MCCR-M-14 - Pump
Golar GIMI
SubSystem Description : FW Water Cooling for Bow Gas Engines & AC Units
01.20 Ensure Cooling lines are installed as per P&ID and vendor drawings
Printed by: CMS Admin, Aldwin. 09-Jan-2023 21:25, (ID=403842). Checklist type: MCCR-M-14, Rev: 8 page 1 of 2
Mechanical Completion Checksheet
MCCR-M-14 - Pump
Golar GIMI
SubSystem Description : FW Water Cooling for Bow Gas Engines & AC Units
02.03 Check calibration pot are installed correctly and visible where applicable.
02.04 Check constant level oiler are fitted, filled and protected where applicable.
02.05 Check lube oil, seal oil and cooling system are correct as per design.
03.01 Check position. Pump impeller height adjusted as per vendor requirements.
03.02 Check all guide bolting is secured by lock washers or check nuts.
Check correct number of riser spools in place, installed correctly. Spool faces are
03.03
undamaged and square.
03.04 Check riser spool mounts, gaskets and guides are installed and secured.
03.05 Check riser spool stud bolts are in accordance with specifications and all fitted.
Comments/Remarks:
Electronic Signature
Completed by Vendor/KSL Approved by KSL Accepted by Golar Witnessed by DNV
Company Keppel Shipyard Ltd Keppel Shipyard Ltd Golar NA
Printed by: CMS Admin, Aldwin. 09-Jan-2023 21:25, (ID=403842). Checklist type: MCCR-M-14, Rev: 8 page 2 of 2
CWP NO: C140-CWP-00GN-L01
CLIENT :
Golar LNG
DRAWN : AM TITLE : CLIENT DWG NO. :
06 14.03.22 LQ NO PL RE-ISSUED FOR CONSTRUCTION (REFERENCE TO MR COMMENT NO. 1919) 18002-ROR-080-L-XB-0002 LOW TEMPERATURE SYSTEM DATE : 27.06.2018 P&ID -
05 12.11.19 AM NO PL RE-ISSUED FOR CONSTRUCTION (P&ID FROZEN AS PER GOLAR-KEPPEL MEETING) 18002-ROR-080-L-XB-0003 HIGH TEMPERATURE SYSTEM SCALE : AS SHOWN 18002-KEP-040-P-XB-0006
04 05.07.19 AM NO PL ISSUED FOR CONSTRUCTION (UPDATED AS PER GOLAR COMMENT) 18002-KEP-051-P-XB-0002 P&ID - BILGE SYSTEM - BOW AREA
FRESH WATER COOLING SYSTEM
CHKD : CZ SHEET 1 OF 3
03 18.12.18 AM NO PL ISSUED FOR APPROVAL 18002-KEP-069-P-XB-0003 P&ID - LUBE OIL SYSTEM - GAS GENERATOR SET
MAIN CODE : SS01G/00004
GAS GENERATOR SET REV. NO. : 06
02 28.09.18 JR JH PL ISSUED FOR FEED 18002-KEP-050-P-XB-0006 P&ID - SEA WATER COOLING SYSTEM - GAS GENERATOR SET
01 27.06.18 AM CZ PL ISSUED FOR APPROVAL 18002-KEP-000-L-SA-0002 PIPING SPECIFICATION - MARINE SYSTEM
This document is the property of VESSEL :
NO. DATE BY CHKD. APPD.
REVISIONS
DESCRIPTION DWG. NO. TITLE
Keppel Shipyard. It is not to be
copied nor shown to a third party
without prior consent.
Shipyard GOLAR GIMI FLNG
REFERENCE DRAWINGS
ACAD DRAWING A1 SIZE
GAS ENGINE NO. 1 GAS ENGINE NO. 2
Golar LNG
DRAWN : AM TITLE : CLIENT DWG NO. :
06 14.03.22 LQ NO PL RE-ISSUED FOR CONSTRUCTION (REFERENCE TO MR COMMENT NO. 1919) 18002-ROR-080-L-XB-0002 LOW TEMPERATURE SYSTEM DATE : 27.06.2018 P&ID -
05 12.11.19 AM NO PL RE-ISSUED FOR CONSTRUCTION (P&ID FROZEN AS PER GOLAR-KEPPEL MEETING) 18002-ROR-080-L-XB-0003 HIGH TEMPERATURE SYSTEM SCALE : AS SHOWN 18002-KEP-040-P-XB-0006
04 05.07.19 AM NO PL ISSUED FOR CONSTRUCTION (UPDATED AS PER GOLAR COMMENT) 18002-KEP-051-P-XB-0002 P&ID - BILGE SYSTEM - BOW AREA
FRESH WATER COOLING SYSTEM
CHKD : CZ SHEET 2 OF 3
03 18.12.18 AM NO PL ISSUED FOR APPROVAL 18002-KEP-069-P-XB-0003 P&ID - LUBE OIL SYSTEM - GAS GENERATOR SET
MAIN CODE : SS01G/00004
GAS GENERATOR SET REV. NO. : 06
02 28.09.18 JR JH PL ISSUED FOR FEED 18002-KEP-050-P-XB-0006 P&ID - SEA WATER COOLING SYSTEM - GAS GENERATOR SET
01 27.06.18 AM CZ PL ISSUED FOR APPROVAL 18002-KEP-000-L-SA-0002 PIPING SPECIFICATION - MARINE SYSTEM
This document is the property of VESSEL :
NO. DATE BY CHKD. APPD.
REVISIONS
DESCRIPTION DWG. NO. TITLE
Keppel Shipyard. It is not to be
copied nor shown to a third party
without prior consent.
Shipyard GOLAR GIMI FLNG
REFERENCE DRAWINGS
ACAD DRAWING A1 SIZE
GAS ENGINE NO. 1 GAS ENGINE NO. 2
Golar LNG
DRAWN : AM TITLE : CLIENT DWG NO. :
06 14.03.22 LQ NO PL RE-ISSUED FOR CONSTRUCTION (REFERENCE TO MR COMMENT NO. 1919) 18002-ROR-080-L-XB-0002 LOW TEMPERATURE SYSTEM DATE : 27.06.2018 P&ID -
05 12.11.19 AM NO PL RE-ISSUED FOR CONSTRUCTION (P&ID FROZEN AS PER GOLAR-KEPPEL MEETING) 18002-ROR-080-L-XB-0003 HIGH TEMPERATURE SYSTEM SCALE : AS SHOWN 18002-KEP-040-P-XB-0006
04 05.07.19 AM NO PL ISSUED FOR CONSTRUCTION (UPDATED AS PER GOLAR COMMENT) 18002-KEP-051-P-XB-0002 P&ID - BILGE SYSTEM - BOW AREA
FRESH WATER COOLING SYSTEM
CHKD : CZ SHEET 3 OF 3
03 18.12.18 AM NO PL ISSUED FOR APPROVAL 18002-KEP-069-P-XB-0003 P&ID - LUBE OIL SYSTEM - GAS GENERATOR SET
MAIN CODE : SS01G/00004
GAS GENERATOR SET REV. NO. : 06
02 28.09.18 JR JH PL ISSUED FOR FEED 18002-KEP-050-P-XB-0006 P&ID - SEA WATER COOLING SYSTEM - GAS GENERATOR SET
01 27.06.18 AM CZ PL ISSUED FOR APPROVAL 18002-KEP-000-L-SA-0002 PIPING SPECIFICATION - MARINE SYSTEM
This document is the property of VESSEL :
NO. DATE BY CHKD. APPD.
REVISIONS
DESCRIPTION DWG. NO. TITLE
Keppel Shipyard. It is not to be
copied nor shown to a third party
without prior consent.
Shipyard GOLAR GIMI FLNG
REFERENCE DRAWINGS
ACAD DRAWING A1 SIZE
Machine alignment information
Dimensions mm
Measurements mm
Tolerances mm
Dexter
06/01/23
Hari prasath
04-Jan-2023
DOCUMENT TITLE
Vessel Name: Golar GIMI FLNG RFI Report No: G00004-SM-B-VI-MR1F-01530 Rev: 0
Date of Inspection: 01-Dec-2021 Time of Inspection: 10:40 Location of Inspection: Bow Machinery Rm (12700 ABL)
1 Type of Inspection
Long Description:
Comments/Remarks:
Inspection has been verified and accepted by Golar.
Electronic Signature
Inspected By QC/Rep Inspected By KSL Inspected By Golar Inspected By DNVGL
Company Keppel Shipyard Ltd Keppel Shipyard Ltd Golar NA