Professional Documents
Culture Documents
Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay Simasay
Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay Simasay
Barangay Simasay
PROGRAM OF WORKS
Item No. Description Unit Quantity Unit Cost Total Cost Percentage
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: Rehabilitation of PCCP & Construction of Road Shouldering
February 23, 2023
of Purok 3 Barangay Simasay
BILL OF QUANTITIES
(Columns (1), (2), (3) and (4) are to be filled up by the Procuring Entity ) (Column (5) & (6) are to be filled up by the bidder)
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: Rehabilitation of PCCP & Construction of Road
February 23, 2023
Shouldering of Purok 3 Barangay Simasay
DETAILED ESTIMATES
B) Equipment:
1 Backhoe for 3 day @P 12,200.00 = P 36,600.00
1 Dumptruck for 3 day @P 11,360.02 = P 34,080.06
70,680.06
C) Labor:
1 Foreman for 3 day @P 600.00 = P 1,800.00
2 Labor for 3 day @P 350.00 = P 2,100.00
3,900.00
Indirect Cost:
OCM = P 11,187.01
PROFIT = P 7,458.01
Tax/VAT = P 11,187.01
29,832.02
B) Equipment:
1 Backhoe for 1 day @P 12,200.00 = P 12,200.00
12,200.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
3 Skilled Worker for 1 day @P 450.00 = P 1,350.00
5 Labor for 1 day @P 350.00 = P 1,750.00
3,700.00
Indirect Cost:
OCM = P 21,192.00
PROFIT = P 14,128.00
Tax/VAT = P 21,192.00
56,512.00
B) Equipment:
1 Transit Mixer for 7 day @P 10,500.00 = P 73,500.00
1 Concrete Vibrator for 7 day @P 730.00 = P 5,110.00
1 Concrete Saw for 7 day @P 1,750.00 = P 12,250.00
1 Bar Cutter for 4 day @P 260.00 = P 1,040.00
91,900.00
C) Labor:
1 Foreman for 7 day @P 600.00 = P 4,200.00
6 Skilled Worker for 7 day @P 450.00 = P 18,900.00
12 Labor for 7 day @P 350.00 = P 29,400.00
52,500.00
Indirect Cost:
OCM = P 27,605.40
PROFIT = P 18,403.60
Tax/VAT = P 27,605.40
73,614.40
B) Equipment:
C) Labor:
1 Foreman for 4 day @P 600.00 = P 2,400.00
6 Skilled Worker for 4 day @P 450.00 = P 10,800.00
12 Labor for 4 day @P 350.00 = P 16,800.00
30,000.00
Indirect Cost:
OCM = P 16,860.96
PROFIT = P 11,240.64
Tax/VAT = P 16,860.96
44,962.56
B) Equipment:
C) Labor:
1 Foreman for 4 day @P 600.00 = P 2,400.00
5 Skilled Worker for 4 day @P 450.00 = P 9,000.00
10 Labor for 4 day @P 350.00 = P 14,000.00
25,400.00
Indirect Cost:
OCM = P 11,365.50
PROFIT = P 7,577.00
Tax/VAT = P 11,365.50
30,308.00
B) Equipment:
1 Road Grader for 2 day @P 13,380.08 = P 26,760.16
1 Road Roller for 2 day @P 13,210.00 = P 26,420.00
1 Water Truck for 2 day @P 9,600.00 = P 19,200.00
72,380.16
C) Labor:
1 Foreman for 2 day @P 600.00 = P 1,200.00
2 Labor for 2 day @P 350.00 = P 1,400.00
2,600.00
Indirect Cost:
OCM = P 14,281.22
PROFIT = P 9,520.82
Tax/VAT = P 14,281.22
38,083.26
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay Simasay February 23, 2023
ACCOMPLISHMENT
25.00% 25.00% 25.00% 25.00%
CASH FLOW
239,148.20 239,148.20 239,148.20 239,148.20
CUMULATIVE ACCOMPLISHMENT
25.00% 50.00% 75.00% 100.00%
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay Simasay February 23, 2023
LOCATION: Simasay, Tangub City, Misamis Occidental
Project Manager 1
Project Engineer 1
Materials Engineer 1
Const. Foreman 1
Skilled Worker 6
Laborers 14
TOTAL 24
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay
February 23, 2023
Simasay
LOCATION: Simasay, Tangub City, Misamis Occidental
Backhoe 1
Dumptruck 1
Road Grader 1
Road Roller 1
Water Truck 1
Transit Mixer 1
Concrete Vibrator 1
Concrete Saw 1
Bar Cutter 1
TOTAL 9
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: Rehabilitation of PCCP & Construction of Road Shouldering of Purok 3 Barangay Simasay February 23, 2023
Item No. Description Unit Quantity Unit Cost Total Cost Percentage 5 days 5 days 5 days 5 days 5 days 5 days
III Concrete Works cu.m. 20.10 12,818.43 257,650.44 26.93% 8.98% 8.98% 8.98%
Submitted By:
PERT / CPM
3 DAYS 4 DAYS
V
5 DAYS
Submitted By:
50 DAYS
500(3) 50 DAYS
III
B.5 311(1)
103(1)A B.9
V
5 DAYS
102(2)
B.8(1)
Submitted By:
SGM CONSTRUCTION