Professional Documents
Culture Documents
Activity: Earthworks Project: Contract No. 18 - 57B - Western Division Unseal road upgrade
ITP Number: / EAR / Location:
Drawing & Revision No:
Preliminary works
Contractors Ensure all the underground services
Existing Service Location Permit to Dig Prior to Excavation
Rep are identified and Marked
PWD
Contractors Check if clearing is as per contract
Clearing and Grubbing specification Site Inspection As Required
Rep Drawing and Specifcation
Section 201
Technical
Engineer's Check if all agreed silt,erosion& dust Prior to earthworks
Drainage Specification HOLD POINT Site Inspection
Assistant control measures are installed commences
D4.2
PWD
Engineer's
Stockpiling specification & HOLD POINT Site Inspection Engineer's Approval Identification of Dump Site
Assistant
TNZ F/1
minimum <2 - 500mm (constructed
and compacted in 2 layers of 250
DCP inferred CBR to 1m 1 test at the centre of each
Contractors normainal thickness
depth on the prepared lane, or part thereof, at 50m
Rep >2 300mm (constructed and
subgrade intervals .
compacted in 2 layers of 150
normainal thickness
Contractors
HOLD POINT Subgrade Cut Visual Check each section
Rep
Contractors
Proof Rolling Visual R.L 50mm above to 50mm
Rep
below design level
PWD
Contractors Manufacturers
Geotextlie – materials specification Visual Check each lot (1 roll)
Rep compliance certificate
and TNZ F/1
Directional placement Visual
1 check per 100m2 of
PWD Tensioning laps Visual material placed with a
Geotextlie – construction TNZ F/7 specification Contractor Rep
Spacing Visual minimum of 3 tests for area
and TNZ F/1
covered
Damage Visual
PWD
Engineer's Notify Engineer a
Inspection of finished cut / fill areas specification HOLD POINT Engineer's approval On completion
Assistant minimum of 48 hours
and TNZ F/1
Activity: Stormwater Drainage Project: Contract No. 18 - 57B - Western Division Unseal road upgrade
ITP Number: / SWD / Location:
Drawing & Revision No:
Materials
PWD
Contractors
Foundation specification Material Approved Ap 65 As Required
Rep
& TNZ F/1
PWD
Contractors
Bedding& Haunching specification Submit Engineer's Approval Prior to start
Rep
& TNZ F/1
As per the contract Drawing,Should
PWD
Contractors also comply PWD 501 the
Pipes & fitting specification Specification Prior to start
Rep manufractures instruction and good
501
trade practice
Construction
PWD
Contractors
Pipe Bedding specification Visual As per Pipe Bedding Clause 501.02 As required
Rep
501
PWD
Contractors As per laying and jointing pipe Clause
Laying& Jointing Pipes specification Visual As required
Rep 501.09
501
PWD
Contractors
Drainage Structure specification Visual As per Drainage Structure Clause 1 As required
Rep
501
PWD
Contractors As per Backfilling& Compactiob
Backfilling&Reinstatement specification Visual As required
Rep standard 501.12
501
PWD
Contractors Should be completed with atleast
Surfacing of Trenches specification Visual As required
Rep 150mm compacted fill material
501
Inspection
Engineers Commencement of
General 20.3.1 Engineers Approval Every Layer
Assistant Stages
All required test needs to be
Testing 20.3.2 Contractor Rep Submit Every Layer
completed
Activity: Subbase Project: Contract No. 18 - 57B - Western Division Unseal road upgrade
ITP Number: / SUB/ Location:
Drawing & Revision No:
Activity: Base- Course Project: Contract No. 18 - 57B - Western Division Unseal road upgrade
ITP Number: /BAS/ Location:
Drawing & Revision No:
Verification
Contractors
Check pavement width Visual PWD specification 302.02 © 1 per 20m
Rep
PWD specification Tolerance: -30mm
PWD Contractors
Redress Surface Visual +30mm 2 per 20m
specification Rep
302 Materials Contractors
for Pavement Rep /
Surface check Construction HOLD POINT Visual Dipping Every 20m
Engineers
Assistant
Contractors Tech Spec D4.6 Clegg Impact Hammer
Compaction Visual Continuous
Rep testing at every 40m