You are on page 1of 6

‫ﻓﻰ ﺑﺪﺍﻳﺔ ﺍﻟﻤﺸﺮﻭﻉ ﺣﻀﺮﺗﻚ ﻻﺯﻡ ﺗﻌﺘﻤﺪ ﻣﻦ ﺍﻹﺳﺘﺸﺎﺭﻯ ﺍﻟﻨﺴﺐ ﺍﻟﻠﻰ ﻫﺘﻨﺰﻟﻚ ﻓﻰ ﺍﻟﻤﺴﺘﺨﻠﺺ ﻧﻈﻴﺮ ﻛﻞ ﻣﺮﺣﻠﺔ ﻣﻦ ﻣﺮﺍﺣﻞ ﺗﻨﻔﻴﺬ

ﺃﻯ ﺑﻨﺪ ﻣﻦ‬

‫‪ :‬ﺑﻨﻮﺩ ﺍﻟﻤﻘﺎﻳﺴﺔ ﻓﻠﻮ ﻣﺜﻼ ﻋﻨﺪﻙ ﺑﻨﺪ ﺗﻮﺭﻳﺪ ﻭﺗﺮﻛﻴﺐ ﻣﻮﻟﺪ ﺇﺣﺘﻴﺎﻃﻰ ﻓﺤﻀﺮﺗﻚ ﻣﺜﻼ ﺑﺘﻘﺴﻢ ﺍﻟﻨﺴﺐ ﻛﺎﻟﺘﺎﻟﻰ‬

‫ﻧﻈﻴﺮ ﺍﻟﺘﻮﺭﻳﺪ ﻟﻠﻤﻮﻗﻊ ﻭﺗﺴﻠﻴﻢ ﺷﻬﺎﺩﺓ ﺍﻹﺧﺘﺒﺎﺭ ﻓﻰ ﺍﻟﻤﺼﻨﻊ ‪* 70%‬‬

‫ﻣﻊ ﺗﺴﻠﻴﻢ ﺗﺮﻛﻴﺐ ﺍﻟﻤﻮﻟﺪ ﻟﻺﺳﺘﺸﺎﺭﻯ ‪* 20%‬‬

‫‪ switching on‬ﻋﻨﺪ ﻋﻤﻞ ‪* 5%‬‬

‫‪ testing and commissioning‬ﺑﻌﺪ ﻋﻤﻞ ‪* 5%‬‬

‫ﻓﺒﺘﻔﺎﻭﺽ ﺍﻹﺳﺘﺸﺎﺭﻯ ﻭﺑﺘﻘﺪﻡ ﺷﻴﺖ ﺯﻯ ﺍﻟﻤﺮﻓﻖ ﺩﻩ ‪ switching on‬ﻓﺄﻧﺖ ﻟﻮ ﻣﻘﺎﻭﻝ ﻣﻤﻜﻦ ﻣﻴﻌﺠﺒﻜﺶ ﺍﺧﺮ ‪ % 5‬ﺩﻯ ﻭﻋﺎﻭﺯﻫﺎ ﻣﻊ ﺍﻝ‬

‫‪.‬ﻟﻺﻋﺘﻤﺎﺩ ﻗﺒﻞ ﺗﻘﺪﻳﻢ ﺃﻭﻝ ﻣﺴﺘﺨﻠﺺ ﻭﺍﻹﺳﺘﺸﺎﺭﻯ ﺑﻴﻌﺪﻝ ﺣﺴﺐ ﻣﺎﻫﻮ ﺷﺎﻳﻒ ﻣﺎﻟﻢ ﻳﺬﻛﺮ ﺧﻼﻑ ﺫﻟﻚ ﻓﻰ ﺍﻟﻌﻘﺪ ﺑﻴﻨﻚ ﻭﺑﻴﻦ ﺍﻟﻤﺎﻟﻚ‬

‫ﻣﺮﻓﻖ ﻣﻘﺎﻳﺴﺔ ﻣﺸﺮﻭﻉ ﻛﺎﻣﻞ ﻣﺘﻮﺿﺢ ﻓﻴﻪ ﻧﺴﺐ ﺍﻟﻤﺴﺘﺨﻠﺺ ﻣﻘﺎﺑﻞ ﺗﻨﻔﻴﺬ ﻛﻞ ﻣﺮﺣﻠﺔ ﻣﻦ ﻣﺮﺍﺣﻞ ﺗﻨﻔﻴﺬ ﻛﻞ ﺑﻨﺪ ﻣﻦ ﺑﻨﻮﺩ ﺍﻟﻤﻘﺎﻳﺴﺔ‬
APPROVED ELECTRICAL WEIGHTS

B.O.Q Add
DESCRIPTION NO. Weight Percentage
NO. percentage

Work notification of RMU factory testing ( Certificate must be


1 0% 0%
RING MAIN UNIT (RMU) accepted and stamped from electric authority )
2 Material inspection on site + Test certificate . 70% 70%
Supply, install and commission RMU 22 KV-500 MVA insulated
type Comprising Ring Main Switches 630 A and outgoing circuit 3 start Activity of RMU installation . 0% 70%
1 1.1 breaker SF6 630 A with Interlocked earth switch, voltage indicator, 4 RMU installation inspection . 20% 90%
work including earth leakage indicator, termination of outgoing and
incoming cables , fixing and supporting structures and all 5 cable tray inspection with cable termination . 0% 90%
accessories required to complete the installation in accordance with
electrical authority requirement . 6 Switch - on RMU inspection . 5% 95%

7 testing and commissioning RMU inspection . 5% 100%


Work notification of Transformars factory testing ( Certificate must be
1 0% 0%
accepted and stamped from electric authority )
POWER TRANSFORMER
2 Material inspection on site + Test certificate . 70% 70%
Supply, install and commission dry type power transformer 22 KV ±
3 Activiy to start Transformer installation . 0% 70%
2x2.5%, / 0.4 Kv 50 Hz, three phase , Dyn 1 1 , (AF) air forced cooling,
1.2 ventilation with required fans, tap changer, IP31, blug in connection 4 Transformer installation inspection . 20% 90%
Connection incoming and outgoing cables, fixing , and supports required
to complete the installation 5 cable tray inspection . 0% 90%

Dry type Transformer 1250 KVA, 22/0.4 KV/50Hz 6 Switch - on Transformer inspection . 5% 95%

7 testing and commissioning Transformer inspection . 5% 100%

1 shop drawing . 0% 0%
HIGH & MEDIUM POWER DISTRIBUTION BUSBAR Material inspection on site including factory testing certificate
2 70% 70%
+supplier + origin certificate .
Supply , install and commission live copper conductors (3 PH . 3 Activity to start for BUSBAR installation . 0% 70%
1.3 +N+E),busbar trunking system for fixed and removable circuit breakers ,
(IP-54 ) according to standard, including tap - off , transformer plug unit 4 BUSBAR installation inspection . 20% 90%
fixation and supporting and all accessories reauired to complete the
installation and as indicated on the drawings 5 Switch on BUSBAR inspection . 5% 95%

6 Testing and commissioning BUSBAR inspection . 5% 100%

1 Cables material inspection on site + Factory testing certificate. 30% 30%

2 Start of activity for Cable Tray/ ladder installation. 0% 30%


MEDIUM VOLTAGE CABLE 3 Cable Tray installation inspection. 20% 50%
upply, install and commission multi core aluminum conductors, XLPE
insulated, steel tap armured , PVC sheathed 18/30 KV installed between 4 Start of activity for cable installation. 0% 50%
1.4
main source and R.M.U and power transformers include Cable Clamps, 5 Cable installation inspection. 35% 85%
Cable ladder, Cable Joints and all Accessories Required to Complete The
Installation. 6 Cables termination inspection. 5% 90%

7 Switch on inspection. 5% 95%

8 Testing and Commissioning inspection. 5% 100%


Work Notification of Generator factory testing certificate in addition to show
1 0% 0%
DIESEL GENERATOR SET room testing certificate + Origin certificate.
Supply and Install 1500 R.P.M, 415/240 Volt, 50 HZ, 4 Wire, with 2 Material inspection on site. 70% 70%
insulated solidly earthen neutral, automatic starting including supply
& install, of forced air cooling system, batteries, exhaust system, 3 Activity to start for generator installation 0% 70%
2 piping, control panel, completely installed under ground bulk fuel 4 GENERATOR installation inspection. 20% 90%
tank, day tank & supporting structures, piping, canvas, fuel transfer
pumps & all related access. 5 cable termination. - -
6 Switch-on GENERATOR inspection. 5% 95%
Gen ( 400 KVA )
7 Testing and Commissioning GENERATOR inspection. 5% 100%

3 EARTHING SYSTEM 1 Material Inspection on site. 70% 70%


Low voltage network - earthing system 2 activity to start for EARTHING installation . 0% 70%
Supply, install and commission type TN-S earthing system, including 3 EARTHING installation inspection 25% 95%
3.1 earthing cables, test link, earth pits, handholes, earthing conductor and
all accessories required to complete the Installation as shown on the 4 EARTHING testing and commissionning 2.5% #NAME?
drawings
Low current - earthing system 1 activity to start for EARTHING installation .

Ditto as above but the resistance shall not exceed (1 ) one ohm.
3.2 2 EARTHING installation inspection

3 EARTHING testing and commissionning

4 LOW VOLTAGE NETWORK 1 Work Notification of factory test ( at least 24 hour notification in advance). 0% 0%

2 Material inspection + Factory test certificate. 70% 70%

3 Activity to start for panel board installation. 0% 70%

MAIN DISTRIBUTION BOARDS : 4 Panel installation inspection. 10% 80%


Supply, install and Commission Floor Standing L.V.Mdb Indoor Type
4.1 (IP43) Including Measuring Instruments, Protection Devices, Fixation, 5 Cable tray inspection. 0% 80%
Termination of Incoming and Outgoing Cables, Cable Glands , Fixing
6 Panel termination inspection. 10% 90%
and Supporting Structures and all Accessories Required To Complete The
Installation, and as Shown in Drawings & Schedules . 7 Switch-on inspection. 5% 95%

8 Testing and Commissioning Panel inspection. 5% 100%


B.O.Q Add
DESCRIPTION NO. Weight Percentage
NO. percentage

1 Work Notification of factory test ( at least 24 hour notification in advance). 0% 0%

2 Material inspection + Factory test certificate. 70% 70%

SUB MAIN DISTRIBUTION BOARDS: 3 Activity to start for panel board installation. 0% 70%
Supply, install and Commission Floor Standing L.V.Mdb Indoor Type
(IP42) Including Measuring Instruments, Protection Devices, Fixation, 4 Panel installation inspection. 10% 80%
4.2
Termination of Incoming and Outgoing Cables, Cable Glands, Fixing and
5 Cable tray inspection. 0% 80%
Supporting Structures and all Accessories Required To Complete The
Installation, and as Shown in Drawings & Schedules . 6 Panel termination inspection. 10% 90%

7 Switch-on Panel inspection. 5% 95%

8 Testing and Commissioning Panel inspection. 5% 100%

1 Material Inspection on site. 30% 30%

2 Start of activity for Cable Tray installation. 0% 30%

3 Cable Tray installation inspection. 20% 50%

LOW VOLTAGE CABLES AND RELATED ACCESSORIES 4 Start of activity for cable installation. 0% 50%
Supply, Install And Commission Multi- Core Copper Cables PVC
5 5 Cable installation inspection. 30% 80%
Insulated 0.6/1.0 KV including , cable trayes, Conduits, Conduit Fittings
and All Accessories Required To Complete Installation . 6 Cable Meggar test inspection. 5% 85%

7 Cables termination inspection. 5% 90%

8 Switch on inspection. 5% 95%

9 Testing and commissioning inspection. 5% 100%

6 WIRING DEVICES 1 Material inspection on site. 30% 30%

2 Start of activity of Lighting switch installation. 0% 30%


LIGHTING SWITCHES
Supplying, Installing Connecting & testing Lighting Switches including 3 Lighting switch installation inspection. 60% 90%
6.1
All necessary Accessories and materials required for complete installation
as specified and as indicated on the drawings.
4 Switch on & Testing and commissioning inspection. 10% 100%

1 Material inspection on site. 30% 30%


SOCKETS
Supplying, Installing, Connecting & Testing Sockets Including All 2 Start of activity of Socket installation. 0% 30%
6.2
Necessary Accessories And Materials Required For Complete Installation
3 Socket installation inspection. 60% 90%
As Specified And As Indicated On The Drawings.
4 Switch on & Testing and commissioning inspection. 10% 100%

1 Material inspection on site. 30% 30%

DISCONNECT SWITCHES 2 Start of activity of Disconnect Switch installation. 0% 30%


Supplying, installing, connecting & testing disconnect switches including
6.3 3 Disconnect Switch installation inspection. 60% 90%
all necessary accessories and materials required for complete installation
as specified and as indicated on the drawings. 4 Disconnect switch termination - -

5 Switch on & Testing and commissioning inspection. 10% 100%

7 ELECTRICAL OUTLETS 1 Material inspection on site. 0% 0%

LIGHTING OUTLETS 2 Start of activity of conduit installation. 0% 0%


Supply, install and commission lighting outlets including conduits, cond.
7.1 3 Conduit installation inspection. 40% 40%
Fittings, boxes, wiring, termination, all necessary accessories for
complete installation back to panel boards as specified and as indicated. 4 Start of activity of wires installation. 0% 40%

5 Wire installing inspection . 50% 90%

6 wire test - -
a Lighting Outlets with wire size(3 x 3)mm2
7 Wire termination inspection 5% 95%

8 Switch on 5% 100%

1 Material inspection on site. 0% 0%


2 Start of activity of conduit installation. 0% 0%
SOCKET OUTLETS 3 Conduit installation inspection. 40% 40%
Supply, install and commission Socket outletsincluding conduits, cond.
Fittings, boxes, wiring, termination, all necessary accessories for 4 Start of activity of wires installation. 0% 40%
7.2
complete installation back to panel boards as specified and as indicated. 5 Wire installing inspection 45% 85%
a- Socket outlets with wiring size (3 x 3) mm2
b- Ditto but with wiring size (3x4) mm2 6 wire test 5% 90%
7 Wire termination inspection 5% 95%
8 switch on 5% 100%
1 Material inspection on site. 0% 0%
2 Start of activity of conduit installation. 0% 0%
3 Conduit installation inspection. 40% 40%
DISCONNECT SWITCH OUTLETS
Supply, install and commission disconnect outlets including conduits, 4 Start of activity of wires installation. 0% 40%
7.3
cond. Fittings, boxes, wiring, termination, all necessary accessories for 5 Wire installing inspection 30% 70%
complete installation back to panel boards as specified and as indicated.
6 wire test 20% 90%
7 Wire termination inspection 5% 95%
8 switch on 5% 100%
B.O.Q Add
DESCRIPTION NO. Weight Percentage
NO. percentage

A LIGHT CURRENT SYSTEMS 1 Material inspection on site. 70% 70%


2 Start of activity for low current system equipment. 0% 70%
FIRE ALARM SYSTEM 3 Rack Cable Tray installing inspection. 10% 80%
Supply, Install And Commission Main Fire Alarm Control Panel
A.1 4 cable terminaton. - -
(MFACP) 10 loops Intelligent Addressable Type, Voice Alarm And
Amplifiers Includes But Not Limited To , 5 Switch-on inspection. 15% 95%
6 Testing and Commissioning. 5% 100%

1 Material inspection on site(Devices only). 25% 25%

2 Start of activity for low current system (Raceway). 0% 25%

3 Raceway installing inspection. 15% 40%

4 Start of activity for low current cable. 0% 40%


FIRE ALARM DEVISES AND OUTLETS
Supply, Install And Commission the below listed devices including 5 Cable installing inspection. 15% 55%
A.2
outlets, 2 x 1 .5 mm2 fire alarm wires, EMT conduits, back boces, devices
6 Cable termination inspection. 10% 65%
and all required accessories needed for complete installation
7 Cable Test . 10% 75%

8 Device installing inspection and termination. 10% 85%

9 Switch-on FIRE ALARM DEVISES AND OUTLETS Inspection 10% 95%


Test and Commissioning FIRE ALARM DEVISES AND OUTLETS
10 5% 100%
inspection.
B CLOSED CIRCUIT TELEVISION ( CCTV) SYSTEM 1 Material inspection on site. 70% 70%

2 Start of activity for low current system equipment. 0% 70%

3 Cable Tray installing inspection. 0% 70%


Supply , install, connecting and testing CCTV system enough storage
capacity for 1 month, alarm interface unit, control console , 8 No. color 4 Closed circuit television Rack installing inspection. 10% 80%
B.1 monitor LCD ( 32 Inch ), control keypad, cabling and all necessary
accessories required for complete installation as specification and as 5 System termination 10% 90%
on the drawing.
6 Switch-on Closed circuit television inspection. 5% 95%

7 Testing and Commissioning Closed circuit television. 5% 100%


Supply .install , connecting and testing the below listed CCTV- IP 1 Material inspection on site(Cameras only). 30% 30%
cameras ( day / night ) included domes, brackets, lenses, pan/ tilt unit
cabling, conduits, fittings back to main console and all necessary
accessories for complete installation as specification and as the drawings. 2 Start of activity for low current system (Raceway). 0% 30%

Indoor type fixed color dome camera 3 Raceway installing inspection. 10% 40%
color camera outdoor type complete with outdoor enclosure 4 Start of activity for low current cable. 0% 40%
B.2 5 Cable Installing inspection. 15% 55%
Indoor type fixed color camera 6 Cable termination inspection. 10% 65%

7 Cable Test . 10% 75%

8 Device installing inspection and termination. 15% 90%

9 Switch-on Inspection 5% 95%

10 Test and Commissioning inspection. 5% 100%

C DATA NETWORK 1 Material inspection on site. 0% 0%

2 Start of activity for low current system (Raceway). 0% 0%

3 Raceway installing inspection. 30% 30%

4 Start of activity for low current cable. 0% 30%


Data outlets
Supply, Install And Commission data outlets for data and CCTV systems 5 Cable installing inspection 40% 70%
C.1 including DTP cat.6 wires conduits , sockets and all required accessories
from outlet to related data rack , cable termination and testing from patch 6 Cable Test . 10% 80%
panel to outlet .
7 Cable termination inspection. 10% 90%

8 Switch-on data outlets Inspection 5% 95%

9 Test and Commissioning data outlets inspection. 5% 100%


1 Material inspection on site. 70% 70%
Data Racks 2 Start of activity for low current system equipment. 0% 70%
Supply, Install And Commission the below listed data racks including 3 Cable Tray installing inspection. 0% 70%
C.2 power outlets , ventillation fans , channels , fiber patch panels , DTP cat. 4 Data racks installing inspection. 15% 85%
6 patch panels and all required accessories nedded to complete 5 cables termination 5% 90%
installation ( data rack size shall be according to outlets no.)
6 Switch-on inspection. 5% 95%
7 Testing and Commissioning Data racks. 5% 100%
B.O.Q Add
DESCRIPTION NO. Weight Percentage
NO. percentage

1 Material inspection on site. 30% 30%

2 Start of activity for low current system (Raceway). 0% 30%

Fiber Optic Cables 3 Raceway installing inspection. 20% 50%


Supply, install , test and commission the below listed fiber optic cables
4 Start of activity for low current cable. 0% 50%
including EMT conduits , cables , connectors , terminations and all
C.3 required accessories needed to complete installation 5 Cable installing inspection . 20% 70%

6 Cable Test . 15% 85%


Fiber optic cable 8 core multi mode 50/125 anti rodent type 7 Cable termination inspection. 5% 90%

8 Switch-on fiber optic cables Inspection 5% 95%

9 Test and Commissioning fiber optic cables inspection. 5% 100%

D TELEPHONE NETWORK 1 Material inspection on site. 70% 70%

2 Start of activity for low current system equipment. 0% 70%

3 Cable Tray installing inspection. 0% 70%

4 Main telephone frame installing inspection. 10% 80%


MAIN Telephone Frame
D.1 Supply, install , test and commission MDF 1000 Pair including all 5 Cable Test . - -
required accessories nedded for complete installation
6 cable termination 10% 90%

7 Switch-on inspection. 5% 95%

8 Testing and Commissioning Main telephone frame. 5% 100%

1 Material inspection on site. 70% 70%

2 Start of activity for low current system equipment. 0% 70%


SHOPS TEL. FRAMES
Supply , install and commission telephone frames in shops complete with 3 Cable Tray installing inspection. 0% 70%
all required accessories needed for installation
D.2 5 pair tel. frame 4 shops tel. frames installing inspection. 10% 80%
10 pair tel. frame
20 pair tel. frame 5 cable termination 10% 90%
50 pair tel. frame
6 Switch-on inspection. 5% 95%

7 Testing and Commissioning shops tel. frames. 5% 100%

FLOORS TEL. FRAMES 1 Material inspection on site. 70% 70%


Supply , install and commission telephone frames in shops complete with
all required accessories needed for installation 2 Start of activity for low current system equipment. 0% 70%
TTC/S1 (100 PAIR)
TTC/S2 (100 PAIR) 3 Cable Tray installing inspection. 0% 70%
TTC/F1 (150 PAIR)
D.3 TTC/F2( 150 PAIR) 4 Floor Tel. frames installing inspection. 10% 80%
TTC/G1 (150 PAIR)
TTC/G2( 150 PAIR) 5 cable termination 10% 90%
TTC/B11 (100 PAIR)
TTC/B12(200PAIR) 6 Switch-on inspection. 5% 95%
TTC/B21 (20 PAIR)
TTC/B22 (20 PAIR) 7 Testing and Commissioning floors Tel. frames. 5% 100%
MULTI PAIR TEL. CABLES 1 Material inspection on site. 0% 0%
Supply , install test and commission multi pair tel cables including
2 Start of activity for low current system (Raceway). 0% 0%
covered cable tray , wires , conduits and all required accessories needed
for complete installation 3 Raceway installing inspection. 30% 30%
5 pair tel. frame 4 Start of activity for low current cable. 0% 30%
10 pair tel. frame
D.4 5 Cable installing inspection 50% 80%
20 pair tel. frame
50 pair tel. frame 6 Cable test . 5% 85%
100 pair tel. frame 7 Cable termination inspection. 5% 90%
150 pair tel. frame
8 Switch-on Multi pair Tel. cables Inspection 5% 95%
200 pair tel. frame
9 Test and Commissioning MULTI PAIR TEL. CABLES inspection. 5% 100%

1 Material inspection on site. 0% 0%

2 Start of activity for low current system (Raceway). 0% 0%

3 Raceway installing inspection. 30% 30%

TEL. OUTLETS 4 Start of activity for low current cable. 0% 30%


Supply , install test and commission tel. outlet with 2 pair wires 0.6 mm
D.5 from socket outlet to related tel. frame complete with conduits , sockets , 5 Cable installing inspection 50% 80%
wires , face plates and all required accessories needed for complete
installation 6 Cable test . 5% 85%

7 Cable termination inspection. 5% 90%

8 Switch-on TEL. OUTLETS Inspection 5% 95%

9 Test and Commissioning TEL. OUTLETS inspection. 5% 100%

E TV SYSTEM 1 Material inspection on site. 0% 0%

2 Start of activity for low current system (Raceway). 0% 0%

3 Raceway installing inspection. 30% 30%

4 Start of activity for low current cable. 0% 30%

Supply , install and commission tv outlets including coaxial 5 Cable installing inspection 50% 80%
E-1 cables rg-6 , sockets .conduit , fittings and all required accessories needed
to complete installation from outlet to related TV switch 6 Cable Test . 5% 85%

7 Cable termination inspection 5% 90%

8 Switch-on TV SYSTEM Inspection 5% 95%

9 Test and Commissioning TV SYSTEM inspection. 5% 100%


B.O.Q Add
DESCRIPTION NO. Weight Percentage
NO. percentage

1 Material inspection on site. 70% 70%

2 Start of activity for low current system equipment. 0% 70%

3 Cable Tray installing inspection. 0% 70%


E-2 Supply , install test and commission TV switch 8 port
4 TV switch installing inspection. 15% 85%

5 Switch-on inspection. 10% 95%

6 Testing and Commissioning TV switch . 5% 100%

1 Material inspection on site. 0% 0%


2 Start of activity for low current system (Raceway). 0% 0%
3 Raceway installing inspection. 30% 30%

Supply , install and comission tv coaxial cables RG 11 from roof to each 4 Start of activity for low current cable. 0% 30%
E-3 TV switch including covered cable tray and all accessories needed for 5 Cable installing inspection 50% 80%
complete installation
6 Cable Test . 5% 85%
7 Cable termination inspection. 5% 90%
8 Switch-on tv coaxial cables Inspection 5% 95%
9 Test and Commissioning inspection. 5% 100%

1 Material inspection on site. 70% 70%

2 TV dism 2.7 M diameter , Inb , multiplexer installing inspection. 15% 85%


Supply , install , test and commission TV dism 2.7 M diameter , Inb ,
E-4 multiplexer , connectins to each floor with RG-1 1 cables including all 3 cable termination - -
required accessories needed to complete installation
4 Switch-on TV dism 2.7 M diameter , Inb , multiplexer inspection. 10% 95%

5 Testing and Commissioning TV dism 2.7 M diameter , Inb , multiplexer . 5% 100%

1 Material inspection on site. 70% 70%

PUBLC ADDRESS SYSTEM


Supply, install and commission public address system complete with all 2 Start of activity for low current system equipment. 0% 70%
accessories to complete the work as detailed in specification and drawings
MAIN RACK 3 Cable Tray installing inspection. 0% 70%
Metal rack 19" with glass door and fan
Mixer preamplifiers
Power amplifiers 4 MAIN RACK installing inspection. 15% 85%
F CD - player 5 disc
AM/FM tuner with antenna 5 Cable Test . - -
Graphic equalizer -dual channel
Monitor panel JMU
Pre recorded message 6 Cable termination inspection. 5% 90%
2 Paging zones desk type
Power switching unit & Zone selector switch 7 Switch-on inspection. 5% 95%

8 Testing and Commissioning of MAIN RACK. 5% 100%

1 Material inspection on site.(speakers) 25% 25%


2 Start of activity for low current system (Raceway). 0% 25%
3 Raceway installing inspection. 15% 40%

Ceiling mounted speakers 4 Start of activity for low current cable. 0% 40%
Supply , install , test and commission ceiling mounted speakers , indoor 5 Cable installing inspection . 20% 60%
F-2 type , 3 watt complete with outlet , wires , conduits , back box and all
required accessories needed to complete installation from ceiling outlet to 6 Cable Test . 10% 70%
main sound system rack 7 Cable termination inspection. 10% 80%
8 Device installing inspection and termination. 10% 90%
9 Switch-on Ceiling mounted speakers Inspection 5% 95%
10 Test and Commissioning Ceiling mounted speakers inspection. 5% 100%
1 Material inspection on site. 25% 25%
2 Start of activity for low current system (Raceway). 0% 25%
3 Raceway installing inspection. 15% 40%

Wall mounted speakers 4 Start of activity for low current cable. 0% 40%
Supply , install , test and commission ceiling mounted speakers , indoor 5 Cable installing inspection . 20% 60%
F-3 type , 6 watt complete with outlet , wires , conduits , back box and all
required accessories needed to complete installation from ceiling outlet to 6 Cable Test . 10% 70%
main sound system rack 7 Cable termination inspection. 10% 80%
8 Device installing inspection and termination. 10% 90%
9 Switch-on Wall mounted speakers Inspection 5% 95%
10 Test and Commissioning Wall mounted speakers inspection. 5% 100%