Professional Documents
Culture Documents
ScienceDirect
Procedia Computer Science 00 (2017) 000–000
www.elsevier.com/locate/procedia
Available online at www.sciencedirect.com
Procedia Computer Science 00 (2017) 000–000
www.elsevier.com/locate/procedia
ScienceDirect
Procedia Computer Science 121 (2017) 732–739
b
Department of Civil and Environmental Engineering, Imperial College London,South Kensington, London SW7 2AZ, UK
a
Dyson School of Design Engineering, Imperial College London,South Kensington, London SW7 2AZ, UK
b
Department of Civil and Environmental Engineering, Imperial College London,South Kensington, London SW7 2AZ, UK
Abstract
In construction projects delays are not only disruptive but also expensive. Thus, the reasons for schedule deviation need to be
Abstract
identified. The delay factors determined in previous research were predominantly studied through surveys. In these studies, the
participants
In wereprojects
construction stakeholders
delaysinareconstruction projects, and
not only disruptive but the
alsoreasons for schedule
expensive. Thus, thedeviation
reasons were identified
for schedule through need
deviation their point
to be
of view. In The
identified. addition,
delaydelay factors
factors are typically
determined considered
in previous individually
research and are presented
were predominantly at the
studied samesurveys.
through level. In In
reality,
theseowing to the
studies,
complex structure
participants of construction
were stakeholders projects andprojects,
in construction long execution
and the time,
reasonsnon-conformance in schedules
for schedule deviation occurs bythrough
were identified a chain their
of events.
point
Theview.
of aim In
of addition,
this research is factors
delay to investigate the factors
are typically causingindividually
considered schedule deviation in construction
and are presented at the projects andInunderstand
same level. the cause-
reality, owing to the
effect relationships
complex structure ofbetween the events
construction leading
projects and to delays.
long Among
execution various
time, techniques developed
non-conformance to root
in schedules causebyproblems,
occurs a chain offault tree
events.
analysis
The aim (FTA)
of this is an established
research tool. FTA
is to investigate thelooks deeply
factors into schedule
causing the chaindeviation
of events in
leading to a problem
construction to identify
projects its primary
and understand cause.
the cause-
FTA was
effect applied tobetween
relationships a modular construction
the events leadingproject that Among
to delays. experienced significant
various techniquesdelays. The analysis
developed identified
to root cause multiple
problems, faultdelay
tree
factors, and
analysis (FTA)showed
is an how they aretool.
established linked
FTAfrom thedeeply
looks primary
intocauses to the
the chain of ultimate event. to
events leading The root of most
a problem delaysits
to identify was traced cause.
primary to the
inexperience
FTA of thetoproject
was applied stakeholders.
a modular construction project that experienced significant delays. The analysis identified multiple delay
factors, and showed how they are linked from the primary causes to the ultimate event. The root of most delays was traced to the
inexperience of the project stakeholders.
© 2017 The Authors. Published by Elsevier B.V.
© 2017 The Authors.
Peer-review Published by
under responsibility of Elsevier B.V. committee of the CENTERIS - International Conference on ENTERprise
the scientific
Peer-review
Information under responsibility of the scientific committee of the CENTERIS - International Conference on ENTERprise
© 2017 The Systems
Authors. /Published
ProjMANby - International
Elsevier B.V.Conference on Project MANagement / HCist - International Conference on
Information Systems / ProjMAN - International Conference on Project MANagement / HCist - International Conference on
Health
Health and
and Social
Peer-review underCare
Social Information
responsibility
Care Information Systems
of the and
scientific
Systems Technologies.
and committee of the CENTERIS - International Conference on ENTERprise
Technologies.
Information Systems / ProjMAN - International Conference on Project MANagement / HCist - International Conference on
Keywords:
Health andConstruction
Social Caredelay, Delay factor,
Information Productivity,
Systems Prefabrication, Root-cause analysis
and Technologies.
1. Introduction
A construction project is considered to be successful when it is completed on time, within budget and all the
stakeholders are satisfied with its quality (Gündüz et al. 2013). Completing projects within the contract time is often
regarded as an indicator of efficiency (Chan and Kumaraswamy 1997). However, unique features of construction
projects, such as long execution period, complicated processes, high sensitivity to environmental influences, the
diverse interests of the different stakeholders and the dynamic structure of project teams, often make the delivery of
projects on time very challenging (Zou et al. 2007). Indeed, the construction industry generally regards delays to be
inevitable (Aibinu and Odeyinka 2006).
In order to control or eliminate the obstacles to complete a project on time, the reasons for construction delays
have to be understood. Many studies have been carried out for this purpose, and the methods typically applied are
surveys conducted using interviews or questionnaires (e.g. Assaf et al. 1995; Gündüz et al. 2013), and reviews of
existing literature (e.g. Chan and Kumaraswamy 1997; Aibinu and Odeyinka 2006; Pethkar and Birajdar 2015). These
studies have generally regarded all the causes of non-conformance in construction schedules to be at the same level.
In other words, the cause-effect relationships between delay factors are missing. Furthermore, the importance of a
delay factor is generally assigned subjectively by the participants to a study based on personal experience. Thus, there
is no systematic and objective way of judging how significant a delay factor is.
In reality, lateness in construction schedules results from a chain or sequence of events. Any undesired delay
event must be triggered by intermediate events and these in turn are caused by primary events which should be
identified, understood and blamed for. Hence, all the delay factors in a construction project are connected not only
chronologically but also logically. This is because all the stakeholders in a construction project are interacting
dynamically with each other during the whole execution period. Thus, in order to effectively reveal the primary delay
causes, a new paradigm has to be implemented.
The aim of this research is to investigate the factors causing schedule deviation in construction projects and
understand the casual relationships between the events leading to delays. The research is based on the analysis of a
modular construction project. Fault Tree Analysis was used to identify the delay factors and reveal the cause-effect
relationships between them.
2. Background
3. Methodology
The following sections introduce the case study upon which the research is based, the data collected and the
modelling technique used to analyse delays.
Fig. 1. A comparison of the time lines of stick built and modular construction.
Fig. 2. The structure of a fault tree. The logical symbols are AND and OR-gates
The first step of the FTA is to define the undesired event for which causes are to be identified. In this study
the undesired event is “the construction project cannot be completed by the contract calendar date”. The boundary of
the FTA was defined by the stakeholders and places involved in the construction project under study. The second step
is to determine the immediate necessary and sufficient events that result in the top event and draw the logical symbols
which best describes the relationship between them. Once the undesired event is resolved into its immediate causes,
the next step is to treat each intermediate event as an intermediate level top event, and determine its immediate,
necessary and sufficient causes. This will be repeated until the primary causes are identified.
Fig. 3. Fault tree analysis for the delays in the construction of a public infrastructure. The primary delay factors are
circled by oval-shaped frames, and numbered.
For the two delay events presented in grey-shaded boxes in Figure 3, remedy measures were taken by the
construction company, which resulted in further delays. These are captured by two additional FTA branches presented
in Figure 4. The primary causes for the delays traced through the FTA are numbered in Figures 3 and 4 and listed in
Table 1.
As shown in the FTA, “Components were not delivered as expected” is the undesired event. The primary
causes of such event were found to be associated with lack of information and inexperience. This could be attributed
to the fact that many technologies and operations employed in modular construction are relatively new to the various
parties involved.
Lack of information and experience led, for example, to inaccurate scheduling of the module assembly
process, which then forced the assembly sequence to be changed twice (primary delay factor 1 and 2). Lack of
manufacturing experience and clear understanding of the client’s requirements by the designers resulted first in ill
design of the walkways and beams, and then in incorrect design of the moulds (primary delay factor 8 and 9). As a
result, the moulds had to be sent back to the manufacturer for revision. This seriously slowed down the production of
modular components. Furthermore, the design of the walkways and beams was not delivered on time, which further
delayed the mould design and the start of the components production, leaving insufficient time to make the amount of
components requested by the site.
Pei-Yuan Hsu et al. / Procedia Computer Science 121 (2017) 732–739 737
6 Pei-Yuan Hsu et al. / Procedia Computer Science 00 (2017) 000–000
Fig. 4. Fault tree analyses for the delays caused by the remedies to address the events presented in the grey-shaded
boxes in Figure 3. The primary delay factors identified are circled by oval-shaped frames, and numbered.
Table 1. The primary delay factors found in the case study
No. Primary Delay factors Responsible for
1 Lack of experience by schedule engineers A
2 Lack of information at scheduling time A
3 Inclement weather conditions Ex
4 Traffic congestion between factory and site Ex
5 No tag system built for identifying each component A
6 Lack of experience in making components in the factory by manuf. operators A
7 No effective quality check mechanism for finished components A
8 Requirements were not understood by designers B,C
9 Lack of experience in design for manufacturing by the designers B,C,D
10 Construction company changed the design A
11 Fluctuations in workers’ productivity A
12 Inadequate information exchanged between parties A,B,C,D,E
A: Company A ; B: Company B ; C: Company C ; D: Company D ; E: Company E ; Ex: External
In addition, the manufacturing operators lacked experience of making structural components in a factory
environment (primary delay factor 6). For instance, defects were found on the surfaces of many finished components,
reinforcements were not properly installed in some components, and other components were not produced in
accordance with the detail design drawings. When these faults were identified on the site, the non-compliant
components had to be sent back to recast. The inexperience of the manufacturing operators also led to fluctuations in
productivity (primary delay factor 11), resulting in production below the target quantity.
The delay was also caused by the lack of a systematic management plan. Without a strict quality check
mechanism for finished components, components with defects were sent to the site and got rejected, causing waste in
time and resources (primary delay factor 7). It is noteworthy that the defects identified were aesthetic rather than
structural and the rejection was unjustified. Furthermore, most structural components may look alike in appearance,
but they can actually have slight differences in size and shape. Without an effective tagging system for identifying
such differences wrong components were sent to the site on the wrong date (primary delay factor 5).
Other factors that contributed to the lateness of the project are strong winds which forced the crane to stop
operating (primary delay factor 3) and the traffic congestion between the factory and the site that made the delivery
on time rather challenging (primary delay factor 4).
Unfortunately, the attempts to correct the two delays (shown in the grey-shaded boxes in Figure 3) were
affected by the inexperience and insufficient communication between the parties. As shown in Figure 4, insufficient
738 Pei-Yuan Hsu et al. / Procedia Computer Science 121 (2017) 732–739
Pei-Yuan Hsu et al. / Procedia Computer Science 00 (2017) 000–000 7
information was given to the outsourcing company, and much time was needed to provide explanations, slowing down
the production of the modular components (delay factor 12, the left path in Figure 4). Similarly, not enough
information for producing the drawings of the moulds was provided to the outsourcing company, causing delay in
receiving the detail drawings (primary delay factor 12, the right path in Figure 4).
4.1 Recommendations to address the primary delay factors
The lack of experience by the schedule engineers and the insufficient information for establishing the
construction schedule could be improved by using a more sophisticated scheduling method. For instance, the program
evaluation review technique generally applied for construction scheduling could be integrated with a discrete event
simulation (DES). In this context, the output of the DES would provide the probability that a pre-determined schedule
is realised in the future.
The schedule deviations due to unfavourable weather, lateness in transportation and productivity fluctuation
can be minimised by employing a detailed supply chain configuration between the factory and the site. The supply
chain could be modelled by mathematical programming (e.g. linear programming or stochastic programming)
considering uncertainties in both manufacturing and assembly.
A quality system should be implemented to make sure that all the finished components comply with the
detailed design and there are no unacceptable defects. In addition, the site manager should be involved in the quality
checking process to assure that the components are ready for assembly. Moreover, to reduce wrong and missing
deliveries, radio frequency identification (RFID) tags could be applied to finished components to identify when and
where they are located.
Given that the project involved multiple companies, a digital platform could be established to support the
communication between the parties and supplement periodical face to face meetings. Furthermore, minutes meetings
should be captured and a record preserved to clarify the responsibility of each party.
5. Evaluation
According to the problem report produced by the construction company, the schedule delay was caused by:
1) the late release of the design of the structural components, which was subcontracted to the design and consultancy
company; and 2) a misunderstanding of the design by the company responsible of producing the detail design of the
structural components. Schedule deviations were chronologically logged by the large construction company as events
in a spreadsheet. Delay factors can be inferred from the events but the cause effect relationships between the factors
is not made explicit. Using FTA this research mapped multiple delay factors which were traced all the way to their
primary causes as shown in Figure 3 and 4. This approach to modelling shows that some delay factors possess greater
significance than others.
6. Discussion
Most of previous studies on delay factors in the construction industry have compiled lists and categorised the
factors identified. However, recognizing an important delay factor does not provide substantial help in problem
solving. This is because all the delay factors in a construction project are connected both chronologically and logically.
The problem can only be effectively resolved by tracing a delay factor to its primary causes and removing them. For
example, late delivery of building materials at sites has been listed as a leading delay factor in many literatures.
Nevertheless late delivery can be triggered by many causes, and all can be tracked back to their primary causes as
demonstrated by our FTA. This study demonstrates that FTA is a powerful tool for analysing a complex network of
delay events in a construction project, and identify the roots of the delays.
Modular construction has several unique features that distinguish it from conventional stick-built
construction. As a result it owns a different set of prevailing delay factors. Since the production of modular
components in a factory is carried out concurrently with the construction work on site, the design must be finished at
a much earlier stage than that required in stick-built projects, making accuracy and timeliness the two most critical
requirements in modular construction projects. Actually, this has become one of the major reasons to constrain many
projects from adopting the modular construction method (Blismas et al. 2005; Alazzaz, F. & Whyte 2015). In our case
study, a large part of the delay factors is design related. The ill design and late-submission of the design drawings
seriously slowed down the project and made the correction of the design errors very time consuming. By the same
reason, design changes by the construction company could be especially problematic in modular construction.
It is also worth noting that off-site modular construction has both the characteristic of manufacturing and
construction, so it possesses some delay factors which are absent in stick-built construction. Among these there are,
Pei-Yuan Hsu et al. / Procedia Computer Science 121 (2017) 732–739 739
8 Pei-Yuan Hsu et al. / Procedia Computer Science 00 (2017) 000–000
for instance, the lack of a holistic quality management system for finished products in the manufacturing factory, and
the lack of tagging and tracking techniques implanted on modular components to prevent mistakes in the shipping
process. In addition, a specialised manufacturing factory, which often is located far away from construction sites, and
unusually bulky cargos, which have to be transported using specialised vehicles via specific routes, all make
transportation especially uncertain in modular construction.
7. Conclusion
Fault tree analysis was applied to identify the primary delay factors in a modular construction project. It
revealed that some delay events are more important than others, and clearly showed the cause-effect relationships
among them. This study of delays in modular construction found that lack of experience in the technologies and
operations employed in this new construction method is an important factor. Moreover, there are other unique delay
factors to modular construction such as the lack of a holistic quality management system and tagging and tracking
systems for finished products. Changes in design and uncertainty in the transportation of modular components are
other examples of critical delay factors.
Acknowledgements
The authors acknowledge the support of the Taiwan Top University Strategic Alliance-Imperial PhD scholarship.
References
1. Abd El-Razek M E, Bassioni H A and Mobarak A M. Causes of delay in building construction projects in Egypt. “Journal of
Construction Engineering and Management”, 134(11), 831-841, 2008.
2. Aibinu A A and Odeyinka H A. Construction delays and their causative factors in Nigeria. “Journal of Construction Engineering and
Management”, 132(7), 667-677, 2006.
3. Alazzaz F and Whyte A. A review of current barriers (real and perceived) to off-site construction. “21st IIER International
Conference”, 11 April 2015, Australia, 27-31, 2015.
4. Andersen B and Fagerhaug T. Root cause analysis. In: Hytinen A and O’Mara P (eds.) “Root cause analysis: Simplified tools and
techniques”. 2ed. Milwaukee: ASQ Press, 2006.
5. Assaf S A, Al-Khalil M and Al-Hazmi M. Causes of delay in large building construction projects. “Journal of management in
engineering”, 11(2), 45-50, 1995.
6. Aurisicchio M, Bracewell R and Hooey BL. Rationale mapping and functional modelling enhanced root cause analysis. “Safety
science”, 85, 241-257,2016.
7. Battikha M G. Reasoning mechanism for construction non-conformance root-cause analysis. “Journal of Construction Engineering
and Management”, 134(4), 280-288, 2008.
8. Blismas N G, Pendlebury M, Gibb A and Pasquire C. Constraints to the use of off-site production on construction projects.
“Architectural engineering and design management”, 1(3), 153-162, 2005.
9. Chan D W and Kumaraswamy M M. A comparative study of causes of time overruns in Hong Kong construction projects.
“International Journal of project management”, 15(1), 55-63, 1997.
10. Doloi H, Sawhney A, Iyer K C and Rentala, S. Analysing factors affecting delays in Indian construction projects. “International
Journal of Project Management”, 30(4), 479-489, 2012.
11. El-Sayegh S M .Risk assessment and allocation in the UAE construction industry. “International Journal of Project Management”,
26(4), 431-438, 2008.
12. Gündüz M, Nielsen Y and Özdemir M. Quantification of delay factors using the relative importance index method for construction
projects in Turkey. “Journal of Management in Engineering”, 29(2), 133-139, 2013.
13. Lee W S, Grosh D L, Tillman F A and Lie C H. Fault Tree Analysis, Methods, and Applications A Review. “IEEE transactions on
reliability”, 34(3), 194-203, 1985.
14. Pethkar P M and Birajdar B V. Literature review on causes of delay in building construction projects.” Journal of Information,
Knowledge and Research in Civil Engineering”, 3(2), 217-220, 2015.
15. Rausand M and Hoyland A. Qualitative system analysis. In: David J (eds.) “System reliability theory: models, statistical methods,
and applications”. 2ed. Hoboken: John Wiley & Sons, Inc, 2004.
16. Rosenfeld, Y. Root-cause analysis of construction-cost overruns. Journal of Construction Engineering and Management, 140(1),
04013039-1-10, 2013.
17. Sambasivan M and Soon Y W. Causes and effects of delays in Malaysian construction industry. “International Journal of project
management”, 25(5), 517-526, 2007.
18. Sklet S. Comparison of some selected methods for accident investigation. “Journal of hazardous materials”, 111(1), 29-37, 2004.
19. Sweis G, Sweis R, Hammad A A and Shboul A. Delays in construction projects: The case of Jordan. “International Journal of Project
Management”, 26(6), 665-674, 2008.
20. Wilson P F, Dell L D and Anderson G F. Introduction. In: Lau, J L and Nilles B S (eds.) “Root cause analysis: A tool for total quality
management”. Milwaukee: ASQ Press, 1993.
21. Zou P X, Zhang G and Wang, J. Understanding the key risks in construction projects in China. “International Journal of Project
Management”, 25(6), 601-614, 2007.