You are on page 1of 1

STR MYANMAR CO.

, LTD MGS KITCHEN PROJECT 7/6/2020

Bill of Quantity
Sr.No
Particular Quantity Unit Rate Per Amount

Store Materials
1 Cement 293.84 Bags 3,450 Bags 1,013,762.58
2 20mm Ø MS Rod 0.73 Tons 1,200,000 Tons 875,520.00
16mm Ø MS Rod 0.36 Tons 1,200,000 Tons 435,814.94
12mm Ø MS Rod 0.21 Tons 1,200,000 Tons 254,007.00
3 10mm Ø MS Rod 2.03 Tons 1,260,000 Tons 2,559,371.85
5,138,476.37

Materials
1 Sand 11.02 Sud 10,000 Sud 110,193.89
2 Aggregate 9.09 Sud 26,462.25 Sud 240,667.54
3 Fuel 18.31 Gals 3,800 Gals 69,590.70
4 Hardcore 2.52 Sud 23,275 Sud 58,674.82
5 Binding Wire 16.53 Viss 2,000 Viss 33,058.48
6 J/Wood 2.57 Tons 570,000 Tons 1,462,118.40
7 5 ply wood 22.51 Shts 11,500 Shts 258,916.57
8 Nail 10.65 Viss 1,800 Viss 19,164.45
16 Brick 16305.00 Nos 100 Nos 1,630,500.00
28 Window (M+L) 203.88 Sft 4,500 Sft 917,437.50
31 Plastic Sheet 481.25 Sft 650 Sft 312,812.50
Total Cost 5,113,134.85

Labour
1 Surveyor 0.10 Nos 20,000 Nos 1,972.00
2 Manson 101.91 Nos 8,500 Nos 866,195.99
3 Steel Fixer 77.91 Nos 8,500 Nos 662,248.86
4 Carpenter 75.67 Nos 8,500 Nos 643,210.30
6 Worker 369.99 Nos 7,000 Nos 2,589,941.06
7 Machine Driver 4.58 Nos 8,500 Nos 38,915.85
Total Cost 4,802,484.06
Total 15,054,095.27
Say 15,100,000.00