Extension Of Nasser Institute Hospital

DOCUMENT TITLE:

INSPECTION AND TEST PLAN

EARTHWORKS
(Excavation and Backfilling)

Document No.:

ITP- ENIH-SC-014

Segment Quality
Sr. Quality Engineer Project Manager
Manager

00 24/01/2021 Initial release Hazem Sharaf Essam Salah Mohamed Yosri

Rev Date Rev details Prepared by Checked by Approved by

Page 1 of 3
Extension Of Nasser INSPECTION AND TEST PLAN Document No.: ITP ENIH-SC-014
Institute Hospital EARTH WORKS Rev.: 00

FORMS INDEX

NO. FORM NO. DESCRIPTION


1 FM-104-1001 Earth work Report
Certified test
2 Test report provided by a third party “Laboratory”
Report

Note: The referenced forms are included in and controlled by the referenced document. The latest revision of these forms
will be used.

Page 2 of 3
Extension Of Nasser Institute Hospital

Inspection and Test Plan


FOR EARTH WORKS

Contractor Hassan Allam Construction


Package No.
Description of Work EARTH WORKS Ref.ITP NO : HAC-DAR-TOD-ENIH-SC-014
Location Hospital Building Rev : 00
Date : 8/26/2023

Inspection involvment Verification


Sr#. Description of Activity Test/ Inspection Reference Document Acceptance Criteria Frequeney
Document
HAC DAR
1.0-EXCAVATION
•Before any excavation works,
site shall be surveyed by the
Surveyor inspection for setting out and contractor to establish existing Approved Method Statement
• Surveying Report
1.1 excavation limits (Topographical survey before ground level. Egyptian Code for Soil & N/A Perior starting work H W
• Approved IR
works). •Marking for the excavation Mechanics
limits to be matching with the
project specification.
•Inspection for level of bottom Approved Method Statement
Surveying for Bottom level of the excavation • Surveying Report
1.2 excavation prior to start Egyptian Code for Soil & N/A Perior start replacement H H
(form level). • Approved IR
replacement soil. Mechanics
•Bottom of excavation shall
be compacted by suitable
compactor which enough to
control the disturbance soil ASTM 1195
1.3 Testing for bottom of excavation after finish excavation. Egyptian Code for Soil & As per geotechnical report 500 m2 H H • 3rd party report
•Plate load test shall be Mechanics
performed for bottom of
excavation to check soil
bearing capacity.
2.0 Fill, Backfill and Replacement soil
Approved Method Statement
Replacement soil, Fill and backfill material •Sieve analysis and proctor to
2.1 Egyptian Code for Soil & N/A Perior start replacement H W • 3rd party report
conformation and suitability be checked.
Mechanics
•Suitability of the used
material • Minimum degree of
•Compaction test for the compaction (Percentage
Approved Method Statement
Rplacement and compaction for replacement, fill layers from Maximum dry
2.2 Egyptian Code for Soil & Every 250 M2 H W • Approved IR
and backfill material (sand cone test) density) to be: 95%
Mechanics
-Thickness of each layer not • Thickness of each layer
exceed 250mm not exceed 250mm

Abbreviations and Definitions:


S: Surveillance - Random checkpoint.
W: Witness - Not allowed to start the Next Phase, if the inspection body not present at the date and time stipulated in the examination request.
H: Holdpoint - Not allowed to start the Next Phase, until the examination and acceptance of the inspection body.
R: Review Documents