DESCRIPTION OF ITEM: RATE ANAYLISIS SPEC.

NO:
ITEM CODE: UNIT (BRITISH): SM
ITEM NAME: DOOR

DETAIL
Flush door 1.5"thick including iron mongery excluding chowkat & lock : Shesham

MATERIAL QTY UNIT RATE(PKR) AMOUNT


Wood --deodar 0.0755 Cft 6000.00 Cft 453
Wood --Partal 0.0539 Cft 1670.00 Cft 90
Veneer : Commercial 2.000 Sft 143.75 Sft 288
Nails 0.0715 Kg 400 Kg 29
Hings 5" 0.1429 Doz 1280 Doz 183
Handles 6" 0.1071 No 90 No 10
Door Stops 6" 0.0715 No 300 No 21
Tower Bolt 10" 0.0715 No 190 No 14
TOTAL MATERIAL 74.94 % 1,086
LABOUR
Skilled Labour 0.0104 day 1000 day 10.4
Carpanter 0.0243 day 1800 day 43.74
TOTAL LABOUR 6.56 % 54
Sundries (Labour Only):3% 1.624

1142

CONT. PROFIT +OVER HEADS (MATERIAL +LABOUR+EQUIPMENT): 19.5 % 222.74

COMPOSITE RATE PER Sft RS. 1,365 COST PER SM : 14,687