This Agreement made and executed this 1st day of April, 2022 at Barangay Tomitom, Ipil,
Zamboanga Sibugay, Philippines by and between:
The Department of Social Welfare and Development – Field Office IX, a National
Government Agency of the Republic of the Philippines, with principal address at the General
Vicente Alvarez St., Zamboanga City, represented by its OIC – Regional Director,
ATTY. SITTIE RAIFAH M. PAMALOY-HASSAN, herein referred to as the “DSWD”;
The Local Government Unit of Ipil, a unit of the Government of the Republic of the
Philippines, with principal address at Purok Petrotex , Barangay Poblacion, municipality of Ipil,
province of Zamboanga Sibugay, represented by its Municipal Mayor,
HON. ANAMEL C. OLEGARIO, herein referred to as “MLGU”;
The Local Government Unit of Tomitom, a unit of the Government of the Philippines in the
municipality of Ipil, represented by its Barangay Chairperson, HON. MA ELSIE O. BOLODO,
herein referred to as “BLGU”;
The Barangay Health Emergency Response Team (BHERT), a duly recognized organization
with principal address at Barangay Tomitom, municipality of Ipil, Zamboanga Sibugay,
established to operate and maintain the completed Construction of Isolation Facility in
Barangay Tomitom, municipality of Ipil, Zamboanga Sibugay, represented by its
Chairperson/President, RECHEL L. GRECIA, herein referred to as “Association”;
-and-
The Municipal Health Office (MHO) with their office address and their Head of offices at Ipil,
Zamboanga Sibugay represented by its Chairperson/President, DRA. ADNILRE D. VERZON,
herein referred to as “Stakeholders”.
WITNESSETH THAT:
WHEREAS, the DSWD through the KC-NCDDP-AF, funded the priority subprojects of
communities during the Development Planning Forum;
WHEREAS, the community, with the leadership of the Barangay Development Council –
Technical Working Group (BDC-TWG) and the assistance provided by the Barangay and
Municipal local government units and other stakeholders, satisfactorily completed their
subproject entitled Construction of Isolation Facility;
1 Actual parties to the MPA will depend on those with actual commitments/roles in the O&M of completed
subproject.
WHEREAS, the community, municipal and barangay LGUs and other stakeholders (if
applicable) shall share the operation and maintenance responsibilities to sustain the delivery of
services provided by the completed sub-project through proper and timely operation and
maintenance activities;
WHEREAS, the BLGU shall primarily be responsible and accountable in ensuring that O&M
activities are implemented as planned;
NOW, THEREFORE, for and in consideration of the foregoing premises, the PARTIES do
hereby mutually agree and bind themselves as follows:
This Agreement shall take effect upon signing of the Parties concerned and enforceable for as
long as there is DSWD presence in the municipality or barangay.
IN WITNESS THEREOF, the parties, through their duly authorized representatives, have
hereunto entered into this Agreement and affixed their signatures on the date and place herein
above-mentioned.
Witnesses:
FATIMA S. CAMINAN
ARDO
ACKNOWLEDGEMENT
Republic of the Philippines )
___________________________) S.S.
BEFORE me, a NOTARY PUBLIC for and in this __________ day of _______________, 2022
personally appeared before me
Known to me to be the same persons who executed the foregoing instrument consisting of
__________ pages, including this page wherein this acknowledgement is written, signed by the
parties and their instrumental witnesses, which instrument they acknowledge to be their free and
voluntary act and deed, as well as that of the juridical persons which they represent.
IN WITNESS WHEREOF, I have hereunto affixed my notarial seal and signature this
____________ day of ___________________2022 at _______________________.
Doc No.__________
Page No. _________
Book No. _________