Bar Chart Bhubaneswari Ph-2 04-08-2023
Bar Chart Bhubaneswari Ph-2 04-08-2023
Name of work Rail Connectivity for 01 SILOs (12MTY) for Bhubaneswari OCP adjacent Spur No. 5&6 &connectivity is taking off
at &TLSBand up to Spur 3&4 by regrading the existing Bulb Lines between 5&6 and 3&4 of MCL at Talcher coal
fields.
Work Order No. MCL/HQ/SAMB/Siding/22-23/65 Dt.21.05.2022 Colour Code
Name of Client M/s Mahanadi Coalfields Limited Planned
May-23
Aug-23
Nov-23
Mar-23
Mar-24
Dec-23
Apr-23
Feb-23
Feb-24
Sep-23
Oct-23
Jun-23
Jan-24
months)
Jul-23
Phase-I (Take off at Ch.3/766.09 to Ch.7/523.00 = 3757.00m route length)
1 Retaining wall cum drain - 250 m 3
2 Weigh bridge room- 1No. & crew rest room- 1No. 4
3 S&T Goomty- 2Nos. & S&T Cabin building - 1No. 4
4 Minor Bridges - 2 Nos. (Ch.3/900 to 5/170 ) 1
5 Minor Bridges - 4 Nos. (Ch.6/050 to 7/523) 2#
6 Formation work from Ch.3/900 to 5/170 2
7 Formation work from Ch.6/050 to 7/523 3#
8 Track linking from Ch.3/900 to 5/170 2
9 Track linking from Ch. 6/050 to 7/523 2#
10 Dismantling of Platform No.6 , Formation & Track 1*
linking from Ch. 5/170 to 6/050
11 S&T work 2
12 OHE work & Commissioning of Phase-I of 2
Bhubaneswari SILO work
Page 1 of 2
BAR CHART
Name of work Rail Connectivity for 01 SILOs (12MTY) for Bhubaneswari OCP adjacent Spur No. 5&6 &connectivity is taking off
at &TLSBand up to Spur 3&4 by regrading the existing Bulb Lines between 5&6 and 3&4 of MCL at Talcher coal
fields.
Work Order No. MCL/HQ/SAMB/Siding/22-23/65 Dt.21.05.2022 Colour Code
Name of Client M/s Mahanadi Coalfields Limited Planned
May-23
Aug-23
Nov-23
Mar-23
Mar-24
Dec-23
Apr-23
Feb-23
Feb-24
Sep-23
Oct-23
Jun-23
Jan-24
months)
Jul-23
Phase-II (Ch.7/523.00 to Ch.11/501.361 = 3978.361m route length)
1 Retaining wall cum drain - 2750 m 5#
2 S&T Goomty-1No. & S&T Cabin building - 1No. 4#
3 Major Bridge - 1 No. 6#
4 Minor Bridges - 11 Nos. 6#
5 Formation work from Ch.7/523.00 to Ch.11/501.361 6#
7 S&T work 6#
8 OHE work & Commissioning of Phase-II 6#
Bhubaneswari SILO work - Ananta Bulb portion
Note:-
The Phase-II (Ananta Bulb) work will be taken up after handing over the the existing line by MCL.
# = After handing over of Ananta Bulb.