Professional Documents
Culture Documents
1
8/20/2023
Pre-Construction phase:
o It covers major part of investigations, planning and design.
o It is organized in several consecutive studies:
i. Reconnaissance study
ii. Pre-feasibility study
iii. Feasibility study
Er. Jagarnath Shah_Chapter 3.0
2
8/20/2023
Implementation phase:
o It covers engineering and construction of the projects.
o It consists the following activities:
i. Design and procurement:
a. definite plan study
b. final design
c. tender/contract document
d. tendering and contracting
ii. Detailed design and working drawings
a. Detailed design and preparation of working drawings for civil,
structural and transmission works.
b. Detailed design and preparation of working drawings for
electro-mechanical Er.and hydro-mechanical equipments.
Jagarnath Shah_Chapter 3.0
Operation phase:
o The HPP starts for revenue generation and research and
training works shall be carried out in parallel to the
operation of the project.
3
8/20/2023
4
8/20/2023
o From land use map, we can estimate the number of people to be displaced,
submerged area of village, fertile land etc. and to estimate compensation to
resettle to another place.
5. Stability:
6. Accessibility:
o If the site is near to load centre, it will reduce the cost of transmission line
works and also reduce the power losses during transmission.
Er. Jagarnath Shah_Chapter 3.0
8. Morphological study:
10
5
8/20/2023
6
8/20/2023
13
14
7
8/20/2023
15
16
8
8/20/2023
17
18
9
8/20/2023
19
20
10
8/20/2023
o It is a bankable document.
22
11
8/20/2023
23
Construction:
Consultant – Owner Contractor – supplier
i. Contract management i. Civil engineering work
ii. Detail design and working drawing ii. Hydraulic steel work
iii. Material control iii. Mechanical equipment
iv. Construction management iv. Electrical equipment
v. Site management and construction v. Transmission line
Supervision vi. Engineering details
Er. Jagarnath Shah_Chapter 3.0
vii. Erection and testing
24
12
8/20/2023
Operation:
• Operation and maintenance by owner
• Power generation facilities, dams, waterways
• Transmission lines and sub stations
• Revenue generation
• Research and training works shall be done parallel to operation of
plants
25
26
13
8/20/2023
% of time % of time
27
14
8/20/2023
29
30
15
8/20/2023
S1
S2
32
16
8/20/2023
33
34
17
8/20/2023
V1²/2g hʟ
P1/γ
V2²/2g
Q
P2/γ
Z1
Datum Z2
1 2
Er. Jagarnath Shah_Chapter 3.0
35
36
18
8/20/2023
i. Discharge of any river varies over a wide range, high discharge are
available only for short duration in a year.
38
19
8/20/2023
C (1+i)ᵑ * i P
Total annual cost = --------------- + ------- ---------------------- (2)
Er. Jagarnath Shah_Chapter 3.0
(1+i)ᵑ - 1 100
39
Power Estimation:
• Following steps should be followed for estimation of power:
i. Draw flow duration curve (FDC)
ii. Draw Power duration curve (PDC)
iii. Determine best installed capacity (BIC)
iv. Determine firm power and secondary power.
Er. Jagarnath Shah_Chapter 3.0
40
20
8/20/2023
41
• Besides above, there are many other formulae employing simple extrapolation
from past records to more complex correlations:
i. Scheer formula:
10ᶜ
G = -------------
U⁰˙¹⁵
Where, G = annual growth in generation in %.
U = per capita generation
C = constant
= 0.02 (population growth rate) + 1.33
Er. Jagarnath Shah_Chapter 3.0
42
21
8/20/2023
E = KM⁰˙⁶ (2)⁰˙⁴⁶⁵ᵗ
Where, E = electricity consumption
M = index of manufacture or production
K = adjustment factor
t = time for which consumption is to be projected
43
Reservoir Planning:
• When a barrier is constructed across a river or streams in the form of
dam, water gets stored on the u/s side of the barrier, forming a pool of
water, is called reservoir.
• Dams and reservoirs are complementary to each other. They require
very careful planning, design and operation.
• Dam and reservoir planning such as selection of dam and reservoir site,
fixation of reservoir capacity, safe yield or storage and other connection
works has very important role for development of multipurpose
projects.
44
22
8/20/2023
45
i. Hydropower
ii. Irrigation
iv. Navigation
vii. Recreation
46
23
8/20/2023
Reservoir regulation:
o The water level in the reservoir will normally fluctuate between the
normal pool level (NPL) and the minimum pool level (MinPL). The storage
between these two limits will be maximum conservation of water which is
sufficient for satisfying the irrigation need.
Er. Jagarnath Shah_Chapter 3.0
47
o Normal floods will be absorbed in the capacity lying below the NPL and
severe floods shall be absorbed by the capacity lying between NPL and
Maximum pool level (MaxPL). Spillway starts discharging water as soon as
the water level starts rising above the NPL.
o During monsoon, the irrigation demand is almost nil and water will be
released only for hydropower generation. The reservoir level will thus
continue to rise steadily. The rise in water level is allowed to reach the NPL
by the end of monsoon season.
48
24
8/20/2023
49
50
25
8/20/2023
Surcharge storage:
o The storage between the MaxPL and NPL is called surcharge storage.
o It is actually the storage made during flood time and if needed, may be
disposed d/s by spillway.
o This storage cannot be stored for later use.
Dead storage:
o The storage below the MinPL is called dead storage.
o It is below the outlet and hence, this storage cannot be used for any purpose.
o This ideal capacity of the storage has to be provided so as to accommodate the
deposition of silt in the reservoir.
Er. Jagarnath Shah_Chapter 3.0
51
Valley storage:
o The amount of water stored in the river before the dam
construction is the valley storage.
o After completion of dam construction, reservoir is formed and
storage goes on increasing.
Net increase in storage
= storage capacity of reservoir – natural valley storage
Bank storage:
o When a reservoir is full, a part of storage enters the permeable
soil as seepage. When the reservoir level falls down, this seepage
from the permeable soil comes out and contributes to the
storage, which is known as bank storage.
Er. Jagarnath Shah_Chapter 3.0
52
26
8/20/2023
53
Reservoir Capacity:
• The reservoir capacity can be estimated on the basis of mass curve which
has to be adjusted to account for dead storage, evaporation loss and carry-
over storage.
54
27
8/20/2023
55
• River water normally carries certain amount of silt eroded from the catchment
during heavy rain or due to high run-off velocity.
• The extent of erosion i.e. silt or sediment load in the river depends upon the
nature of soil, topography, vegetation cover, intensity of rainfall, technique of
soil conservation and watershed management.
• The sediment particles try to settle down to the bottom due to gravitational
force but may be kept in suspension due to upward current in turbulent inflow.
• When water reaches a dam site or reservoir, the velocity and turbulence
decreases and coarser particles settle down in the head reaches of the
reservoir and suspended and finest particles settle towards further down
reaches of the reservoir.
• Some fine particles in suspension may escape from dam through spillway,
sluice gate etc.
Er. Jagarnath Shah_Chapter 3.0
56
28
8/20/2023
57
c. Aggradations of reservoir
58
29
8/20/2023
• R S Varshney has given the following formula to estimate the suspended load:
S = 1.534/A⁰˙²⁶⁴
Where, S = mean annual sediment in the reservoir in million M³ per 100 Km².
o In case of Nepal, for area from 5000 sq.km to 6000 sq.km, this formula
gives 5% error. Er. Jagarnath Shah_Chapter 3.0
59
Vent + Went
Vexit
Vdep
Here, Vent = entered suspended sediment
Went = entered bed sediment
Vdep = volume of deposited sediment
Vexit = volume of sediment exit through the sluice gate or other way.
60
30
8/20/2023
1. Pre-construction measures
i. Proper selection of dam or reservoir site
ii. Construction of dam in stages (i.e. initially dam is designed for low depth
and then height of dam is raised after getting silt deposition)
iii. Construction of series of check dams to control debris and landslide flow
in the reservoir
iv. Vegetation cover or screen on u/s of reservoir site and on the catchment
area to arrest the large amount of sediment.
v. Control of sediment inflow in the reservoir by providing series of small low
dams in sandy river to arrest the sediment on u/s of reservoir.
Er. Jagarnath Shah_Chapter 3.0
61
62
31
8/20/2023
63
Capacity of reservoir V
Capacity inflow ratio, CIR = ----------------------------------------- = -------
Total inflow in to the reservoir Q
64
32
8/20/2023
65
Life of reservoir:
• The dead storage in the reservoir is provided to accommodate the sediment.
• When the sediment inflow is more, dead storage within few years gets fully
silted and sediment begins to encroach the useful storage.
• The useful life of the reservoir is said to exist till the useful storage is reduced
to 20% of the designed capacity.
• The estimation of useful life of reservoir is made by:
i. Work out CIR in % and find annual loss of reservoir capacity
ii. Find the correction factor for settlement and consolidation of deposited
sediment which is about 15% of total over a period of 200 years.
iii. Work out η and CIR for different reservoir capacity from graph or table.
iv. Ascertain the total load for a given period, capacity curves are determined
at interval of 25, 50, 75, 100 years etc. and so on and then check up the
quantity of water in different zones of reservoir.
v. A plot may be developed to show the available capacity in different zones
and total capacity against time period. From this plot, it is easy to evaluate
Er. Jagarnath Shah_Chapter 3.0
the failure period and this period is taken as life of reservoir.
66
33
8/20/2023
67
68
34
8/20/2023
69
70
35
8/20/2023
General layout of dam, intake & desander w.r.t. river geometry near the dam
71
72
36