You are on page 1of 3

1. States the mandatory involvement of Maintenance Officials 7.

In the worksite layout, it is the section of roadway where a) 3 days


of the RO/DEOs on specific tasks concerning DPWH projects drivers are informed about the approaching work area and b) 7 days
within their area of jurisdiction what to expect ahead c) 10 days
a) Department Order No. 41, s. 2016 d) 30 days
b) Department Order No. 171, s. 2015 a) Advance Warning Area
c) Department Order No. 80, s. 2016 b) Transition Area 14. Growth of grass, weeds, and shrubs or any kind of
d) Department Order No. 67, s. 2017 c) Adjacent Clearance for Workers vegetation from the side of the canal to the RROW limits
  d) Termination Area reaching an average height of 0.60 meters
2. The act of preserving and keeping the roadway system in, as a) Vegetated Shoulder
8. It is a lateral safety buffer beside the work area that b) Inverted Shoulder
near as possible, its originally constructed or subsequently
increases protection and safety for workers c) Lush Vegetation
improved state
a) Advance Warning Area d) Vegetated Canal
a) Roadway Design
b) Transition Area
b) Roadway Construction
c) Adjacent Clearance for Workers 15. Form MP-1 refers to
c) Roadway Maintenance
d) Termination Area a) Prescribed Response Time
d) None of the above
b) Updated MPP List
9. This Department Order provides a clear understanding of the c) Weather Chart
3. Type of Roadway Maintenance that is regularly performed
provisions under Department Order No. 171, s. 2015, and to d) Daily Road Inspection Report
for a specific period of time i.e., pavement markings application
clearly illustrate how the mechanisms on the point system are
a) Routine Maintenance
applied in the imposition of sanctions to erring technical 16. As indicated under Section 4 “Point System for the
b) Periodic Maintenance
personnel and officials Imposition of Sanctions; Annex “1” of the Amended Policy
c) Preventive Maintenance
a) Department Order No. 41, s. 2015 Guidelines on the Maintenance of National Roads and Bridges, a
d) Emergency Maintenance
b) Department Order No. 80, s. 2016 calibrated sanction shall be imposed to the erring technical
4. Maintenance that is regularly performed throughout the year c) Department Order No. 67, s. 2017 personnel and officials once total percentage points of specific
and includes carriageway maintenance and roadside d) None of the above DEO is __________.
maintenance.   a) Lower than 50%
a) Routine Maintenance b) 50%
10. Shall be directly responsible for the efficient and timely
b) Periodic Maintenance c) Lower than 75%
maintenance of all national roads and bridges within the
c) Preventive Maintenance d) 75%
respective jurisdictions
d) Emergency Maintenance
a) District Engineer 17. What is the type of Joint in PCCP which is also called cold
5. Maintenance performed on the roadway system during and b) Assistant District Engineer joint? It is constructed when there is an interruption of more
after storms, calamities, and other emergency conditions to c) District Maintenance Engineer than 30 minutes in the concreting operation which is placed not
protect the traveling public and roadway system and provide d) Maintenance Point Persons within 1.50 m. of an expansion joint or contraction joint.
temporary passage when possible a. Contraction Joint
11. The frequency of inspection/validation by BOM to the
a) Routine Maintenance b. Expansion Joint
Regional Offices except for NCR.
b) Periodic Maintenance c. Construction Joint
a) once a year
c) Preventive Maintenance d. Longitudinal Joint
b) at least two (2) times a year
d) Emergency Maintenance e. None of the Above
c) at least three (3) times a year
d) at least four (4) times a year  
6. It is a new concept designed to increase the efficiency and
effectiveness of road maintenance operations.   18. _______________ ensure the adhesion of the surface
12. Response time for rectifying Code 05 Pumping and
a) Road and Bridge Performance Based Maintenance course to the binder course.
Depression
b) Maintenance Backlog Reduction a. Bitumen
a) 3 days
c) Preventive Maintenance b. Prime Coat
b) 7 days
d) Long Term Performance Based Maintenance Contract c. Tack Coat
c) 10 days
d. None of the Above
d) 30 days
13. Response time for rectifying Code 07 Low/inverted shoulder
  communication link which brings economic development to a 31. __________involves excavation of common materials used
19. What is the raised rim of concrete which forms the edge of nation. as embankment fill which results from excavation along the
the sidewalk while the _____ is the horizontal paved portion a. Pavement road traverse.
slightly inclined. b. Sidewalk a. Rock excavation
a. Pavement c. Road b. Common excavation
b. Bridge d. None of the above c. Surplus excavation
c. Curb and Gutter d. None of the above
d. None of the above 26. ___________ is composed of Portland cement concrete of
sufficient character to support the weight of passing vehicle. 32. Which of the following is under the construction
20. What is the type of Joint in PCCP which is also called (Rigid Pavement) requirements for Storm Drainage and Sewerage System
weakened-plane joints? It is provided to relieve the tensile a. Asphalt Road a. Installation of Soil, Waste, Drain and Vent Pipes
stresses due to temperature, moisture, and  friction, b. Concrete Road b. Sewer Connections and Clean-outs
thereby controlling cracking. c. Gravel Road c. Water Test on System
a. Contraction Joint d. None of the above d. All of the above
b. Expansion Joint
c. Construction Joint 27. ___________ consists of a layer of thick mixture of sand 33. This Item shall consist of furnishing all materials,
d. Longitudinal Joint and gravel using a bituminous material called asphalt as binder. equipment and labor for the complete installation of the storm
e. None of the Above (Flexible Pavement) drainage system inclusive of all pipings, gutters, canals, catch
a. Asphalt Road basin, junction boxes, handholes, manholes and other
21. _______________ Is an application of thin bituminous b. Concrete Road appurtenant structures, as well as the sewerage system
material to a porous base before putting c. Gravel Road inclusive of all sanitary sewer pipings and septic vaults where
a. Bitumen d. None of the above no public sewer exist, from the building to the point of
b. Prime Coat discharge.
c. Tack Coat 28. _________is the simplest form of road constructed by A. Storm Drainage and Sewerage System
d. None of the Above shaping and smoothing the natural soil traversed by the road B. Plumbing
line. C. Both Plumbing and Sewerage System
22. What is the Department Order which states the Guidelines a. Asphalt Road D. All of the above
on the use of Dowel Bars in PCCP? b. Earth Road
a. DO 80 s 2016 c. Gravel Road 34. Color code for Grade 40 Reinforcing Steel Bar being used in
b. DO 42 s 2016 d. None of the above roads and buildings.
c. DO 32 s 2016 a. Green
d. None of the above 29. __________connects a provincial or national road to a b. White
public wharf or railway station. c. Red
23. What does PCCP stands for? a. Primary National Road d. Yellow
a. Portland Concrete Cement Pavement b. Secondary National Road  
b. Portland Cement Concrete Pavement c. Tertiary Road 35. Deployment of resources at the project site falls under
c. Pavement Concrete Cement Portland d. None of the above which item of work.
d. Portland Cement Content Pavement a. Item 800(1)
30. __________the main highway trunk line system that is
b. Item B.9
24. As per department order, what is the standard length of continuous in extent that goes from province to province and
c. Item B.5
dowel bar of PCCP? region to region.
d. Item 801(1) 
a. 1 meter a. Primary National Road
b. 0.60 meter b. Secondary National Road 36. ___________ is the Promotion and maintenance of highest
c. 0.80 meter c. Tertiary Road degree of physical, mental and social well-being of workers in
d. None of the above d. None of the above all occupation.
a. Construction Safety and Health Program (CSHP)
 25. A ____________ is a structure that link barangays and  
b. Occupational Safety and Health
cities in the country and serve as medium in transporting goods
c. Construction Safety and Health Organization
and commodities from one place to another and as
d. Both a and c c. Spread Footing 49. Roofing Accessories with at least 250 mm laps over the
d. Deep Foundation roofing sheets and, together, shall be riveted at every second
37. This item shall consist of the necessary excavation for corrugation.
foundations of buildings in reasonably close conformity with the 43. It is  placed directly on the slab on fill (SOF) for low rise a. Valleys
plans or as established by the engineer. building or on the basement floor  for high rise building to form b. Flashing
a. ITEM 802 a protective barrier between the soil and the concrete structure c. Gutter
b. ITEM 804 which, in turn, ensure protection to its architectural finishes. d. Ridge and Hip Rolls
c. ITEM 803 a. Gravel bed  
d. ITEM 801 b. Base coarse 50. The average required strength of non-load bearing
c. Polyethylene Film Concrete Hollow Blocks.
38. ______________ is the process of adding diluted control d. Lean Concrete a. 3.45 Mpa (500psi)
products directly to the base of a plant. It provides deep,
b. 5.5 Mpa (800psi)
targeted treatment and is a useful way for professionals to 44. Minimum concrete cover for Beams and Columns
c. 6.9 Mpa (1000psi)
apply insecticides to trees with pest infestations. a. 40mm
d. 4.14 Mpa (600psi)
a. Poisoning b. 75mm
b. Cordoning c. 20mm
c. Soil drenching d. 35mm
d. Wood preservation
45. Minimum concrete cover for Footing, Footing Tie Beams
39. A method which trenches in concentric circles, squares or a. 40mm
rectangle are dug 150mm to 220mm wide and at least one b. 75mm
meter apart and applied with liquid termite concentrate working c. 20mm
solution at the rate specified by the product data. d. 35mm
a. Drenching Method
b. Pressure Treatment Method  
c. Non-pressure treatment method 46. Minimum bend diameter  for 28mm to 23mm
d. Cordoning Method a. 5 bar diameters
  b. 8 bar diameters
40. It is usually called the __________, which is the chief c. 10 bar diameters
means of supporting a building. It carries both the dead load d. 40 bar diameters
and the live loads and their primary purpose is to transmit the
47. An admixture that causes development of microscopic air
collective building loads to the underlying soil or rocks.
bubbles in cement concrete paste during mixing, usually to
a. Column
increase its resistance to freezing throwing and to improve
b. Beams
workability.
c. Base Soil
a. Retarding
d. Foundation
b. Water – reducing / Accelerating
 
c. Air-entraining
41. Back fill shall be placed in layers at 200mm thk and shall be
d. Water-reducing
compacted to ______ percent  Maximum dry density.
a. 95 48. The maximum drop height of chute in depositing of
b. 98 concrete for column.
c. 100 a. 1.6m
d. 97 b. 1.8m
c. 1.7m
42. It is a continuous thick concrete slab on the soil that
d. 1.5m
extends the entire footprint of the building.
 
a. Mat Foundation
b. Strip Foundation

You might also like