Professional Documents
Culture Documents
Construction of Hinterland Road, Sapang Dalaga - Concepcion, Mansawan Road, Misamis Occidental
Construction of Hinterland Road, Sapang Dalaga - Concepcion, Mansawan Road, Misamis Occidental
PROGRAM OF WORKS
Item No. Description Unit Quantity Unit Cost Total Cost Percentage
PROJECT BILLBOARD/
B.5 Each 2.00 8,064.00 16,128.00 0.08%
SIGNBOARD
MOBILIZATION/ Lump
B.9 1.00 78,400.00 78,400.00 0.40%
DEMOBILIZATION Sum
PART C. EARTHWORKS
INDIVIDUAL REMOVAL OF
100(3)a1 TREES (SMALL, 150 - 300 MM Each 4.00 9,264.50 37,058.00 0.19%
DIA.)
INDIVIDUAL REMOVAL OF
100(3)a2 TREES (SMALL, 301 - 500 MM Each 1.00 36,498.00 36,498.00 0.19%
DIA.)
INDIVIDUAL REMOVAL OF
100(3)a3 TREES (SMALL, 501 - 750 MM Each 3.00 12,166.00 36,498.00 0.19%
DIA.)
REMOVAL OF ACTUAL
STRUCTURES/OBSTRUCTION
101(3)a1 Sq.M 278.00 1,056.55 293,720.90 1.50%
(PCCP UNREINFORCED, 0.15 M
THICK)
REMOVAL OF STRUCTURES
101(6) AND OBSTRUCTION Cu.M 10.30 16,457.48 169,512.04 0.87%
(CONCRETE)
SURPLUS COMMON
102(2) Cu.M 52,845.64 24.02 1,269,352.27 6.48%
EXCAVATION
STRUCTURE EXCAVATION
103(1)a Cu.M 578.00 1,240.09 716,772.02 3.66%
(COMMON SOIL)
EMBANKMENT FROM
104(1)a ROADWAY EXCAVATION Cu.M 537.96 3,389.81 1,823,582.18 9.31%
(COMMON SOIL)
SUBGRADE PREPARATION
105(1)a Sq.M 5,866.80 117.94 691,930.39 3.53%
(COMMON MATERIAL)
CRUSHED AGGREGATE
300(2) Cu.M 140.70 3,694.93 519,876.65 2.65%
SURFACE COURSE
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: CONSTRUCTION OF HINTERLAND ROAD, SAPANG
February 23, 2023
DALAGA - CONCEPCION, MANSAWAN ROAD, MISAMIS OCCIDENTAL
BILL OF QUANTITIES
(Columns (1), (2), (3) and (4) are to be filled up by the Procuring Entity ) (Column (5) & (6) are to be filled up by the bidder)
INDIVIDUAL REMOVAL Nine Thousand Two Hundred Thirty Seven Thousand Fifty
100(3)a1 OF TREES (SMALL, 150 - Each 4.00 Sixty Four Pesos and 50/100 Eight Pesos Only
300 MM DIA.)
Php 9,264.50 Php 37,058.00
INDIVIDUAL REMOVAL Twelve Thousand One Hundred Thirty Six Thousand Four
100(3)a3 OF TREES (SMALL, 501 - Each 3.00 Sixty Six Pesos Only Hundred Ninety Eight Pesos Only
750 MM DIA.)
Php 12,166.00 Php 36,498.00
REMOVAL OF ACTUAL Two Hundred Ninety Three
STRUCTURES/OBSTRUCTI One Thousand Fifty Six Pesos
Thousand Seven Hundred Twenty
101(3)a1 ON (PCCP Sq.M 278.00 and 55/100
Pesos and 90/100
UNREINFORCED, 0.15 M
THICK) Php 1,056.55 Php 293,720.90
3,694.93 519,876.65
Two Million Four Hundred
PORTLAND CEMENT Four Thousand Five Hundred Ninety Three Thousand Five
CONCRETE PAVEMENT Twenty Four Pesos and 75/100 Hundred Eighty Nine Pesos and
311(1)a Sq.M 551.10
(UNREINFORCED, 0.15 M 72/100
THICK, 14 DAYS)
4,524.75 2,493,589.72
4,267.73 1,596,131.02
4,604.89 1,013,075.80
NINETEEN MILLION FIVE HUNDRED NINETY FOUR
TOTAL THOUSAND NINE HUNDRED NINETY TWO PESOS AND 19,594,992.84
84/100
Submitted By:
SGM CONSTRUCTION
`
PROJECT NAME: CONSTRUCTION OF HINTERLAND ROAD, SAPANG DALAGA -
February 23, 2023
CONCEPCION, MANSAWAN ROAD, MISAMIS OCCIDENTAL
DETAILED ESTIMATES
B) Equipment:
1 Container Van with ACU for 1 day @P 45,000.00 = P 45,000.00
45,000.00
C) Labor:
Indirect Cost:
OCM = P 6,750.00
PROFIT = P 4,500.00
Tax/VAT = P 6,750.00
18,000.00
B) Equipment:
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
1 Skilled Worker for 1 day @P 450.00 = P 450.00
2 Labor for 1 day @P 350.00 = P 700.00
1,750.00
Indirect Cost:
OCM = P 1,728.00
PROFIT = P 1,152.00
Tax/VAT = P 1,728.00
4,608.00
C) Labor:
1 Safety Officer for 180 day @P 600.00 = P 108,000.00
108,000.00
Indirect Cost:
OCM = P 18,483.00
PROFIT = P 12,322.00
Tax/VAT = P 18,483.00
49,288.00
B) Equipment:
32 Barricade Flasher Light for 36 day @P 6.00 = P 6,912.00
6,912.00
C) Labor:
1 Flagman for 36 day @P 450.00 = P 16,200.00
1 Labor for 36 day @P 350.00 = P 12,600.00
28,800.00
Indirect Cost:
OCM = P 9,901.80
PROFIT = P 6,601.20
Tax/VAT = P 9,901.80
26,404.80
B) Equipment:
1 Low Bed Trailer for 2 trips @P 28,000.00 = P 56,000.00
56,000.00
C) Labor:
Indirect Cost:
OCM = P 8,400.00
PROFIT = P 5,600.00
Tax/VAT = P 8,400.00
22,400.00
PART C. EARTHWORKS
100(1) CLEARING AND GRUBBING 0.52 Hectare
A) Materials:
B) Equipment:
1 Payloader for 3 day @P 13,800.00 = P 41,400.00
2 Dumptruck for 3 day @P 11,360.00 = P 68,160.00
1 Backhoe for 3 day @P 12,200.00 = P 36,600.00
146,160.00
C) Labor:
1 Foreman for 3 day @P 600.00 = P 1,800.00
2 Labor for 3 day @P 350.00 = P 2,100.00
3,900.00
Indirect Cost:
OCM = P 22,509.00
PROFIT = P 15,006.00
Tax/VAT = P 22,509.00
60,024.00
B) Equipment:
1 Backhoe for 1 day @P 12,200.00 = P 12,200.00
1 Dumptruck for 1 day @P 11,360.00 = P 11,360.00
1 Chainsaw for 1 day @P 600.00 = P 600.00
24,160.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
1 Skilled Worker for 1 day @P 450.00 = P 450.00
2 Labor for 1 day @P 350.00 = P 700.00
1,750.00
Indirect Cost:
OCM = P 3,970.50
PROFIT = P 2,647.00
Tax/VAT = P 3,970.50
10,588.00
B) Equipment:
1 Backhoe for 1 day @P 12,200.00 = P 12,200.00
1 Dumptruck for 1 day @P 11,360.00 = P 11,360.00
1 Chainsaw for 1 day @P 600.00 = P 600.00
24,160.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
1 Skilled Worker for 1 day @P 450.00 = P 450.00
2 Labor for 1 day @P 350.00 = P 700.00
1,750.00
Indirect Cost:
OCM = P 3,910.50
PROFIT = P 2,607.00
Tax/VAT = P 3,910.50
10,428.00
B) Equipment:
1 Backhoe for 1 day @P 12,200.00 = P 12,200.00
1 Dumptruck for 1 day @P 11,360.00 = P 11,360.00
1 Chainsaw for 1 day @P 600.00 = P 600.00
24,160.00
C) Labor:
1 Foreman for 1 day @P 600.00 = P 600.00
1 Skilled Worker for 1 day @P 450.00 = P 450.00
2 Labor for 1 day @P 350.00 = P 700.00
1,750.00
Indirect Cost:
OCM = P 3,910.50
PROFIT = P 2,607.00
Tax/VAT = P 3,910.50
10,428.00
REMOVAL OF ACTUAL
101(3)a1 STRUCTURES/OBSTRUCTION (PCCP 278.00 Sq.M
UNREINFORCED, 0.15 M THICK)
A) Materials:
B) Equipment:
1 Backhoe for 5 day @P 12,200.00 = P 61,000.00
1 Backhoe w/ Pavement Breaker for 5 day @P 15,500.00 = P 77,500.00
1 Dumptruck for 5 day @P 11,360.00 = P 56,800.00
195,300.00
C) Labor:
1 Foreman for 5 day @P 600.00 = P 3,000.00
2 Skilled Worker for 5 day @P 450.00 = P 4,500.00
4 Labor for 5 day @P 350.00 = P 7,000.00
14,500.00
Indirect Cost:
OCM = P 31,470.00
PROFIT = P 20,980.00
Tax/VAT = P 31,470.00
83,920.00
B) Equipment:
1 Backhoe w/ Pavement Breaker for 3 day @P 15,500.00 = P 46,500.00
1 Backhoe for 3 day @P 12,200.00 = P 36,600.00
1 Dumptruck for 3 day @P 11,360.00 = P 34,080.00
117,180.00
C) Labor:
1 Foreman for 3 day @P 600.00 = P 1,800.00
2 Labor for 3 day @P 350.00 = P 2,100.00
3,900.00
Indirect Cost:
OCM = P 18,162.00
PROFIT = P 12,108.00
Tax/VAT = P 18,162.00
48,432.00
B) Equipment:
1 Backhoe for 18 day @P 12,200.00 = P 219,600.00
1 Payloader for 18 day @P 13,800.00 = P 248,400.00
2 Dumptruck for 18 day @P 11,360.00 = P 408,960.00
876,960.00
C) Labor:
1 Foreman for 18 day @P 600.00 = P 10,800.00
3 Labor for 18 day @P 350.00 = P 18,900.00
29,700.00
Indirect Cost:
OCM = P 135,999.00
PROFIT = P 90,666.00
Tax/VAT = P 135,999.00
362,664.00
B) Equipment:
1 Backhoe for 14 day @P 12,200.00 = P 170,800.00
2 Dumptruck for 14 day @P 11,360.00 = P 318,080.00
488,880.00
C) Labor:
1 Foreman for 14 day @P 600.00 = P 8,400.00
3 Labor for 14 day @P 350.00 = P 14,700.00
23,100.00
Indirect Cost:
OCM = P 76,797.00
PROFIT = P 51,198.00
Tax/VAT = P 76,797.00
204,792.00
B) Equipment:
1 Backhoe for 16 day @P 12,200.00 = P 195,200.00
1 Payloader for 16 day @P 13,800.00 = P 220,800.00
2 Dumptruck for 16 day @P 11,360.00 = P 363,520.00
1 Road Grader for 16 day @P 13,380.00 = P 214,080.00
1 Road Roller for 16 day @P 13,210.00 = P 211,360.00
1 Water Truck for 8 day @P 9,600.00 = P 76,800.00
1,281,760.00
C) Labor:
1 Foreman for 16 day @P 600.00 = P 9,600.00
2 Labor for 16 day @P 350.00 = P 11,200.00
20,800.00
Indirect Cost:
OCM = P 195,384.00
PROFIT = P 130,256.00
Tax/VAT = P 195,384.00
521,024.00
B) Equipment:
1 Road Grader for 16 day @P 13,380.00 = P 214,080.00
1 Road Roller for 16 day @P 13,210.00 = P 211,360.00
1 Water Truck for 5 day @P 9,600.00 = P 48,000.00
473,440.00
C) Labor:
1 Foreman for 16 day @P 600.00 = P 9,600.00
2 Labor for 16 day @P 350.00 = P 11,200.00
20,800.00
Indirect Cost:
OCM = P 74,136.00
PROFIT = P 49,424.00
Tax/VAT = P 74,136.00
197,696.00
B) Equipment:
1 Road Grader for 14 day @P 13,380.00 = P 187,320.00
1 Road Roller for 14 day @P 13,210.00 = P 184,940.00
1 Water Truck for 14 day @P 9,600.00 = P 134,400.00
506,660.00
C) Labor:
1 Foreman for 14 day @P 600.00 = P 8,400.00
2 Labor for 14 day @P 350.00 = P 9,800.00
18,200.00
Indirect Cost:
OCM = P 135,631.50
PROFIT = P 90,421.00
Tax/VAT = P 135,631.50
361,684.00
B) Equipment:
1 Road Grader for 6 day @P 13,380.00 = P 80,280.00
1 Road Roller for 6 day @P 13,210.00 = P 79,260.00
1 Water Truck for 1 day @P 9,600.00 = P 9,600.00
169,140.00
C) Labor:
1 Foreman for 6 day @P 600.00 = P 3,600.00
2 Labor for 6 day @P 350.00 = P 4,200.00
7,800.00
Indirect Cost:
OCM = P 55,701.00
PROFIT = P 37,134.00
Tax/VAT = P 55,701.00
148,536.00
B) Equipment:
4 Transit Mixer for 21 day @P 10,500.00 = P 882,000.00
2 Concrete Vibrator for 21 day @P 730.00 = P 30,660.00
1 Concrete Screeder for 21 day @P 4,360.00 = P 91,560.00
1 Water Truck for 21 day @P 9,600.00 = P 201,600.00
1 Concrete Saw for 21 day @P 1,750.00 = P 36,750.00
1 Bar Cutter for 10 day @P 260.00 = P 2,600.00
1,245,170.00
C) Labor:
1 Foreman for 21 day @P 600.00 = P 12,600.00
4 Skilled Worker for 21 day @P 450.00 = P 37,800.00
12 Labor for 21 day @P 350.00 = P 88,200.00
138,600.00
Indirect Cost:
OCM = P 267,170.55
PROFIT = P 178,113.70
Tax/VAT = P 267,170.55
712,454.80
B) Equipment:
4 Transit Mixer for 36 day @P 10,500.00 = P 1,512,000.00
1 Concrete Vibrator for 36 day @P 730.00 = P 26,280.00
1 Concrete Screeder for 36 day @P 4,360.00 = P 156,960.00
1 Water Truck for 36 day @P 9,600.00 = P 345,600.00
1 Concrete Saw for 36 day @P 1,750.00 = P 63,000.00
1 Bar Cutter for 12 day @P 260.00 = P 3,120.00
2,106,960.00
C) Labor:
1 Foreman for 36 day @P 600.00 = P 21,600.00
4 Skilled Worker for 36 day @P 450.00 = P 64,800.00
12 Labor for 36 day @P 350.00 = P 151,200.00
237,600.00
Indirect Cost:
OCM = P 472,217.55
PROFIT = P 314,811.70
Tax/VAT = P 472,217.55
1,259,246.80
B) Equipment:
1 Bar Cutter for 14 day @P 1,758.00 = P 24,612.00
1 Bar Bender for 14 day @P 2,812.00 = P 39,368.00
1 Cargo Truck for 6 day @P 6,264.00 = P 37,584.00
101,564.00
C) Labor:
1 Foreman for 14 day @P 600.00 = P 8,400.00
2 Skilled Worker for 14 day @P 450.00 = P 12,600.00
8 Labor for 14 day @P 350.00 = P 39,200.00
60,200.00
Indirect Cost:
OCM = P 88,420.65
PROFIT = P 58,947.10
Tax/VAT = P 88,420.65
235,788.40
B) Equipment:
2 One Bagger Mixer for 37 day @P 1,376.00 = P 101,824.00
2 Concrete Vibrator for 37 day @P 972.00 = P 71,928.00
2 Water Truck for 4 day @P 9,600.00 = P 76,800.00
250,552.00
C) Labor:
1 Foreman for 37 day @P 600.00 = P 22,200.00
8 Skilled Worker for 37 day @P 450.00 = P 133,200.00
16 Labor for 37 day @P 350.00 = P 207,200.00
362,600.00
Indirect Cost:
OCM = P 189,249.00
PROFIT = P 126,166.00
Tax/VAT = P 189,249.00
504,664.00
B) Equipment:
1 One Bagger Mixer for 13 day @P 1,376.00 = P 17,888.00
1 Water Truck for 13 day @P 9,600.00 = P 124,800.00
142,688.00
C) Labor:
1 Foreman for 13 day @P 600.00 = P 7,800.00
2 Skilled Worker for 13 day @P 450.00 = P 11,700.00
8 Labor for 13 day @P 350.00 = P 36,400.00
55,900.00
Indirect Cost:
OCM = P 171,014.10
PROFIT = P 114,009.40
Tax/VAT = P 171,014.10
456,037.60
B) Equipment:
1 Backhoe for 5 day @P 12,200.00 = P 61,000.00
1 One Bagger Mixer for 14 day @P 1,376.00 = P 19,264.00
1 Water Truck for 3 day @P 9,600.00 = P 28,800.00
109,064.00
C) Labor:
1 Foreman for 14 day @P 600.00 = P 8,400.00
2 Skilled Worker for 14 day @P 450.00 = P 12,600.00
8 Labor for 14 day @P 350.00 = P 39,200.00
60,200.00
Indirect Cost:
OCM = P 108,543.90
PROFIT = P 72,362.60
Tax/VAT = P 108,543.90
289,450.40
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: CONSTRUCTION OF HINTERLAND ROAD, SAPANG DALAGA - CONCEPCION, MANSAWAN ROAD,
February 23, 2023
MISAMIS OCCIDENTAL
LOCATION: CONCEPCION, MISAMIS OCCIDENTAL
ACCOMPLISHMENT
25.00% 25.00% 25.00% 25.00%
CASH FLOW
4,898,748.21 4,898,748.21 4,898,748.21 4,898,748.21
CUMULATIVE ACCOMPLISHMENT
25.00% 50.00% 75.00% 100.00%
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: CONSTRUCTION OF HINTERLAND ROAD, SAPANG DALAGA - CONCEPCION, MANSAWAN
February 23, 2023
ROAD, MISAMIS OCCIDENTAL
LOCATION: CONCEPCION, MISAMIS OCCIDENTAL
Project Manager 1
Project Engineer 1
Materials Engineer 1
Const. Foreman 1
Safety Officer 1
Flagman 1
Skilled Worker 12
Laborers 22
TOTAL 40
Submitted By:
SGM CONSTRUCTION
PROJECT NAME: CONSTRUCTION OF HINTERLAND ROAD, SAPANG DALAGA - CONCEPCION,
February 23, 2023
MANSAWAN ROAD, MISAMIS OCCIDENTAL
Payloader 1
Dumptruck 2
Backhoe 1
Chainsaw 1
Plate Compactor 1
Water Truck 2
Road Grader 1
Road Roller 1
Transit Mixer 4
Concrete Vibrator 2
Concrete Screeder 1
Concrete Saw 1
Bar Cutter 1
TOTAL 25
Submitted By:
Item No. Description Unit Quantity Unit Cost Total Cost Percentage 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days 10 days
PROJECT BILLBOARD/
B.5 Each 2.00 8,064.00 16,128.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SIGNBOARD
OCCUPATIONAL SAFETY AND
B.7(1) Month 6.00 28,751.33 172,507.98 0.88% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05%
HEALTH PROGRAM
B.8(1) TRAFFIC MANAGEMENT Month 6.00 15,402.80 92,416.80 0.47% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
MOBILIZATION/ Lump
B.9 1.0 78,400.00 78,400.00 0.40% 0.20% 0.20%
DEMOBILIZATION Sum
100(1) CLEARING AND GRUBBING Hectare 0.5 404,007.69 210,083.99 1.07% 0.64% 0.43%
INDIVIDUAL REMOVAL OF
100(3)a1 TREES (SMALL, 150 - 300 MM Each 4.00 9,264.50 37,058.00 0.19% 0.19%
DIA.)
INDIVIDUAL REMOVAL OF
100(3)a2 TREES (SMALL, 301 - 500 MM Each 1.00 36,498.00 36,498.00 0.19% 0.19%
DIA.)
INDIVIDUAL REMOVAL OF
100(3)a3 TREES (SMALL, 501 - 750 MM Each 3.00 12,166.00 36,498.00 0.19% 0.19%
DIA.)
REMOVAL OF ACTUAL
STRUCTURES/OBSTRUCTION
101(3)a1 Sq.M 278.00 1,056.55 293,720.90 1.50% 0.75% 0.75%
(PCCP UNREINFORCED, 0.15 M
THICK)
SURPLUS COMMON
102(2) Cu.M 52,845.64 24.02 1,269,352.27 6.48% 2.59% 2.27% 1.62%
EXCAVATION
STRUCTURE EXCAVATION
103(1)a Cu.M 578.00 1,240.09 716,772.02 3.66% 2.19% 1.46%
(COMMON SOIL)
EMBANKMENT FROM ROADWAY
104(1)a Cu.M 537.96 3,389.81 1,823,582.18 9.31% 4.65% 3.26% 1.40%
EXCAVATION (COMMON SOIL)
SUBGRADE PREPARATION
105(1)a Sq.M 5,866.80 117.94 691,930.39 3.53% 2.05% 1.48%
(COMMON MATERIAL)
200(1) AGGREGATE SUBBASE COURSE Cu.M 350.90 3,607.56 1,265,892.80 6.46% 3.23% 3.23%
404(1)a REINFORCING STEEL (GRADE 40) Kg. 9,601.90 85.95 825,283.30 4.21% 2.53% 1.68%
506(1) STONE MASONRY Cu.M 220.00 4,604.89 1,013,075.80 5.17% 3.10% 2.07%
50 DAYS
500(3) 50 DAYS
III
B.5 311(1)
103(1)A B.9
V
5 DAYS
102(2)
B.8(1)
Submitted By:
SGM CONSTRUCTION