1U61-OWS-90604-02 Joint No. 01A 6 " 1U81-OWS-90805-04 Joint No. 14 6 "
1U81-OWS-90805-05 Joint No. 17 6 "
2. WELDING 1U81-OWS-90805-06 Joint No. 18 6 "
1U11-FW-00003-03 Joint No. 02 6 "
1U11-FW-00003-03 Joint No. 02-1A 6 " 2. WELDING
1U31-OWS-90303-01 Joint No. 06 4 " 1U11-FW-00003-03 Joint No. 02-1A 6 "
1U41-ISW-50001-01 Joint No. 10 30 " 1U21-OWS-90212-01 Joint No. 13 6 "
1U61-OWS-90604-02 Joint No. 01A 6 " 1U21-OWS-90212-03 Joint No. 13 4 "
1U41-FW-00012-01 Joint No. 05 16 "
3. WRAPPING 1U41-ISW-60007-01 Joint No. 06 46 "
1U31-CWR-90012-01 Joint No. 12 24 " 1U51-FW-00108-01 Joint No. 01-1' 6 "
1U31-CWR-90012-01 Joint No. 18 24 " 1U51-FW-00108-01 Joint No. 11 6 "
1U31-CWR-90012-02 Joint No. 10 20 " 1U61-OWS-90604-02 Joint No. 01A 6 "
1U31-CWR-90012-02 Joint No. 14 20 " 1U61-OWS-90605-02 Joint No. 10 6 "
1U31-CWR-90012-02 Joint No. 17-1 20 "
1U31-CWR-90012-02 Joint No. 18 20 " 3. WRAPPIING
1U31-OWS-90303-01 Joint No. 06 4 " 1U21-OWS-20052-01 Joint No. 03 2 "
1U61-TRIM-MH601V1-01 Joint No. 01 4 " 1U21-OWS-20052-01 Joint No. 06 4 "
1U61-TRIM-MH601V1-01 Joint No. 02 4 " 1U21-OWS-20052-01 Joint No. 07 4 "
1U61-TRIM-MH601V1-01 Joint No. 03 4 " 1U21-TRIM-MH201V1-01 Joint No. 04 4 "
1U61-TRIM-MH601V1-01 Joint No. 04 4 " 1U21-TRIM-MH204V1-01 Joint No. 01 4 "
1U61-TRIM-MH601V1-01 Joint No. 05 4 " 1U21-TRIM-MH204V1-01 Joint No. 02 4 "
1U21-TRIM-MH204V1-01 Joint No. 05 4 "
1U21-TRIM-MH205V1-01 Joint No. 02 4 "
1U21-TRIM-MH205V1-01 Joint No. 05 4 "
1U21-TRIM-MH206V1-01 Joint No. 05 4 "
1U31-FW-00017-01 Joint No. 02 16 "
1U41-SWR-50003-01 Joint No. 01 30 "
1U41-TRIM-MH401V1-01 Joint No. 03 4 "
1U61-FW-00001-01 Joint No. 05 6 "
1U61-OWS-90604-01 Joint No. 11 4 "
1U61-OWS-90604-01 Joint No. 12 4 "
1U61-OWS-90604-01 Joint No. 13 4 "
1U61-OWS-90604-01 Joint No. 14 4 "
1U61-OWS-90604-01 Joint No. 15 4 "
1U61-OWS-90604-02 Joint No. 07 6 "
1U61-OWS-90604-02 Joint No. 10 6 "
1U61-OWS-90604-02 Joint No. 11 6 "
1U61-OWS-90604-02 Joint No. 12 6 "
1U61-OWS-90604-02 Joint No. 13 6 "
1U61-TRIM-MH601V1-01 Joint No. 03 4 "
1U61-TRIM-MH602V1-01 Joint No. 05 4 "

1.DIRECT MANPOWER (MD)

Korea Local Non- Foreigner Previ. Today Accum. Korea Local Non- Foreigner Previ. Today Accum.
No Direct Local No Direct Local
M F M F M F M F M F M F M F M F M F M F M F M F M F M F

1 Foreman Scaffolder 1 287 - 1 - 288 - 15 - -

2 Foreman Welder 1 335 - 1 - 336 - 16 - -

3 Foreman Pipe Fitter 1 509 - 1 - 510 - 17 - -

4 Pipe Fitter 23 7,782 - 23 - 7,805 - 18 - -

5 Rigger 4 1,671 - 4 - 1,675 - 19 - -

6 Scaffolder 8 2,313 - 8 - 2,321 - 20 - -

7 Material Control 2 601 - 2 - 603 - 21 - -

8 Warehouse 2 602 - 2 - 604 - 22 - -

9 Electrician 2 593 - 2 - 595 - 23 - -

10 Welder 10 5,272 - 10 - 5,282 - 24 - -

11 General Worker 20 7,540 - 20 - 7,560 - 25 -

12 28 -

13 - - 74 - - - - - 27,505 - 74 - 27,579 -

14 TOTAL - 74 - - 27,505 74 27,579

3. INDIRECT MANPOWER (MD)


Non- Non-
Korea Local Local Foreigner Previ. Today Accum. Korea Local Local Foreigner Previ. Today Accum.
No Indirect No Indirect
M F M F M F M F M F M F M F M F M F M F M F M F M F M F

1 Site Manager 1 - 284 - 1 - 285 15 Operator Crawler Crane - 201 - - - 201 -

2 Construction Manager 1 272 - 1 - 273 - 16 Crew Crawler Crane - 200 - - - 200 -

3 HSE Coordinator 1 232 - 1 - 233 - 17 Operator TMC 1 265 - 1 - 266 -

4 Engineer 3 468 - 3 - 471 - 18 Surveyor 3 520 - 3 - 523 -

5 HR Coordinator 1 287 - 1 - 288 - 19 Operator Mobile Crane 50T 1 250 - 1 - 251 -

6 Material Control Supervisor 1 292 - 1 - 293 - 20 Driver 1 236 - 1 - 237 -

7 QC Coordinator 1 280 - 1 - 281 - 21 Permit Holder 1 - 218 - 1 - 219

8 General Affair 1 291 - 1 - 292 - 22 QC Administration 3 - 471 - 3 - 474

9 Piping Supervisor 2 517 - 2 - 519 - 23 Painter - 1,471 - - - 1,471 -

10 QC Inspector 4 804 - 4 - 808 - 24 Operator Hydraulic Crane - 68 - - - 68 -

11 Paramedic 1 - 266 - 1 - 267 26 Crew Hydraulic Crane - 68 - - - 68 -

12 HSE Supervisor 2 113 - 2 - 115 -

13 Watcher/BKO 2 166 - 2 - 168 - SUB - TOTAL - - 25 7 - - - - 7,001 1,492 25 7 7,026 1,499

14 Finance Officer 1 253 - 1 254 TOTAL - 32 - - 8,493 32 8,525

4. EQUIPMENT (ED)
No Item Capacity Unit Previ. Today Accum. No Item Capacity Unit Preavi Today Accum.
1 CRAWLER CRANE 180T Unit 198 0 198 11 MOBILE CRANE 200 TON 60 0 60
2 TRUCK MOUNTER CRANE 10T Unit 285 1 286 12
3 HILUX - PICKUP 1 Unit 300 1 301 13
4 SUMP PUMP 2 INCH 1025 2 1,027 14
5 GENERATOR SET 25 KVA 445 1 446 15
6 GENERATOR SET 150 KVA 309 1 310 16
7 DRY OVEN 50 KG 544 2 546 17
8 DRY OVEN 100 KG 401 2 403 18
9 GENERATOR SET 300 KVA 291 1 292
Total 4,100 12 4,112
10 MOBILE CRANE 50 TON 242 1 243

5. QUANTITY

NO Description Total Quantity Unit Previous Today Acum Plan Tomorrow Progress % Remarks

AREA 101 / 6" ; AREA 102 / 4" , 6" ; AREA 104 / 16", 46" ; AREA 105 / 6" ; AREA 106 /
1 FIT UP 39,092 DI 40,475 96 40,571 58 103.78% 6"
CW 9,059 DI 9,444 0 9,444 0 104.25%
SW 13,456 DI 12,824 46 12,870 0 95.65%
FW 5,154 DI 4,762 34 4,796 0 93.05%
OTHER 11,423 DI 13,445 16 13,461 58 117.84%

2 WELDING 39,092 DI 39,302 52 39,354 72 100.67% AREA 101 / 6" ; AREA 103 / 4" ; AREA 104 / 30" ; AREA 106 / 6"

CW 9,059 DI 9,363 0 9,363 0 103.35%


SW 13,456 DI 12,764 30 12,794 30 95.08%
FW 5,154 DI 4,572 12 4,584 0 88.94%
OTHER 11,423 DI 12,603 10 12,613 42 110.42%

3 WRAPPING 39,092 DI 30,653 152 30,805 152 78.80% AREA 103 / 4", 20", 24" ; AREA 106 / 4"

4 GLASS FLAKE LINING 13,456 DI 12,480 0 12,480 108 92.75%

TOTAL

Prepared by Subcontractor Reviewed by Contractor


Name : Tiara Putri Annisa Signature : Name : Signature :

Date : July 25, 2023 Date :


WEATHER SUMMARY
October 2022
TIME / DATE ###
###

TEMPERATURE (℃)
7:00 - 8:00
8:00 - 9:00
9:00 - 10:00
10:00 - 11:00 D
A
11:00 - 12:00 Y
12:00 - 13:00
13:00 - 14:00 O
F
14:00 - 15:00 F
15:00 - 16:00
16:00 - 17:00
17:00 - 18:00
18:00 - 19:00
19:00 - 20:00
20:00 - 21:00
21:00 - 22:00
22:00 - 23:00
23:00 - 23:59
0:00 - 1:00
1:00 - 2:00
2:00 - 3:00
3:00 - 4:00
4:00 - 5:00
5:00 - 6:00
6:00 - 7:00

Weather
Heavy Rain
Rain
Cloudy
PROJECT : LOTTE INDONESIA NEW ETHYLENE COMPLEX Project
DATE : July 25, 2023

PHOTOGRAPH DAILY REPORT

TOOL BOX MEETING AT 104 AREA SURVEY ACTIVITY LINE 1U31-TRIM-MH301V1-01

BEVELLING PIPE ACTIVITY AREA 103 MASTIC VALVE ACTIVITY 1U51-FW-00001-01

HOLIDAY TEST ACTIVITY LINE 1U31-CWR-90012-02 JOINT NO.10 HOLIDAY TEST ACTIVITY 1U31-OWS-90303-01 JOINT NO 2,3,4,5,6,7

Prepared by : Tiara Putri Annisa