10K NEOM Residential Community - 1
Contract: Engineering Procurement & Construction Contract
CC Ref: 10K-4800000621
QA/QC Corrective Action Plan Report CAPR
Summary of QC Corrective action per subject plan:
As of the 27th of August, today accomplished KPI is 84.20% against 61.7%
1. QA/QC fully coordinated with the Construction team and focused on clearing pending NCR/INCR/SQN/SON – and
results found within 2 weeks from Aug. 16th to Aug. 27th, 2023 Action made improved as of the latest up-to-date KPI
61.7% to 84.20%
2. As of Aug. 16th, Overall Pending 7 NCRs were targeted and closed 6 NCRs / one (1) remain till date Aug. 27, 2023
3. As of Aug. 16th, to 27th overall SWI / SQN /SON is 65 and closed 40 remaining 25 most of it ongoing, QC daily
monitoring till subject to offer for closing.
a. Day-by-day site activities are closely monitored by QA/QC. General SWI receiving regularly to clients are
concentrated and any rectification made for closing accomplished SWI immediate action is performed to
submit in aconex.
b. Proactive SWI, in general, is advised by Construction continually to improve quality performance at all site
work to avoid unnecessarily re-doing work.
4. WIR & MIR revise and resubmit issue QC follow-up on all pending document requirements, construction rectifications
and immediate action is our must. The overall inspection rejection ratio as of Aug. 27 th, 2023 is -7.15% over 100%
5. See below QA/QC MATRIX for the references.
Table of contents:
ITEM # DESCRIPTION
1. Project Quality KPI MATRIX calculator
2. STATUS OF CLIENT NCR DATA
3. STATUS OF N&P INCR DATA
4.
STATUS OF CLIENT SWI STANDARD VIOLATIONS
5. STATUS OF N&P SQN/SON STANDARD VIOLATIONS
6. STATUS OF N&P WIR
7. STATUS OF N&P MIR
01 Project Quality KPI MATRIX calculator
Project Quality KPI
Project: 10K NRC – 1 CC: 480000621 QAQC Department
Month: Aug. 16 - AUG 27 2023 Date: (AUG. 27, 2023)
KPI Criteria Value / Quantity Impact on PQI
Audit NCR -5 % * NCR 0 0.0%
INCR -0.5 % * NCR 2 -1.0%
NCRs INCR Exceed ACD -1 % * NCR 0 0.0%
INCR Rep. -2 % * NCR 0 0.0%
Client NCR -5 % * NCR 1 -5.0%
Total -6.0%
CIR Rejection Ratio - 0.4 % * WIR(RR) % 0.8% -0.3%
CIR Failure Rate - 0.2 % * WIR(FR) % 0.0% 0.0%
Inspections
MIR Rejections Including Revisions - 0.5 % * MIR # 0 0.0%
Total -0.3%
WRR Joint -1 % * WRRJ 0.00% 0.0%
Weld Rejection Rates
WRR Linear -25 % * WRRL 0.000% 0.0%
Total 0.0%
Site Quality "Internal" SQN Violation 0.25 % * SQN 4 1.0%
Notifications "Client" LBE/SI - Violation -0.5 % * NCR 21 -10.5%
Total -9.5%
Overall -15.8%
PQI 84.2%
2 STATUS OF CLIENT NCR DATA
Section Number for Requirement Completion Date by
Action to be taken <Date> (Actual or
Client-driven frequency box Estimated)
0 N&P QA/QC department focused on the 5 NCRs to be closed as As promised to recover
Client NCR ACTIVE (-5%) 01 minor
1 promised with full coordination with our team Construction. deviated KPI due to NCRs
CIV MEC ELE ARC STR
1-NCR only balance for Mech’l issue potable water and fire hydrant 4 NCRS closed
OPEN CLOSE OPEN CLOS OPEN CLOS OPEN CLOS OPE CLOSE flushing Zone 1 Type A&B 1 NCRS open for water
E E E N
potable flushing in Type
0 3 1 6 0 0 0 0 0 0 Note: Only potable balance the fire hydrant system flushing completed A&B Zone 1
3 STATUS OF N&P INCR DATA
Section Number for Requirement Completion Date by
Action to be taken <Date> (Actual or
NAP QC-driven frequency box Estimated)
0 QA/QC closed 2 INCR QA/QC followed up with
EPC INCR ACTIVE (-2%) 02 minor
1 N&P sustainability for
CIV MEC ELE ARC STR QA/QC 2 remaining INCR issue is for MAT submittal pending for review submittal
OPEN CLOSE OPEN CLOS OPEN CLOS OPEN CLOS OPE CLOSE sprinklers and installation at the site without MIR approval and no WIR
E E E N
0 0 2 2 0 2 0 0 0 0
4 STATUS OF CLIENT SWI STANDARD VIOLATIONS
EXTERNAL SITE WORK INSTRUCTION LOG (SWI)
Discipline Received From NAD Close Open Rejected
CIV - Civil 16 12 4 0
MEC - Mechanical 24 12 12 0
ARC- Architectural 2 0 2 0
ELE - Electrical 9 6 3 0
QMN 1 1 0 0
TOTAL 52 31 21 0
5 STATUS OF N&P SQN/SON STANDARD VIOLATIONS
SITE OBSERVATION REPORT LOG (SOR/SQN) FROM N&P QC
Discipline From NAP Close Open Rejected
CIV - Civil 2 2 0 0
ELE - Electrical 6 3 3 0
MEC - Mechanical 5 4 1 0
TOTAL 13 9 4 0
6 STATUS OF N&P WIR
B-
A - Work C - Revise AWAITING
OVERALL WIR Incorporate D-
RAISED May and FOR PROGRESS
SUMMARY Comments - Rejected
Proceed Resubmit APPROVAL
Proceed
ARCHITECTURAL 9 0 7 1 0 1 77.78%
CIVIL 753 26 693 14 9 11 94.29%
SURVEY 0 0 0 0 0 0 #DIV/0!
STRUCTURAL 3 0 3 0 0 0 100.00%
ELECTRICAL 225 29 144 2 14 36 70.67%
MECHANICAL 268 12 185 23 7 41 70.90%
OVERALL TOTAL 1,258 67 1,032 40 30 89 84.98%
WIR REVISIONS PROGRES CHART
84.98%
90.00%
DISCIPLINE - REVISION 01 02 03 04 05 80.00%
70.00%
ARCHITECTURAL 9 0 0 0 0
60.00%
CIVIL 742 11 0 0 0
50.00%
SURVEY 0 0 0 0 0 40.00%
30.00%
STRUCTURAL 3 0 0 0 0
20.00%
ELECTRICAL 223 2 0 0 0 10.00%
0.00%
MECHANICAL 254 10 0 0 0
PROGRESS
Overall 1231 23 0 0 0
7 STATUS OF N&P MIR
C - Revise
B-
A - Work and
OVERALL MIR Incorporate D- Under
RAISED May Resubmit PROGRESS
SUMMARY Comments - Rejected Review
Proceed - Do Not
Proceed
Proceed
ARCHITECTURAL 0 0 0 0 0 0 #DIV/0!
CIVIL 43 0 43 0 0 0 100.00%
SURVEY 0 0 0 0 0 0 #DIV/0!
STRUCTURAL 3 0 3 0 0 0 100.00%
ELECTRICAL 69 1 59 1 0 8 86.96%
MECHANICAL 68 0 61 7 0 0 89.71%
OVERALL TOTAL 183 1 166 8 0 8 91.26%
MIR REVISIONS
PROGRES CHART
91.26%
100.00%
04
DISCIPLINE - REVISION 01 02 03 05 80.00%
ARCHITECTURAL 0 0 0 0 0
60.00%
CIVIL 40 3 0 0 0
SURVEY 0 0 0 0 0 40.00%
STRUCTURAL 3 0 0 0 0 20.00%
ELECTRICAL 63 0 0 0 0 0.00%
MECHANICAL 68 0 0 0 0 PROGRESS
Overall 174 3 0 0 0