Concreting of Barangay Road One Taguite, Tangub City
Concreting of Barangay Road One Taguite, Tangub City
PROGRAM OF WORKS
Item No. Description Unit Quantity Unit Cost Total Cost Percentage
202 (1) Crushed Aggregate Base Course cu.m. 48.99 1,676.06 82,110.18 19.12%
311 (1) B Cement Concrete Pavement, = .20m sq.m. 221.47 1,080.22 239,236.32 55.72%
Four Hundred Twenty Nine Thousand Three Hundred Eighty Five Pesos and
429,385.06 100%
06/100
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City May 31, 2023
BILL OF QUANTITIES
Part No. ____________ Part Description ___________
(Columns (1), (2), (3) and (4) are to be filled up by the Procuring Entity ) (Column (5) & (6) are to be filled up by the bidder)
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City May 31, 2023
DETAILED ESTIMATES
B) Equipment:
1 Backhoe for 1 day @P 16,000.00 = P 16,000.00
1 Dumptruck for 1 day @P 12,000.00 = P 12,000.00
28,000.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
3 Labor for 1 day @P 350.00 = P 1,050.00
1,650.00
Indirect Cost:
OCM = P 4,447.50
PROFIT = P 2,965.00
Tax/VAT = P 4,447.50
11,860.00
B) Equipment:
1 Grader for 1 day @P 16,000.00 = P 16,000.00
1 Road Roller for 1 day @P 15,000.00 = P 15,000.00
31,000.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
4 Labor for 1 day @P 350.00 = P 1,400.00
2,000.00
Indirect Cost:
OCM = P 4,950.00
PROFIT = P 3,300.00
Tax/VAT = P 4,950.00
13,200.00
B) Equipment:
1 Grader for 1 day @P 16,000.00 = P 16,000.00
1 Road Roller for 1 day @P 15,000.00 = P 15,000.00
31,000.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
4 Labor for 1 day @P 350.00 = P 1,400.00
2,000.00
Indirect Cost:
OCM = P 8,797.50
PROFIT = P 5,865.00
Tax/VAT = P 8,797.50
23,460.00
B) Equipment:
1 One Bagger Mixer for 3 day @P 1,376.00 = P 4,128.00
1 Concrete Vibrator for 3 day @P 730.00 = P 2,190.00
6,318.00
C) Labor:
1 Foreman for 3 day @P 600.00 = P 1,800.00
4 Skilled Worker for 3 day @P 450.00 = P 5,400.00
12 Labor for 3 day @P 350.00 = P 12,600.00
19,800.00
Indirect Cost:
OCM = P 25,632.45
PROFIT = P 17,088.30
Tax/VAT = P 25,632.45
68,353.20
B) Equipment:
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
4 Labor for 1 day @P 350.00 = P 1,400.00
2,000.00
Indirect Cost:
OCM = P 2,178.00
PROFIT = P 1,452.00
Tax/VAT = P 2,178.00
5,808.00
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City May 31, 2023
ACCOMPLISHMENT
25.00% 25.00% 25.00% 25.00%
CASH FLOW
107,346.27 107,346.27 107,346.27 107,346.27
CUMULATIVE ACCOMPLISHMENT
25.00% 50.00% 75.00% 100.00%
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City May 31, 2023
LOCATION: Barangay Taguite, Tangub City
Project Manager 1
Project Engineer 1
Construction Foreman 1
Skilled Worker 4
Labor 12
TOTAL 19
Submitted By:
SGM CONSTRUCTION
May 31, 2023
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City
Road Roller 1
Grader 1
Backhoe 1
Concrete Vibrator 1
Dumptruck 1
TOTAL 6
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Barangay Road One Taguite, Tangub City May 31, 2023
Item No. Description Unit Quantity Unit Cost Total Cost Percentage 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days 5 days
102 Surplus Common Excavation cu.m. 63.90 649.61 41,510.08 9.67% 4.83% 4.83%
202 (1) Crushed Aggregate Base Course cu.m. 48.990 1,676.06 82,110.18 19.12% 6.37% 6.37% 6.37%
311 (1) B Cement Concrete Pavement, = .20m sq.m. 221.47 1,080.22 239,236.32 55.72% 13.93% 13.93% 13.93% 13.93%
B.5 Project Billboard/Sign Board sets 2.00 10,164.00 20,328.00 4.73% 0.53% 0.53% 0.53% 0.53% 0.53% 0.53% 0.53% 0.53% 0.53%
Four Hundred Twenty Nine Thousand Three Hundred Eighty Five Pesos and
429,385.06 100%
06/100
Periodeic 5.36% 10.74% 5.91% 6.90% 6.90% 20.83% 14.46% 14.46% 14.46%
Planned
Commulative 5.36% 16.10% 22.01% 28.91% 35.81% 56.63% 71.09% 85.54% 100.00%
Submitted By:
PERT / CPM
23 DAYS 22 DAYS
B.5
5 DAYS
Submitted By:
50 DAYS
500(3) 50 DAYS
III
B.5 311(1)
103(1)A B.9
V
5 DAYS
102(2)
B.8(1)
Submitted By:
SGM CONSTRUCTION