Professional Documents
Culture Documents
Prime Cost Template
Prime Cost Template
Direct Materials: £ £ £
Material AB1 Assembly 6kg @ £10 60.00
Finsihing 8kg @£10 80.00 140.00
Direct Labour:
Skilled Assembly 2hrs @£18 36.00
Finishing 1hrs @£18 18.00 54.00
Direct Expenses:
Machine Hire 300.00
PRIME COST 818.00
Job Cost Statement Job Ref 123/ADR
Direct Materials: £ £ £
Material AB1 Assembly 75kg @ £0.50 37.50
Finsihing 8.5kg @£0.50 4.25 41.75
Direct Labour:
Skilled Assembly 7hrs @£32.80 229.60
Finishing 1.25hrs @£32.80 41.00 270.60
Direct Expenses:
Machine Hire 1250.00
PRIME COST 1856.10
Job Cost Statement Job Ref ADFABG128ADS
Direct Materials: £ £ £
Material AB1 Assembly 35kg @ £0.75 26.25
Finsihing 2.4kg @£0.75 1.80 28.05
Direct Labour:
Skilled Assembly 2hrs @£43.40 86.80
Finishing0.5hrs @£43.40 21.70 108.50
Direct Expenses:
Machine Hire 2000.00
PRIME COST 2297.55
Direct Labour:
Skilled Assembly 2hrs @£43.40 86.80
Finishing0.5hrs @£43.40 21.70 108.50