BILL OF QUANTITY

Date: August 28,2023


Subject: Qoutation for Wall Panel, Gypsum and Metal Ceiling Works (Labor Cost)
Project: North-South Commuter Railway CP: N-01 (Malolos-Minalin)
Location: Apalit, Pampanga, Philippines

Unit Rate
NO. Item No. Description Specification Unit Qty. Amount Remarks
Material Construction Total

A Apalit Station

1 Wall Panel

T= 2.3mm Galvanized Steel Panel Wall Cladding on 100 x 100 x 9 x2 3mm Steel Channel Vertical and 75 x75 x 15 x2.3mm
1.1 506(2) Steel Channel Horizontal Frame with Rockwool Insulation including Joint Sealant and AlI Required Fixing Accessories sq.m 363.00 - 800.00 800.00 290,400.00
(Fluorores in Paint for Steel Channel)

Expanded Aluminum Wall Fluorores in Paint Finish including 100 × 50 × 5 × 7.5mm Steel including
1.2 606(4) sq.m 1,954.00 - 800.00 800.00 1,563,200.00
T9mm x W65mm Galvanized Steel Fasteners and T=3mm Stainless Steel Bracket and All Necessary Accessories

2 Gypsum Ceiling

T=100mm Perforated Acoustic Gypsum Board with T= 9.5mm Moisture-Resistant Gypsum Board on
2.1 542(1) C01 Ceiling sq.m 151.00 - 500.00 500.00 75,500.00
LGS Ceiling Suspension System

3 Metal Ceiling

3.1 544(1) C02 Ceiling Lay-in metal ceiling w/ Rockwool on exposed Tee hot dipped galvanized fire-rated metal framing with ceiling trim sq.m 946.00 - 575.00 575.00 543,950.00

3mm Dia. 6mm O/C AISI Type 316 SS, Stainless Steel louver (Open area: 42%) Ceiling weave by 4 x
3.2 544(4) C04 Ceiling 1.5mm Dia. Stainless Steel wire at O/C including T=50mm (50kg/m3) Rockwool Acoustic insulation on louver ceiling. sq.m 5,992.00 - 575.00 575.00 3,445,400.00
24mm Dia Galvanized Steel Hanger Rods

3.3 544(5) C05 Ceiling Catcher and Wire Mesh Netting Ceiling including Hangers sq.m 4,769.00 - 575.00 575.00 2,742,175.00

3.4 544(7) T=2.3mm Steel Sheet Panel Fluororesin Paint Finish for Soffit of Stairs and Escalator sq.m 685.00 - 575.00 575.00 393,875.00

3.5 544(8) C06 Ceiling T=3mm, Mesh Pitch=76mm, Aluminum Expanded Metal Ceiling with Powder Coat Finish sq.m 1,630.00 - 575.00 575.00 937,250.00

Total 9,991,750.00

Terms of payment & Condition:


1.) Mobilization Upon Signing Contract
2.) Weekly Progress Billing (per accomplishment)
3.) Plans and Design not included in this proposal
4.) Water and Electricity not included in this proposal
5.) Scafolding and other equipment and tools - Owner/Gencon Expenses
6.) Proposal Valid 3 days from the date of proposal

Prepared By: Engr. Aldrian C. Frias Conforme: