PLANNING COMMISSION
( PC – 1FORM )
(INFRASTRUCTURE SECTORS)
The objectives of the sector / sub The objectives of the sector is to improve
sector as indicated in the medium socio economic development in the area.
term/five year plan be reproduced The objective of the sub sector area.
included objective of the project i. To improve communication facilities in
and develop a linkage between the the area
proposed project and sect oral ii. To provide access to the local market,
objectives. business centers public places, schools,
health centers etc.
iii. To provide transportation facilities for
agriculture commodities/products to the
local markets & minerals etc.
iv. To improve education and health facility
in the area.
v. To improve law and order situation in
the area.
i. Description of the project and indicate The project would provide an all weather
existing facilities in the area and access to the population our 95000 people
justify the establishment of the project living in 55 No major and small villages in
the torkow tehsile of chitral district.
ii. Provide technical parameter i.e input i. Total length 73 KM
and output of the project. Also discuss ii. Formation width 32 feet
technology aspect of the project. iii. Black topped width 12 feet
iv. Asphalt wearing course 2” thick
v. Base course 9” thick
vi. Sub base 9” thick
iii. Provide details of civil works equipment The project include cutting as well filling
machinery and other physical facilities for the Embankment.
for the project. Involves black toping of road, construction
of cross drainage and retaining structure
at numerous location PCC & RRM road
side drainage are also provided
as per requirement. The above stated civil
works involves dozers, road roller, tar boilers
asphalt drum, mixer and excavators
vi. Relation s hip of present project with This is existing road network of the
other project area and facilitate the smooth flow of
traffic with the result that the area
can be made accessible for the
execution of other projects of public
interest.
vii. For road provide information Regarding Refer drawing typical cross section
land width geometric and pavement width
viii. Land classification for bridges & culvert Public and private land
ix. Thickness / width of road way on bridges Reflected in the typical cross section
& Culvert
Average daily traffic of motor vehicles i. Heavy vehicle 60 Nos per day
by category as well as the car units be ii. Light vehicle 320 Nos per day
provide
ii. Basis of Determining the capital cost be The DCE has been based on CSR 1999,
provided. It includes market survey, and MRS 2013.
schedule rate, estimation on the basis of
previous work done etc.
Item wise annual operating cost based on 1% of the project cost (23.232 M)
proposed capacity utilization be worked
out for 5 years and sources of its financing
Capacity of the projects being implemented The project has the capacity to serve the
in public/ private sector expected traffic for 50 year.
Others N.A
b. Debt N.A
Financial:
Income to the project along with The local government of District Chitral
assumptions may levy export tax on fruits & minerals
exported to the rest of the country. It may
also impose road user/ registration tax on
vehicles using the stated project.
Economic:
Benefit to the economy along with The Economic life of the area will be
improved through export of fruits and
vegetables taken to the rest of the country.
Moreover the mineral exploitation in the
area will bring in industrial investment in
the mining sector thereby providing uplift
in the life style of the people.
Social:
Benefits with indicators. The people of the area will be provided
with an all weather access to the rest of the
country thereby facilitating them in taking
their patients to better hospitals in
peshawar and in other districts of the
province. they will also avail the facility of
education available in the settled areas.
Environmental:
Environmental impact assessment The environmental impact assessment of
negative / positive. the project is enclosed, which reflects an
over all positive impact of the project
over the project area.
Net present value (NPV) and Benefit Cost Benefit ratio has been calculated,
Cost Ratio based on vehicle operating cost (VOC) and
time saving
Impact of delays on project cost and The delay of the project will increase the
cost
Viability of the project to the level of inflation in the
country which may make the project non
viable during the proceeding years.
Uint cost
Employment analysis
Employment generation (direct and indirect) People will be directly employed during the
span of construction by the contractor for the
execution of the project. They will also get
trained on various construction equipments
used by the contractor, indirect employment
will be generated for trucking of construction
material, it will also provide opportunity to
the crushers and other material suppliers
which are being consumed during the course
of construction.
12 . IMPLEMENTATION SCHEDULE.
Indicate starting and completion date Date of Commencement 2014
of the project. Date of Completion 2017
(Subject to Availability of Funds)
1 XEN 1 No
2 SDOs 1 No
3 Sub Engineers 2 No
4 D.O.A 1 No
5 Head Cleark 1 No
6 Accounts Clerks 2 No
7 Junior Clerks 2 No
8 SDAs 1 No
9 Draftsman 1 No
Manpower requirements by skills during Skill and Unskilled lab our will be arranged by
execution and operation of the project be the contractor
provided
Approved by CDWP