Concreting of Road at Barangay Bongabong
Concreting of Road at Barangay Bongabong
PROGRAM OF WORKS
Item No. Description Unit Quantity Unit Cost Total Cost Percentage
Two Hundred Five Thousand Five Hundred Fifty Six Pesos and 40/100 205,556.40 100%
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
BILL OF QUANTITIES
(Columns (1), (2), (3) and (4) are to be filled up by the Procuring Entity ) (Column (5) & (6) are to be filled up by the bidder)
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
DETAILED ESTIMATES
B) Equipment:
1 One Bagger Mixer for 10 day @P 1,562.00 = P 15,620.00
1 Concrete Vibrator for 10 day @P 730.00 = P 7,300.00
22,920.00
C) Labor:
1 Foreman for 10 day @P 600.00 = P 6,000.00
4 Skilled Worker for 10 day @P 450.00 = P 18,000.00
10 Labor for 10 day @P 350.00 = P 35,000.00
59,000.00
Indirect Cost:
OCM = P 22,023.90
PROFIT = P 14,682.60
Tax/VAT = P 22,023.90
58,730.40
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
LOCATION: Barangay Bongabong, Tangub City
CASH FLOW
ACCOMPLISHMENT
25.00% 25.00% 25.00% 25.00%
CASH FLOW
51,389.10 51,389.10 51,389.10 51,389.10
CUMULATIVE ACCOMPLISHMENT
25.00% 50.00% 75.00% 100.00%
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
LOCATION: Barangay Bongabong, Tangub City
Project Manager 1
Project Engineer 1
Materials Engineer 1
Construction Foreman 1
Skilled Worker 4
Laborers 10
TOTAL 18
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
LOCATION: Barangay Bongabong, Tangub City
Concrete Vibrator 1
TOTAL 2
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Concreting of Road at Barangay Bongabong May 9, 2023
Item No. Description Unit Quantity Unit Cost Total Cost Percentage 10 days 10 days 10 days
I Cement concrete pavement cu.m. 12.0 17,129.70 205,556.40 100.00% 33.33% 33.33% 33.33%
Two Hundred Five Thousand Five Hundred Fifty Six Pesos and 40/100 205,556.40 100%
PERT / CPM
15 DAYS 15 DAYS
START I FINISH
5 DAYS
Submitted By:
50 DAYS
500(3) 50 DAYS
III
B.5 311(1)
103(1)A B.9
V
5 DAYS
102(2)
B.8(1)
Submitted By:
SGM CONSTRUCTION