Professional Documents
Culture Documents
C. Ask the person for proof the payment is required A. -10% to +25%
D. A change control system D. Ask for information on risks that would cause your
estimate to be too low
Q4. A cost baseline is an output of which cost
management process? Q8. An estimate that is -25% /+75% percent of actual is
considered a:
A. Determine Budget
A. Definitive estimate
B. Estimate Activity Resources
B. Parametric estimate
C. Control Costs
C. Budget estimate
D. Estimate Costs
D. Rough order of magnitude estimate
Q5. The cost contingency reserve should be:
A. Lack of historical records from previous projects Q14. Company ABC is evaluating three consulting
companies to find a consultant to perform
B. Unavailability of desired resources professional services. They request information on how
the three consulting companies allocate fringe benefits
C. Lack of company processes to their clients. What type of cost is Company ABC
asking about?
D. Inadequate scope definition
A. Direct
Q10. You were appointed as project manager for a
contact center project. To ensure project’s success, you B. Indirect
decided to send your team abroad to study on new
technologies. Which type of cost is team training? C. Variable
A. Fixed D. Fixed
A. Have the construction company pays the fee Q17. Which of the following information about the
project would NEVER be available during project
B. Refuse to pay the fee planning?
Q13. A project has a team member assigned to the C. Benefit cost ratio
project full time. What is the MOST likely effect on the
project if that resource completes her activity sooner D. Internal rate of return
than planned?
A. Wasted cost
D. An understanding of the cost risk in the work that has C. Uses top-down estimating techniques
been estimated
D. Uses bottom-up estimating techniques
Q21. The approximate resource costs necessary for
completing project activities are compiled during Q26. Which of the following does NOT assess the value
which project management process? a project bring to an organization
Q22. A project manager wants to decrease costs on a Q27. The project manager is allocating overall cost
project which a consultant is completing for her estimates to individual activities to establish a baseline
company. What costs should the project manager for measuring project performance. That process is
consider to accomplish this? this?