BRIJ GOPAL CONSTRUCTION COMPANY PVT. LTD.

Project Name: Rehabilitation And Up-gradation of 4-Lane to 6-Lane of Bhadrak - Baleshwar Section of NH-5 (New NH-16) from Km. 136.500 to Km. 199.141) in the State of Odisha to be Executed
as Hybrid Annuity Mode Under NHDP Phase - V (Package - II)

MAJOR BRIDGE & MINOR BRIDGE STATUS/PROGRESS


NO OF PILE ABUTMENT&PIER PILE PSC/RCC GIRDER
TYPE OF ABUTMENT/PIER SHAFT ABUTMENT/PIER CAP
SL NO CHAINAGE TYPE (COMPLETED/IN CAP(COMPLETED/IN (COMPLETED/IN REMARKS
FDN (COMPLETED/IN SCOPE) (COMPLETED/IN SCOPE)
SCOPE) SCOPE) SCOPE)

1 149+685 MJB PILE FDN 36/36 4/4 4/4 0/4 12/12

2 150+285 MJB PILE FDN 48/48 0/6 0/6 0/6 12/12 2 SOLID SLABS

3 150+680 MNB OPEN FDN 0/0 0/6 0/6 0/6 N.A 5 SOLID SLABS

4 162+465 MNB PILE FDN 30/30 1/3 1/3 0/3 0/8

5 173+805 MNB OPEN FDN 0/0 3/3 3/3 0/3 N.A 2 SOLID SLABS

6 175+800 MNB OPEN FDN 0/0 2/2 2/2 0/2 N.A 1 SOLID SLAB

7 175+970 MNB OPEN FDN 0/0 0/4 0/4 0/4 N.A 3 SOLID SLABS

8 180+380 MNB OPEN FDN 0/0 0/3 0/3 0/3 N.A 2 SOLID SLABS

9 180+827 MNB OPEN FDN 0/0 0/2 0/2 0/2 N.A 1 SOLID SLAB

10 184+255 MNB OPEN FDN 0/0 0/4 0/4 0/4 N.A 3 SOLID SLABS

11 185+697 MNB OPEN FDN 0/0 0/3 0/3 0/3 N.A 2 SOLID SLABS

12 195+850 MJB PILE FDN 32/32 6/6 6/6 0/6 9/20

13 196+492 MNB PILE FDN 28/28 0/4 0/4 0/4 12/12

14 197+024 MJB PILE FDN 64/64 10/10 10/10 8/10 5/36

15 198+550 MJB PILE FDN 40/80 0/7 0/7 0/7 0/24