Professional Documents
Culture Documents
Chapter 15
Chapter 15
Chapter 15
15.2.1. n = 0.014.
1.1
200 m
150 m
2.1 1.2
150 m
3.1
The solution for this problem is given in the following table. Figure P15.2.1 (b)
has been used to determine the rainfall intensities.
1 2 3 4 5 6 7 8 9 10
Sewer Elevation Length Slope Total Catchment Incremental C CA CA
(m) (m) (m/m) drained area
area (km2)
(km2)
1.1 300 200 0.020 0.01 1.1 0.01 0.60 0.006 0.006
1.2 298 150 0.013 0.008 1.2 0.008 0.75 0.006 0.006
2.1 296 150 0.010 0.005 2.1 0.005 0.80 0.004
1.1
1.2
0.023 0.016
3.1 294.5 150 0.010 3.1
11 12 13 14 15 16 17 18 19 20
Inlet Upstream tc Td i Design Computed Pipe Flow Sewer
time sewer (min) (min) (mm/hr) discharge, diameter size velocity flow
(min) flow time Qp (m3/s) (m) used (m/s) time
(min) (mm) (min)
25 Na 25 25 45.7 0.077 0.248 250 1.56 2.13
20 Na 20 20 50.8 0.085 0.279 300 1.21 2.07
15 Na 15
25 2.13 27.13
20 2.07 22.07
15.2.2. n = 0.014.
1.1
200 m
150 m
2.1 1.2
150 m
3.1
The solution for this problem is given in the following table. Figure P15.2.1 (b)
has been used to determine the rainfall intensities.
1 2 3 4 5 6 7 8 9 10
Sewer Elevation Length Slope Total Catchment Incremental C CA CA
(m) (m) (m/m) drained area
area (km2)
(km2)
1.1 300 200 0.020 0.01 1.1 0.01 0.60 0.006 0.006
1.2 298 150 0.013 0.008 1.2 0.008 0.75 0.006 0.006
2.1 296 150 0.010 0.005 2.1 0.005 0.80 0.004
1.1
1.2
0.023 0.016
3.1 294.5 150 0.010 3.1
11 12 13 14 15 16 17 18 19 20
Inlet Upstream tc Td i Design Computed Pipe Flow Sewer
time sewer flow (min) (min) (mm/hr) discharge, diameter size velocity flow
(min) time (min) Qp (m3/s) (m) used (m/s) time
(mm) (min)
25 Na 25 25 69.85 0.117 0.291 300 1.66 2.01
20 Na 20 20 81.28 0.137 0.334 350 1.42 1.76
15 Na 15
25 2.01 27
20 1.76 21.8
15.2.3. The IDF curve for Phoenix for T = 10 years is used for this problem. n = 0.014.
A layout of the sewer system is shown below.
1000 ft
800 ft
m/s
For a sudden expansion, K = 1.0. Hence,
m.
m/s
Since > 40o, Figure 15.2.9 is used to determine Kb. For = 45o and r/D = 2,
Kb = 0.18.
15 – 4
ft
B 4
Step 4) Compute 1.0
Do 4
Step 5)
Step 15)
Step 16) The upstream inline pressure elevation is 475.7 + 0.59 476.3 ft.
15.2.7. The coefficient of variation of each parameter is computed in the following table.
For a uniform distribution, , ,
15.2.8. The coefficient of variation of each parameter is computed in the following table.
For a triangular distribution:
, ,
15.2.9. From the solution to problem 15.2.7, = 6.90 x 10-2 and = 6.95 x 10-2.
= = 0.80(5)(10) = 40.0 cfs.
= = 50.56 cfs.
= = 6.90 x 10-2(40) = 2.76 cfs
= = 6.95 x 10-2(50.56) = 3.51 cfs.
= 50.56 – 40 = 10.56 cfs.
= 4.47 cfs.
15.2.10. From the solution to example 15.2.6, = 67.50 cfs, = 3.05 cfs,
= 71.51 cfs, = 2.63 cfs. Thus,
, .
The formula for risk using the safety factor approach was given in Chapter 10 as
where = and =
Hence, = (17.11)
15 – 7
1
z
Area, A = m2
m
m/s
Minimum velocity necessary to avoid silt deposition ranges from 0.6 to 0.8 m/s.
Thus the computed velocity is slightly higher than the minimum velocity. OK.
Add 0.5 m of freeboard resulting in a channel depth of about 2.5 m.
1
z
b
15 – 8
Area, A = m2
m
m/s
Minimum velocity necessary to avoid silt deposition ranges from 0.6 to 0.8 m/s.
Thus the computed velocity is slightly higher than the minimum velocity. OK.
Add about 0.5 m of freeboard resulting in a channel depth of about 2.8 m.
Thus,
15 – 9
y = 2.26 m
R = 0.5y = 0.5(2.26) = 1.13 m
Again, check for : design = RSo = 9810(1.13)(0.0016) = 17.74 N/m2
= 1.81 kg/m2.
design < allowable (3.22 kg/m2).
m
Thus, the following design specifications may be used: Gravel rip-rap with D50 =
5 cm, depth of flow of 2.26 m and bottom width of 2.61 m. The cross-section is
the best hydraulic trapezoidal channel cross-section, which is half a hexagon.
A 0.5 m freeboard may be added to the flow depth.
y = 2.89 m
for the best hydraulic triangular sections. Note that for triangular
sections, R is significantly different from y.
m.
Check for : design = RSo = 9810(1.02)(0.0016) = 16.04 N/m2 = 1.64 kg/m2.
design > allowable (1.61 kg/m2). Hence, the lining may not be acceptable.
Use a gravel rip-rap of D50 = 5 cm (allowable = 3.22 kg/m2).
Again, referring to Table 15.3.1, for D50 = 5 cm, and y 60 cm, n = 0.034.
15.3.6
Compute the stem stiffness using MEI = 24.5h2.26 (N·m2) for dormant grass, where h =
0.2 m, so MEI = 24.5(0.2)2.26 = 0.645 N·m2
ks = 0.055
15.3.7
Compute the stem stiffness using MEI = 319h3.3 for green grass, where h = 0.2 m
so MEI = 319(0.2)3.3 = 1.57 N·m2
15.3.8
Compute the stem stiffness using MEI = 24.5h2.26 (N·m2) for dormant grass, where h =
0.2 m, so MEI = 24.5(0.2)2.26 = 0.645 N·m2
ks = 0.055
15.3.9
Compute the stem stiffness using MEI = 319h3.3 for green grass, where h = 0.2 m
so MEI = 319(0.2)3.3 = 1.57 N·m2
15.3.10
15 – 14
15 – 15
15.3.11
15 – 16
15 – 17
15.3.12
15.2.13
15.3.14
For Kentucky blue grass this is a Class C (Table 15.3.5) so τp = 1 lb/ft2 (Table 15.3.4)
Solving R=3.205 ft which can be used to compute the depth of flow y = 4.67 ft and
A = 158.8 ft2
With the hydraulic radius the Manning’s roughness factor can be determined using
15.3.15
Solving R= 1.923 ft which can be used to compute the depth of flow y = 2.505 ft and
A = 68.9 ft2
With the hydraulic radius the Manning’s roughness factor can be determined using
Solving R=3.205 ft which can be used to compute the depth of flow y = 4.67 ft and
A = 158.8 ft2
With the hydraulic radius the Manning’s roughness factor can be determined using
15.4.1. QA = 30 ft3/s.
min where tb is the time form the beginning to a
point on the recession limb of the inflow hydrograph where the flow is 5% of the
peak.
Vr = 30 min(133 cfs)(60 s/min) = 239,400 ft3 = 5.5 ac-ft (note 1 ac-ft = 43560 ft3)
Hence, Vs = 0.94Vr = 0.94(5.5) = 5.17 ac-ft.
133 cfs
I(t)
0.05(133)/133
tp
2tp
15 – 20
The following Figure is drawn for this problem based on Abt and Grigg’s
assumptions.
Q
133 cfs
30 cfs
x
30 min 60 min
The critical storm duration, tD, can be obtained by using Newton’s iteration
method. From equation (15.4.19),
=
15 – 21
Let tD = 70 min.
= -0.017
Hence, min.
min.
This solution appears to be reasonably close enough to the actual solution. tD may
be assumed to be about 71.8 min.
cfs.
Let tD = 75 min.
15 – 22
= -0.015
Hence, min.
cfs.
tD = 21.54 min.
cfs.
tD = 23.37 min.
cfs.
15.4.7. To solve this problem, first the storage outflow relationship is developed using the
stage outflow data given. The result is obtained as shown in the following table.
H Q S 2S/t + Q Q H Q S 2S/t + Q Q
(ft) (cfs) (ft3) (cfs) (cfs) (ft) (cfs) (ft3) (cfs) (cfs)
0.0 0 0 0 0 5.5 156 479160 955 156
0.5 3 43560 76 3 6.0 173 522720 1044 173
1.0 8 87120 153 8 6.5 190 566280 1134 190
1.5 17 130680 235 17 7.0 205 609840 1221 205
2.0 30 174240 320 30 8.0 231 696960 1393 231
2.5 43 217800 406 43 9.0 253 784080 1560 253
3.0 60 261360 496 60 10.0 275 871200 1727 275
3.5 78 304920 586 78 11.0 323 958320 1920 323
4.0 97 348480 678 97 12.0 340 1045440 2082 340
4.5 117 392040 770 117 12.1 341.7 1054152 2099 341.7
5.0 137 435600 863 137
Note that the last data point (given in bold face italic font) have been extrapolated
since the required 2S/t + Q versus Q data exceeded the range of the derived
relationship from the given data.
Using the above 2S/t + Q versus Q relationship, the routing can be performed.
The result is given in the following table.
cfs
ft
ft
ft.
Q(2.59) = 46.06 cfs (by interpolation from the head-discharge table).
The iterations for H3, H4, and so on are done in a similar fashion from which the
result given in the following table is obtained.
Q (cfs)
m
Q(H2) = Q(0.47) = 0.52 m3/s.