CLIENT Nepal Electricity Authority TANSMISSION & SYSTEM OPERATION
PROJECSUPPLY AND CONSTRUCTION OF DAMAK SUBSTATION CONTRACT NO: KCD-66/04
SUBSTA132/33kV 30MVA DAMAK S/S
Design of 132/33KV 30MVA Transformer Foundation Rail Track way
Transformer Detail
Equipment Type : 30 MVA(3 Phase)
Length, L 6.0 m Width, B 4.0 m Height from PL, H 4.5 m Weight, W 59740 Kgs Ref drg no. SFZ11-30000-132 of 30MVA Transformer of HUBEI SUNLIGHT ELECTRIC CO.,LTD General inputs : 2 Net safe Bearing capacity, p= 58.86 KN/m2 =6*9.81 (6T/m )
1 Design of base foundation for rails
Shipping wt of transformer = 59740 kg
= 586.05 KN C/C distance of rail track 2.04 m Available length of rail = 6 m provide individual slab length = 4 m Provided base slab width = 3.04 m3/m distance from rail center line to slab end = 0.50 m Load coming on unit length of base slab 146.51 KN/m = 586.05 / 6
Case I : When wheels run on two parallel tracks
Design of base pad
Load coming on unit length of base slab 146.51235 KN/m Weight of concrete base 10.20 KN/m = 2.04x 25x 0.2 Total 156.71 KN/m SBC at toe level for dead load only 58.86 KN/m2 = 58.86 Required area of individual footing = 2.662 m provided individual base slab length = 4 m Required width of base slab = 0.67 m Provided base slab width = 3.04 m Provided area of base slab = 12.16 m2 CLIENT Nepal Electricity Authority TANSMISSION & SYSTEM OPERATION PROJECSUPPLY AND CONSTRUCTION OF DAMAK SUBSTATION CONTRACT NO: KCD-66/04 SUBSTA132/33kV 30MVA DAMAK S/S Maximum bearing pressure developed = 48.19 KN/m2 = 146.51 / 3.04 < 58.86 KN/m2 OK. Design of base pad
Net bearing pressure 48.19 KN/m2
Moment at middle of slab 25.07 KN-m/m = 48.19 x 2.04^2 / 8 Moment at cantilver part 6.02 KN-m/m = 48.19 x 0.5^2 / 2 Considered Moment = 25.07 KN-m/m Design moment (factored @ 1.5) , Mu 37.61 KN-m/m = 1.5 x 25.07 Provided depth of base slab = 200.00 mm Clear cover provided 50.00 mm Effective depth, d 144 mm = 200 - 50- 12/2 2 Concrete Grade, fck = 20 N/mm 2 Steel Type, fy = 415 N/mm We have BM = 0.138 x fck x b x d2 d =(M2/(0.138 x fck x b)0.5 = 3.69 mm taking b=1 m strip 1000.00 mm To be in safe side take D = 200.00 mm Effective depth d = 144.00 mm For Area of steel required: M=0.87*fy*Ast(d-fy*Ast/(b *fck)) or,37606443=0.87x415xAst(144-415xAst/(20x1000) or,7.49Ast² + -51991Ast +6024.36 =0 Solving Quadratic equation A B C 7.491788 -51991.2 37606443 2 X1 X1= 6119 479 mm 6119.479 2 X2= 820.2805 mm 2 Ast per m width = 820 mm Minimum reinforcement from code- IS:456:clause 25.5.2.1 0.12 % 2 Mininimum Ast for 0.12% reinf. 173 mm /m Max spacing, 3d or 450mm = 432 mm
Provide 12 φ bars @ 125 mm c/c at both top and bottom
2 2 = 905 mm /m, O.K. > 820 mm /m For distribution reinforcement: Provide 10 φ bars @ 150 mm c/c at both top and bottom 2 2 = 524 mm /m, O.K. > 173 mm /m Check for punching against one wall
Punching perimeter 8m =2x4
Effective area for punching 1.15 m2 = 8 x 144/1000 Punching load 293.025 KN = 586.05 /2 2 Punching shear stress developed 0.560 N/mm = 2.2 x 293.02x 1000 /(1.15x 1000 x 1000) < 0.25 x sqrt(fck) = 1.118 N/mm2, O.K. Hence Provide Length of individual slab = 4 m Width of slab = 3.04 m Depth of slab = 200.00 mm Tansverse Reinforcement bar = 12 φ bars @ 125 mm c/c at top and bottom Longitudinal/distribution reinforcement bar = 10 φ bars @ 150 mm c/c at top and bottom