Bar Chart For Completion of Total Bhubaneswari PH-II Dt.19.07.2023
Bar Chart For Completion of Total Bhubaneswari PH-II Dt.19.07.2023
May-23
Aug-23
Nov-23
Mar-23
Dec-23
Apr-23
Feb-23
Sep-23
Oct-23
Jun-23
Jul-23
1 Retaining wall cum drain - 250 m 3
2 Weigh bridge room- 1No. & crew rest room- 1No. 4
3 S&T Goomty- 2Nos. & S&T Cabin building - 1No. 4
4 Minor Bridges - 2 Nos. (Ch.3/900 to 5/170 ) 1
5 Minor Bridges - 4 Nos. (Ch.6/050 to 7/523) 2#
6 Formation work from Ch.3/900 to 5/170 2
7 Formation work from Ch.6/050 to 7/523 3#
8 Track linking from Ch.3/900 to 5/170 2
9 Track linking from Ch. 6/050 to 7/523 2#
10 Dismantling of Platform No.6 , Formation & Track 1*
linking from Ch. 5/170 to 6/050
11 S&T work 2
12 OHE work & Commissioning of Phase-I of 2
Bhubaneswari SILO work
Note:-
The Phase-I work from end of Platform No.6 to Ch.7523 will be taken up after handing over the the existing Ananta bulb line by MCL.