E-5 RFT Final Report 2021
E-5 RFT Final Report 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5
Virgin Naphtha Splitter Feed / Naphtha Hydrofiner Feed
Exchanger
October 18, 2021
Report Prepared by
Bradford Dozier
bdozier@techcorr.com
Report Submitted to
Brian Case
Brian.Case@petrojam.com
—TABLE OF CONTENTS—
1. WORK SCOPE
2. TEST RESULTS
3. OBSERVATIONS
7. TEST PARAMETERS
9. CALIBRATION DATA
APPENDIX
b. Calibration Graphics
c. Analysis Graphics
e. Contact Us
Preface
This report has been formatted to present all findings prior to any other content. Supporting content will follow the test
results.
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
2. TEST RESULTS
97.80% of the tubes were tested. Most of the tubes did not have any relevant defect
indications. One tube was found to have a 56% wall loss indication in an isolated area
near the floating tubesheet. The rest of the tubes with indications had minor to moderate
general corrosion type indications found in random areas along the length of the tubes.
Obstructions due to unknown reasons. Remote field testing (RFT) cannot detect most
flaws at the tubesheets or baffles.
Indications that represent: # of tubes:
Total Number of Tubes (Straight Sections in U-Bend Tubes) 273
Total Number Tubes / Sections Tested 267
No Discernable Defects Detected (NDD) 161 N
10% to 19% wall loss / Minor 84 1
20% to 29% wall loss / Moderate 17 2
30% to 39% wall loss / Moderate 3 3
40% to 49% wall loss / Moderate 1 4
50% to 59% wall loss / Severe 1 5
60% to 69% wall loss / Severe 0 6
70% to Through Wall Hole (TWH) / Severe 0 7
Obstructed tubes in the Test Pattern No Test (OBS) 5
Mechanically Plugged Tubes No Test (PLG) 1 ▲
NDD
10% to 19%
20% to 29%
30% to 39%
40% to 49%
50% to 59%
60% to 69%
70% to TWH
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
Limitations: The Remote Field Test (RFT) examination method, typically has an
accuracy of + or - 10%, with a maximum tolerance of 19.99%. This accuracy can be
effected by the limitations encountered. When performing any electromagnetic
examination, it is important to understand the variations in the test system and test
specimen, as well as the parameters that effect data output. The following is a list of
some of the forms of variation that are commonly encountered that may have an effect
on the data generated when performing a Remote Field Test.
Tube Cleanliness Localized Permeability Electrical Noise / Interference
Probe Fill Factor Magnetic Deposits Geometry
Dented Area Tubesheet Area Composition Changes
Bulged Area Tube Support Area Temperature Changes
Edge Effect Residual Magnetism Conductivity Changes
3. OBSERVATIONS
Previous Tube Test: Previous inspection in 2018 reported one indication to 55% wall loss.
Tubesheet TS1 (test end): No relevant visual indications.
Tubesheet TS2: No relevant visual indications.
Baffles: N/A in shell
Tube O.D.: N/A in shell
Tube I.D.: Scale. Tube end Damage
Shell: N/A
Other:
N N N N N N N N N N N N N N N N
15 N N N N N N N N N N N N N N N 1 15, 16
N N 1 1 1 N N N N N N N N N www.TechCorr.com
Company: Petrojam
N O N 1 1 N N N N N N O Location: Kingston Jamaica
Unit:
18 1 N N N N N N N 18, 8 Equip.Number: E-5
Service: VN Splitter Feed / NH Feed Exchanger
Material: SA-179
Stationary End Size: 3/4"x.083"x240"
Inspection Type: RFT
Analyst: Bradford Dozier
Date: 10/18/2021
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
Row 1
Tube 1
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
Observation Photographs
Exchanger Overview
Plant: Petrojam
Unit / Area: Crude
Equipment Number: E-5
Virgin Naphtha Splitter Feed / Naphtha Hydrofiner
Service:
Feed Exchanger
Built: N/A. Re-tubed sometime after 2014
National Board Number: N/A
Serial Number: N/A
Tube Material: SA-179
Type of Equipment: Shell and Tube Heat Exchanger
Tube Bundle: Floating
Bundle Orientation: Horizontal
Tube Type: Straight
Tube Surface: Prime
Joint Type: Rolled
Total Tubes in Exchanger: 273
Type of Test: Remote Field (RFT)
Total Tubes Tested: 267
Inspection End (TS1): Stationary Tubesheet
Row Orientation: Top to bottom
Tube Orientation: Left to right
Tube OD: .75”
Tube Wall Thickness: .083”
Tube Length: 240”
Tubes Mechanically Plugged: 1
The tube material type and dimensions as necessary to perform the test are provided by the client.
Inaccurate tube data will affect the final results and quantifications.
Tube data is recorded while testing and analyzed post testing with results documented in a tubesheet tube
map format and data sheets giving indication types, quantifications, and locations presented in this report.
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
9. CALIBRATION DATA
Personnel
TechCorr utilizes highly trained and qualified personnel. Quality begins with TechCorr
maintaining personnel specialized in tube examinations. TechCorr personnel have been
through formal and specific classroom training, have received supervised On-The-Job training
hours and have been tested and qualified through TechCorr's extensive Quality Control
Program, which surpasses the American Society of Non-Destructive Testing's ASNT-TC-1A.
The equipment operator is required to pass extensive "mock bundle" tests, that are establish in
the industry for qualifying personnel prior to performing work in that plant or facility. Once in the
field, the equipment operator will acquire the data and have it analyzed within 48hrs by a Level
II Data Analyst. A preliminary report will then be issued representing the tubes and defects
depths found in the tubes. Formal reports will then follow within 1 day or less from the
completion of the analysis.
Calibration Standard(s)
Type Material Dimension Serial Number
Standard 1: Multipurpose RFT SA-214 C/S 3/4” x .083” RFT 21-211
Standard 2:
Test Instrument Settings
Frequency Drive Amplitude Differential Gain Absolute Gain
Frequency 1: 600 Hz X KHz 4 Volts 65 dB 56 dB
Frequency 2: 500 Hz X KHz 4 Volts 65 dB 56 dB
Frequency 3: Hz KHz
Frequency 4: Hz KHz
Mix Freq. 1: N/A KHz N/A N/A
Mix Freq. 2: N/A KHz N/A N/A
Sample Rate: 400 Hz Acquisition Mode Differential and Absolute
Bandwidth: 22 Hz Probe Type Bobbin/Conventional
Filter Cut Off Diff: 10 Hz Order 4 Scan Direction Pulling out
Filter Cut Off Abs: 10 Hz Order 4 Max Scan Speed 1’ per sec.
Applicable Code
ASTM-RFT-E2096-00. Standard Practice for In Situ Examination of Ferromagnetic Heat
Exchanger Tubes Using Remote Field Testing.
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
APPENDIX
Appendix A
Appendix B
CALIBRATION GRAPHIC
Appendix C
Petrojam October 18, 2021
Kingston, Jamaica
Remote Field Inspection Report
E-5 Virgin Naphtha Splitter Feed / Naphtha
Hydrofiner Feed Exchanger
Inspected By: Bradford Dozier Level IIA
Appendix D
Standard of Care
In performing the services requested, TechCorr USA, LLC used the degree of care and
skill ordinarily practiced under similar conditions by others performing such services in
the same or similar locality. All procedures and reference specifications are the current
revision, at the time of the examination. Additional client procedures may be listed or
referenced, but as a minimum TechCorr USA, LLC procedures mandate the quality
level performed during this examination. No other warranties or guarantees, expressed
or implied is intended by TechCorr USA, LLC.
Disclaimer
While all efforts have been made to exercise due diligence for care and caution,
TechCorr USA, LLC cannot assume any liability for damage, leakage, loss of
containment , environmental damage, loss of production, injury (personnel and plant), or
the like associated with the subject. It is understood by all parties that the measurement
techniques used and discussed are non-invasive. As a result, the data provided may
not be indicative of the actual condition and are deductive in nature. TechCorr USA,
LLC is not liable for any misrepresentation of results or conditions. All
recommendations are based upon similar experience, standard industry standards, and
best engineering practice. This report is not to be construed as a guarantee or warranty
of the materials tested. All orders are subject to TechCorr USA, LLC Standard Terms
and Conditions, which are available upon request.
Appendix E
Contact Us
Please feel free to contact us for any questions, comments, work scheduling, planning
or quotations. Also for any changes that may be needed in the report, Client Field
Ticket(s) or invoices.
Our corporate office is located at:
1485 East Sam Houston Parkway South, Suite 160
Pasadena, Texas 77503.