Professional Documents
Culture Documents
1
OUTLINE
Hydropower development
Socio-economic analysis
Environmental analysis
Efficiency of hydropower
2
CHAPTER-2: Planning and Development Process
2.1 Hydropower Development
4
con’t
Project investigation, planning and designing are normally
organized in several consecutive studies:
Resource studies
Resource inventories(lists)
Resource ranking
Site specific studies
Reconnaissance studies
Pre-feasibility studies
Feasibility studies
oThe main purpose of resource inventory investigation is to
identify, register and catalog the hydropower resources
existing in the river basins; areas; districts; and provinces.
o The identified project sites are ranked according to size,
cost, electric demand, etc. 5
Site Specific Studies
Reconnaissance studies
The first stage of hydropower investigation is the
identification of projects.
If this has not been done as part of the resource studies,
It must be carried out as part of the reconnaissance study.
Such study are of preliminary natures, their purpose is
not to investigate projects in detail
Being the first step of project planning, reconnaissance
studies are concerned with identification as well as
investigation of projects which are suitable to the stated
purpose (supplying of an identified power market with
electric power and energy).
6
Cont’d
The main objectives of this study may be:
Assessment of demand or define electric power need
Selection of candidate projects from the resource
inventories which will meet the electric power demand
Investigation of candidate projects and project alternatives
to the best technical level (stated purpose)
Technical ranking of candidate projects should be
prepared and well recorded.
Selection of a suitable project from the list of investigated
candidate projects
Estimation of preliminary cost and implementation
schedule
7
Cont’d
Main activities to be done in this stage
Data collection
Infrastructure information
Power market and demand forecast, Hydrology, Topograp
Geology and geotechnical engineering, Environmental
studies
Socio-economic set up
Office studies
Power demand forecast, Flow regulation
Head, environmental constraints
Field work and reconnaissance report
8
Pre-feasibility study (Preliminary Design)
In this study one or more project alternatives are proposed and
studied before selection.
The main purpose of pre-feasibility is to:
Establish demand for the project
Formulate a plan for developing this project
Assess if the project is technically, economically and environmentally
acceptable
Make recommendation for future action
9
CONT…
The following aspects are to be investigated during pre-feasibility study:
1. Hydrologic Study:
Source extent amount, occurrence and variability of water.
Present, past and future needs of water.
Include opportunities for control and development of water.
Quality of water in terms of its physical and chemical properties.
Sediment quality and quantity.
Existing water rights should be recognized for each and every
stakeholder.
2. Power studies: this considers a balance between power supply and
demand.
3. Layout Planning: a comprehensive layout plan will be prepared and
should be supplemented with sufficient number of drawings, which will
be used for preparation of the bill of quantities. 10
CONT…
4. Geology and foundation engineering
5. Seismic (earthquakes) studies
6. Environmental studies
7. Estimation of cost
8. Economic and financial studies
9. Future investigation plan
10. Pre-feasibility report:
A clear statement should be made in respect of technical, economical
and environmental feasibility of the project.
It should give clear indication whether or not to study the project in
more detail.
11
Feasibility study
Feasibility studies are carried out to determine the
technical, economical and environmental viability of a
project.
This phase of investigation consists of a detailed study
which is directed towards the ultimate permission,
financing, final design and construction of the project under
investigation.
The main part of feasibility studies include:
1. Data Collection
*Socioeconomic data *Population
* Income distribution * Power market
*Tariffs * Hydrology
*Topography * Geology & enviroment
CONT…
2. Project parameter estimation
* Power and energy estimation * Power system studies
* Water resources studies * Geology and foundation
conditions
* Seismic studies * Construction materials
*Existing infrastructure
3. Layout Optimization
*Project layout * Sediment and control
measures
* Number and size of units * Auxiliary equipment
*Transmission planning
13
CONT…
4. Environmental studies
Assessment of environmental disturbance and their
mitigation measures
5. Engineering design
Intake structure and sediment excluder
Headrace and tailrace
Powerhouse
Dimensioning and preparation of specification for hydro
turbine and electromechanical equipment
Construction facilities
14
CONT…
6. Estimation of project cost
Project cost
Operation, maintenance and replacement
Environmental cost
Construction planning and budgeting
Contingencies and other costs
7. Economical and financial analysis
8. Future steps to be taken for the project implementation
9. Feasibility Report
15
Implementation Phase
16
Socio- Economic Analysis
Introduction
Electricity is one of the most important inputs for economic
development of a country.
An economic analysis is based on the benefits and costs from the
view point of society as whole, should include both tangible and
intangible benefits & costs in the analysis.
While a financial analysis is viewed from the perspective of the
project sponsor, and states whether the tangible value of the output
of the project will be sufficient :-
To amortize (pay back) the project loan
To pay operation and maintenance cost
To meet the interest on other financial obligation
17
Cont….
A series of information documents must be assembled in an orderly
fashion before the analysis can be conducted:
Information on the input of the project:- the capital cost of civil
engineering and electromechanical equipment; operating and
maintenance costs; useful life of the civil engineering and electro
mechanical equipment
Information on project construction:- the period of construction, its
progress and data of putting into operation.
Information on hydropower plant parameters:- peak power, installed
capacity and annual generation of the power plant.
Information from market analysis:- the energy purchaser, rate of
capacity and energy(tariff), equipment and labor costs and obtained
from the planning department of the government.
Information from financing:- fund sources and funding; its yearly
18
installment (payment) during construction; interest rate
Economic and Financial feasibility?
19
Economics of Power Generation
The art of determining the per unit (i.e., one kWh) cost of production
of electrical energy is known as economics of power generation
(EPG).
A consumer will use electric power only if it is supplied at reasonable
rate. Therefore, power engineers have to produce electric power as
cheap as possible.
Some important terms in EPG:
I. Economic Life (useful life):
It is the time during which the project can be operated normally
In general
30-40 years for civil engineering
15-25 years for turbine generator sets
10-15 years for diesel sets.
Renewal of the main parts of the equipment in civil engineering is
needed after that period.
20
CONT…
II . Depreciation:- The decrease in the value of the power plant
equipment and building due to constant use is known as depreciation.
This reduction in the value of plant every year is known as annual
depreciation.
III. Present worth:- is a sum of money at the present, the value of an
investment at the present, or the value of money expended in the future
discounted back to the present.
The sum of these values represents the net present value(NPV).
IV. Future worth:- is a sum of money at a future time, the value of a
future investment, or the value of an expenditure at present discounted
out to that future time.
V. Interest:-is the price paid for borrowing money and expressed as a
percentage of the amount borrowed(discount rate). The social interest
rate are different in different countries; usually it takes around 10%.
21
VI . Annual Equivalent Value
22
2.1 Cost of Electrical Energy
The total cost of electrical energy generated can be divided;
i. Fixed cost:- is independent of maximum demand and units
generated.
eg. interest on capital cost of land and salaries of high officials.
ii. Semi-fixed cost:-is depends upon maximum demand but
independent of units generated. The maximum demand on the power
station determines its size and cost of installation.
Eg. Salaries of management, clerical staffs
(iii). Running cost:-is depends only upon the number of units
generated.
is on account of annual cost of fuel, maintenance, repairs and
salaries of operating staff. Since these charges depend upon the
energy output, the running cost is directly proportional to the number
of units generated by the station.
23
Cash Flow Calculations
A cash flow diagram is a graphic representation of cash flow with
magnitude of expenditures(costs) and (benefits)receipts plotted
vertically and time represented on the horizontal scale.
The distance along the horizontal scale represents time.
29
Cont’d
Annual costs:- include the annual capital cost and the annual
operation and maintenance costs, the later involving salaries, material
expenses, water fees, overhaul expenses, interim replacement and
administration, etc
Benefits:
The direct benefits is mainly from the benefits of the energy sale
as in the following expression:
𝐵𝑒 =𝐸𝑒 (1-β)(1-ϒ)P
Where 𝐵𝑒 =benefit from energy sale,𝐸𝑒 =effective annual energy
generation,β =plant use factor,ϒ=Grid loss factor ,P- Energy price
i.e. the total net energy output given out by the generator of the
hydropower plant during the year after the deduction of energy
loss in outage.
In the above equation 𝐸𝑒 (1-β)(1-ϒ) represents the amount of
electric energy on sale 30
Cont’d
31
Methods Of Economic Appraisal (Assessment)
1. The net present value method(NPV)
This method is useful for ranking multiple projects.
If we set the first year of construction as the base year the
procedure is to discount the net benefit (i.e. benefits minus
cost) from each year to the base year, then to obtain their
cumulative sum.
𝑛 𝐵𝑗 −𝐶𝑗
NPV=σ𝑗=0
(1+𝑖)𝑗
If NPV is negative, the project should be rejected as it is
expected that the benefits during its lifetime will be
insufficient to cover the project costs. Assuming that there
are not any restrictions with respect to the required initial
capital among projects or alternative design solutions with
positive NPV the best ones will b with greater NPV.
2. The Benefit – Cost Ratio Method
The benefit–cost ratio is the ratio of the present value of
benefit to that of cost
The criterion B /C ≥ 1
The B/C ratio does not give the amount of net benefit.
33
3. The internal rate of return method (IRR)
IRR is that discount rate at which the net present value is
equal to zero.
IRR is calculated through an iterative process, which is
suitable for spread sheet computer processing.
Like the NPV, IRR incorporates all the pertinent(relevant)
All projects that have an internal rate of return less than
the opportunity cost of capital should be rejected.
The criterion for selection between different alternatives is
normally to choose the investment with the highest rate of
return.
The IRR expression is:
34
Environmental analysis
When building, during normal operation, in the case of an accident
and at the end of the operation of a hydroelectric power station, the
environmental effects discussed below might occur.
1.Construction:-Water pollution caused by construction material or fine
soils getting into the stream, release of fine particles caused by
excavation, improper cleaning of building machinery, etc.
2.Normal operation:- During the operation of hydroelectric power
stations, no toxic substances are released directly, with the exception of
potential lubricant losses
3.Malfunctio:- If an accident occurs in an operation, If dams or weirs
fail, this can have a large impact on the population and the flora and
fauna.
4.End of Operation:-The actual hydroelectric power components are
mainly built from metallic material with recognized and generally
environmentally friendly disposal methods.
35
Event person or
thing affected priority impact
During • Noise • Low
• Low
construction • Accident • Low
• Wild life • Emission
• Forest • Noise • Medium
disturbances
Accident • Better access
future • Medium
• Worker
• Medium
production
loss
• Major
injures or • Medium
death • high
36
The following is a comprehensive checklist that might
be used in developing and using methodologies.
i. Natural considerations:
a. Terrestrial b. Hydrological
• Soils • Surface water levels
• Landforms • Surface water quantities
• Seismic activity • Surface water quality
c. Biological • Ground water levels
• Vegetation • Groundwater quantities
• Fish and aquatic life • Groundwater quality
• Birds d. Atmospheric
• Terrestrial animals • Air quality
• Air movement
37
ii. Cultural and human considerations:
38
Other Social and Political Considerations
40
41