Professional Documents
Culture Documents
Abstract- This paper evaluates minimum and maximum ROK and DPRK until recently, there are many limitations to
exchange power considering economic and technical develop generating resources and expand network for
characteristics between Russia and ROK. First, we evaluate supplying the heavy load in the northern part near Seoul. In
minimum exchange power to assure economic feasibility by this situation, one of the best ways to overcome such
comparing with the total cost and benefit of interconnected line.
For evaluating maximum exchange power, two constraints are difficulties in supplying the power demand seems to be cross-
considered, which are composed of Interconnected line constraint border system interconnection. Especially, power system
and system constraint. Interconnected line constraint depends on interconnection in NEA(Near East Asia) region, so called
geographical situation of Russia and Korean peninsula. System NEAREST (Near East Asian Region Electrical System Tie), is
constraint is evaluated through PSS/E power system analysis. As taking much attention in recent [1-4]. Now, research project
a result of these evaluations, we propose the maximum exchange
on NEAREST has been carrying out in university and
power. As a conclusion, we suggest the reasonable range of
exchange power between ROK and Russia considering economic research institute in Korea. In this paper, interconnection
and technical constraints with the interconnection scenario that scenario between ROK and Russia is investigated in technical
power system interconnection between ROK and Russia will be and economic aspects for verifying the feasibility of
realized in the year of 2010. NEAREST project. For the realizing power system
interconnection, many economic and technical analyses
Index Terms-- Economic constraint, Exchange power, Power should be achieved in advance. Therefore, minimum
system interconnection, Technical constraint exchange power in economic aspect is evaluated by
comparing with life cycle cost and benefit of interconnected
I. INTRODUCTION
line. In addition, evaluation of maximum exchange power in
technical aspect is carried out.
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
2
disturbance. Therefore, this configuration can assuring of the economic feasibility. In this paper, we assume
increase the reliability of interconnected line. that initial annual decreasing rate of electricity tariff
Interconnection bus voltage is set to 1.0pu and difference is 10% and it will decrease annually to 2030, which
receives the reactive power from capacitor banks results in the annual decreasing rate of 2030 is 0%. Another
and converter itself. Each terminal has capacitor key factor is average utility factor of transmission line. The
banks for filtering the high frequency noise, which higher utility factor makes interconnection more beneficial.
is 10% of converter rating. The 60% of average utility factor is used to calculate the
The power exchange scenario is that ROK imports benefit. Table I shows input parameter for estimating life-
power from Russia. We assume Russia has infinite cycle cost and benefit of interconnected transmission line.
surplus power and Russia power system has no any
system constraint to supply power. TABLE I
INPUT PRAMETER
Items Data
Life-cycle span 30 years
Maintenance cost 4% of initial cost
C/S
Power Loss factor 0.7%
Maintenance cost 4% of initial cost
T/L
Power Loss factor 2.52%
Cost rate of ROW of DPRK 20% of tariff benefit
Electricity Russia $0.0259/kwh
tariff ROK $0.0642/kwh
Average utility factor of T/L 60%
Fig.1. Concept diagram of Russia-ROK power system interconnection
Table II shows total cost and benefit of interconnected
line. If 1GW of power is exchanged between ROK and
III. MINIMUM POSSBILE EXCHANGE POWER Russia, total cost is much more than benefit, which can’t
assure of economic advantage. However, more than 2GW of
A. Cost of interconnected line exchange power can guarantee interconnection project to be
in the black. Therefore, we propose that minimum exchange
Total cost of interconnected line, life cycle cost, consists of
power in economic aspect is 2GW.
initial and operating cost. Initial cost includes the construction
cost of transmission line (T/L) and converter station (C/S), TABLE II
operating cost means the maintenance cost and power losses TOTAL COST AND BENEFIT
of transmission line and converter station. In this paper, Exchange
Cost (billion $) Benefit (billion $)
annual maintenance cost can be calculated by multiply initial power
cost with annual maintenance rate of transmission line and 1GW 1.62 1.29
converter station. Cost from power losses is also evaluated by
using power loss factor [5-7]. As mentioned before, 2GW 2.51 2.58
interconnected line will go through the territory of DPRK,
which means Russia and ROK should pay some amounts of 3GW 3.31 3.88
money for using ROW (Right of way) of DPRK. The cost of 4GW 4.12 5.17
ROW is calculated by multiply cost rate of ROW with annual
electricity tariff benefit between Russia and ROK.
IV. MAXIMUM POSSIBLE EXCHANGE POWER
B. Benefit of interconnected line
Benefit of interconnection comes from the electricity tariff Maximum exchange power is evaluated by taking account
difference between ROK and Russia. The electricity tariff of following technical aspects:
difference in 2001 was $0.0383/kWh, but this difference has
been getting decreased because the annual increasing rate of System constraint
electricity tariff in Russia has been higher than that of ROK. Interconnection line constraint
Therefore, decreasing rate of electricity tariff difference
between ROK and Russia is one of the key factors for
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
3
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
4
flows out to bus 1910, 1300, 1301 and 1400. As inflow power transmission line and transformer should have loading of less
from Russia is getting increase, the power from bus 1200 than 120% of rating and bus voltage should keep the range
becomes decreasing gradually. In case that 4GW of power from 0.95pu to 1.05pu. Table VII shows the results of (N-1)
inflows from Russia, bus 1900 provides power to all of the contingency analysis. In Table VII, “number of violations”
connected neighboring buses. As a result of load flow means the number of contingency case that overload or
analysis, no transmission line and transformer violates voltage violation happens. No overload and bus voltage
overload criteria in steady state, which means that no violation occurs until 4GW. However, if inflow power from
transmission line and transformer loadings exceed the 100% Russia is more than 5GW, some violations show up.
of rating.
TABLE VI I
RESULTS OF (N-1) CONTINGENCY ANALYSIS
TABLE V
POWER FLOW (MW) Inflow power Number of violations
Bus Inflow power from Russia from Russia Overload Bus voltage
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
5
Fig. 3. Frequency variation under contingency Only one route can be built from Russia to the
Korean Peninsula because the border is too narrow
a) Methodology (18km) and the Russian side goes through an
We use the PSS/E dynamic simulation program and peak environmentally protected area as shown in Fig. 4.
load data of Korea Electric Power Company (KEPCO) in
2010. As an alternative, there is a way to pass through
The equivalent network model and generation reduction Chinese territory via West Sea or East Sea. Yet, it is
method are same with those of load flow analysis. As not advisable since it can cause conflicts among
mentioned before, we assume that two- bipole HVDC system related countries.
is built for interconnection between Russia and ROK. One-
bipole and two-bipole trip are considered with the case of Considering above situation, maximum two-bipole HVDC
having a range from 1GW to 4GW of inflow power. Operating system is possible for interconnection between Russia and
standard of power system frequency of KEPCO asks ROK.
frequency in steady state to keep the range of 59.8Hz to
60.2Hz and under peak should be over 59.6Hz in transient
state. So, we can find acceptable maximum exchange power
without severe violation of frequency operating standard
under interconnected line trip.
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
6
Chukar 1.602 0.0097 1543 line constraint. As results of these investigations, we propose
4GW as a maximum exchange power with Russia in the year
Thrasher 1.802 0.0075 1673 of 2010. In addition to maximum exchange power, we
Joree 1.880 0.00689 1751 evaluate minimum exchange power by comparing with total
cost and benefit of interconnected line. 2GW seems to be
minimum exchange power to assure economic feasibility.
In addition to conductor size, the number of conductor of
Finally, we can say that the range of 2GW to 4GW seems to
transmission line is also design factor to determine the
be reasonable power exchange level of ROK-Russia
capacity. If we use one Joree conductor per pole, the capacity
interconnected line in the year of 2010. This study is
is 875MW. In case of using two Joree conductors per pole,
performed under the hypothesis and based on research
the capacity can be increased up to 1.75GW. Therefore, the
concept. Therefore, more detailed engineering works from the
maximum capacity of transmission line can be varied
technical and economic viewpoints are required for the
according to transmission line configuration such as
realization of NEAREST.
conductor size and the number of conductor used. If we
design the transmission line of HVDC system with two Joree VI. REFERENCES
conductors per pole, 4GW power can flow through two-bipole
HVDC system. [1] KERI, KEPCO, “A preliminary study of the power system
interconnections in Northeast Asia countries”, Tech Rep. 2000
[2] L. Belyaev and S. Podkovalnikov, “An approach to and results of
C. level of maximum possible exchange power effectiveness assessment of inter-tie <<RFE – DPRK – ROK>>”, 2000
In previous analyses, level of maximum possible exchange [3] Asia Pacific Energy Research Institute, “Cross-border power”, 2002
[4] Belyaev L.S., Chudinova L.Yu.,·, Podkovalnikov S.V. “Studies of
power is proposed as follows: Interstate Electric Ties in Northeast Asia”, International Journal of Global
Energy Issues.- 2002.- Vol.17.- ¹ 2.- pp. 228-249.
Load flow analysis [5] CIGRE Working Group 14.20, "Economic Assessment of HVDC Links",
CIGRE Annual Report, 2000.
There is no violation of overload and voltage in steady [6] D. Wilhelm, "High-Voltage Direct Current Handbook", Electric Power
state up to 6GW of inflow power. In (N-1) contingency, Research Institute, TR-104166, 1994.
however, some violations occur as inflow power exceeds [7] Harold L. Hill, "Transmission Line Reference Book HVDC To ±600kV",
Electric Power Research Institute, RP-104.
4GW. Therefore, 4GW seems to be maximum exchange [8] KEPCO, “Statistics of Electric Power in Korea”, Vol. 72, 2003
power. [9] SURAL, “Product catalog of ACSR”, http://www.sural.com
Dynamic analysis
Power system frequency of ROK can keep the standard VII. BIOGRAPHIES
when losing 2GW of power. However, loss of more than
3GW of power makes frequency violate the standard. Jong–Yul Kim is with the Korea Electrotechnology
Research Institute (KERI) as a Research Engineer since
Considering one-bipole trip, 4GW is maximum exchange 2001. He received the B.S and M.S degrees in Electrical
power. Engineering from Pusan National University. His research
interests are power system Interconnection of Northeast
Asia, application of superconducting devices to power
Interconnection line constraint systems and AI applications to power systems.
Considering the geographical situation between Russia jykim@keri.re.kr
and Korean peninsula, two-bipole system having a
capacity of 4W can be built.
Jae-Young Yoon Yoon Jae-young is the head of the
Power System Research Group at the Korea
Finally, we can say that 4GW of power exchange is Electrotechnology Research Institute (KERI). He
maximum acceptable power between Russia and ROK in the received his BSc., MSc. and Ph.D degree in electrical
engineering from Busan National University. Currently,
year of 2010 taking account of technical aspect. he is managing a research project, application of HTS-
equipment such as cables, current limiting reactors and
V. CONCLUSION transformers and also playing a key role in the research
project related to the Northeast Asia Power System
Interconnection, including North Korea.
This paper evaluates minimum and maximum exchange
Kim, Ho-yong is with the Korea Electrotechnology
power between Russia and ROK in 2010 from the viewpoints
Research Institute(KERI) as a Principle Research
of economic and technical. Two technical constraints are Engineer since 1986. He is currently a Director
considered to determine maximum exchange power. Firstly, of Power System Research Lab. He received BS degree
system constraints such as overload of transmission line and from Seoul National University, Korea in 1979 and MS,
Ph.D. from University of Texas at Austin ,USA in 1982
transformer, voltage profile of bus and frequency variation and 1985 respectively. His main research areas are
caused by interconnection trip are investigated. Secondly, we distribution automation and AI applications to power
look at transmission line capacity limited by interconnected systems and Power System Interconnection.
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.
7
Authorized licensed use limited to: Universidad Nacional de Ingeniería. Downloaded on July 05,2023 at 23:29:00 UTC from IEEE Xplore. Restrictions apply.