Document Number
01 0 1 of 37
Document Title:
CONTROL OF NONCONFORMING
OUTPUTS PROCESS
Approval of
Department / ISO JOWELL P. MAX
Section / Process DEPARTMENT CABRERA FANKHANEL MILA D. PEREZ
Owner
Department Originator Reviewed Approved
IMPORTANT:
This cover sheet is part of the procedure and is not to be discarded unless superseded by a revised issue.
Unauthorized reproduction is strictly prohibited.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
01 0 2 of 37
REVISION HISTORY
Execution Revision Revision Description of Changes Page Originator Reviewed
Date Number Type Affected Date
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
01 0 3 of 37
CONTENTS
1. OBJECTIVE ……………………………………………………………………………………… 4
2. SCOPE ……………………………………………………………………………………………. 4
6. PROCEDURE ……………………………………………………………………………………. 6
8. FORMS ……………………………………………………………………………………………. 15
9. APPENDICES ……………………………………………………………………………………. 16
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 4 of 37
1.0 OBJECTIVE
The objective of this process is to establish and maintain a uniform and consistent
procedure of taking action for the prevention of unintended delivery and use of outputs
such as materials, equipment, products, structure and services that do not conform to
their specified requirements.
2.0 SCOPE
Nonconformity (NC) Any instance where practice or evidence does not fulfill the
requirements. This may be also a condition of “work in place" or
"work in progress" that lacks agreement or conformity, and which
cannot be corrected in the normal course of action.
Punchlists / Snags Workmanship deficiency that can be repaired in a manner that will
not require large amount of resources and time. Can be corrected
by “Making Good” repairs.
Corrective Action A report detailing the nonconformity identified to make an
Report (CAR) unambiguous, defensible, clear and concise definition of the
problem so that corrective action can and will be initiated. This
report also includes an analysis of the root cause of the
nonconformity, request for approval and execution of corrective
action/s, verification and review of the effectiveness of the
corrective action/s.
Issuing Entity (IE) Any Personnel, Department or Company who has the first-hand
knowledge of the nonconformity identified. The Personnel,
Department or Company who raise and issue the Corrective Action
Report (CAR).
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 5 of 37
Head of Issuing The Head of the QA/QC, OH&S, EMS, ISO or TQM who have
Entity (HIE) jurisdiction over level wherein the nonconformity was identified.
Responsible Entity Personnel, Department or Company who committed and
(RE) responsible for the nonconformity.
Head of Responsible The Project Manager, Department Head, SBU Head, Support BU
Entity (HRE) Head or General Manager of the Responsible Entity (RE) who
committed the nonconformity.
Correction/Immediate Short term actions that can be implemented to quickly address part
Action or full cause of the nonconformity.
Corrective Action Long term actions taken to eliminate the cause/s of an existing non-
conformity in order to prevent recurrence.
Concession Permission to use or release a product or service that does not
conform to specified requirements.
Correction Action to eliminate a detected nonconformity through repair or
replacement of defective part/s.
Segregation Process of setting apart the nonconforming materials or equipment
from the conforming ones to prevent unintended use.
Removal and The process of removing the identified nonconforming products
Replacement and services and changing to conforming ones.
Repair To make amends for bringing about the quality level for use of a
product, but not to the extent of altering its original intent.
Preventive Action Action to eliminate the cause of a potential nonconformity or other
potential undesirable situation
Standard Materials Commons materials or equipment not specified in the Inspection
and Test Plan to be check by Stock Clerk using the normal
Warehousing Process.
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 7 of 37
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 8 of 37
6.0 PROCEDURE
6.1.1 The Project QA/QC Staff with the supervision of the Project QA/QC Head
shall inspect incoming materials and equipment based on the approved
Inspection & Test Plan (ITP) and in accordance with the Quality
Assurance / Quality Control Process.
6.1.2 The Project Warehouse Stock Clerk shall inspect common “standard
materials” not covered by the approved Inspection and Test Plan in
accordance with Warehousing Process.
6.1.3 The Project QA/QC Staff shall accomplish the Delivery Inspection Report
after the inspection. The Project QA/QC Staff shall note the
observations prior to unloading. The Project QA/QC Staff shall
recommend actions to the Project QA/QC Head if the material or
equipment is to be:
6.1.4 The Project QA/QC Head shall review and approve the recommended
action of the Project QA/QC Staff if found to be valid. Likewise, the
Supplier shall concur with the findings/observations of the Project
QA/QC Staff if found to be valid.
6.1.5 The Project QA/QC Head together with Project Warehouse Stock Clerk
shall tag nonconforming materials and equipment using the Disposition
Tag to prevent the unintended use of materials/equipment. The Project
QA/QC Head shall determine the final disposition of nonconforming
materials and equipment.
6.1.6 The Project QA/QC Head and Project Warehouse Stock Clerk shall
inform the Procurement Department and provide a copy of the Delivery
Inspection Report.
6.1.7 The Procurement Department shall request action/s from the Supplier
to address the nonconformity identified. The Procurement Department
shall request the Supplier/Subcontractor to perform the necessary
action/s based on the final disposition agreed to bring the product to
level of conformance not limited to the following:
a) Replacement
b) Repair
c) Substitution
d) Concession
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 10 of 37
6.1.11 The Project QA/QC Head shall ensure that all nonconforming materials
and/or equipment shall not be incorporated in the work.
6.2.1 The Project QA/QC Head shall inspect the Final Structure or portion
thereof based on the approved Inspection & Test Plan (ITP) in
accordance with the Quality Assurance / Quality Control Process.
6.2.3 Punchlist or snags shall be closed and addressed in accordance with the
Turn Over Procedure and Quality Assurance and Quality Control
Process.
6.2.4 The Project QA/QC Head shall tag nonconforming structure/s using the
Disposition Tag to prevent its unintended use or the commencement of
succeeding work as necessary. Hold points described in the approved
Inspection and Test Plan (ITP) shall apply.
6.2.8 The Project QA/QC Head shall verify the effectiveness of the corrective
actions taken in accordance with the Corrective Action Process.
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 12 of 37
6.3.3 The Responsible Entity (RE) shall determine and propose the necessary
control to prevent nonconforming outputs to be incorporated in the
work or delivered to and used by the Customer.
6.3.4 The Head of Issuing Entity (HIE) shall ensure that the Corrective Action
Process is effectively implemented at any stage of the work.
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 13 of 37
6.4.2 After execution of the immediate control/s, and when imminent danger
or potential loss above stated is/are fundamentally controlled, the
responsible Department Head shall re-analyze the suitability of
immediate controls applied and shall make adjustments as necessary.
The normal procedure described in this process shall apply
subsequently.
6.5.2 In case of material and equipment supply, disputes shall be resolve and
decided by the Procurement Department.
6.6.1 The Project QA/QC Head/DMR shall update the Corrective Action Report
(CAR) control register to reflect the status of the corrections and
corrective actions taken.
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 14 of 37
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 15 of 37
8.0 FORMS
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 16 of 37
9.0 APPENDICES
Issuing Entity issue 1. Project QA/QC Head and Stock Clerk to Conforming Materials,
Corrective Action Report coordinate with Procurement Equipment, Structures and
(CAR) or Delivery Inspection Department. Services
Report 2. Project QA/QC Head and Stock Clerk tag
nonconforming materials and
equipment.
3. Project QA/QC Head to tag
nonconforming structures.
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 17 of 37
APPENDIX 2: FORMS
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.
Document Title
CONTROL OF NONCONFORMING OUTPUTS
PROCESS
Document Number
01 0 18 of 37
Printed versions are UNCONTROLLED except when stamped “CONTROLLED COPY” in red.