Owner: Francisca Frando

Project Location Bungtolan Daya, Vigan City


Project Title: Piggery

ITEM DESCRIPTION QUANTITY UNIT MATERIAL COST/PC UNIT COST


I CIVIL WORKS
1.1 CHB 5" 665.00 PCS 13.50 8,977.50
1.2 CEMENT 87.00 BAGS 215.00 18,705.00
1.3 SAND 7.94 CBM 450.00 3,573.00
1.4 GRAVEL 3\4" 13.93 CBM 650.00 9,054.50
1.5 10MM. DIA. REBAR 35.00 PCS 118.00 4,130.00
1.6 12MM. DIA. REBAR 32.00 PCS 165.00 5,280.00
1.7 G.I PIPE 2" SCHED #20 8.00 PCS 1650 13,200.00
1.8 G.I WIRE # 16 7.00 KGS 85.00 595.00
1.9 3/8" ORD. PLYWOOD 5.00 PCS 500.00 2,500.00
Total 66,015.00

II ROOFING WORKS
2.1 ORD.CORR. 0.4MM THK X12' 26.00 PCS 540.00 14,040.00
2.2 2X4X14' GOOD LUM. 10.00 PCS 440.00 4,400.00
2.3 2X2X12' GOOD LUM. 22.00 PCS 220.00 4,840.00
2.4 UMBRELLA NAIL 80.00 PCS 2.00 160.00
2.5 NAIL 4" 4.00 kilos 70.00 280.00
Total 23,720.00

Note: TOTAL MATERIAL COST 89,735.00


*Cage Grills/ others : Scrap Items LABOR COST 17,947.00
*Roofing sheets/others : Scrap TOTAL PROJECT COST 107,682.00
*

PREPARED BY:
Engr. Gaylord Frando

Date:
61.56
15.39

0.855

112 6
9.333333 45 48

22.5 281.25 1.265625 45.5625


7.59375

0.3 15

BLDG 2 4 COLS
1.2 7.2
septic tank
2 2.5 depth 2

11 22 275 chb
1.2375 0.0045 1.2375 cbm
44.55
7.425
7 bags

9
2.222222