Pinamalayan aims for a sustainable growth by means of controlled land use and ensuring
environmental integrity through protection, conservation, and ecotourism. Built-up areas such as
settlements and high-rise buildings on both sides of the landmark denote rapid urbanization
as a result of the influx of people and businesses through time. The rice fields denote the
greatest land utilization and source of livelihood. This also indicates that despite the
urbanization, conserving and prioritizing prime agricultural lands and improving production is of
priority concern.
The people and dove that are both enclosed by a caring hand represent a people-centered
development, peaceful environment, and empowered individuals and communities that have
access to various facilities and services despite the projected population growth.
The sunrise provides a background of prosperity for Pinamalayan and its inhabitants, having
reaped the benefits of cityhood and achieved sustainable development.
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
TABLE OF CONTENTS
i|Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-02-003-2* Barangay Livelihood MAgO 2019 2028 Processing center constructed; processing equipment MGDP/BFAR/ Other 37,000.000 37,000.000 1, 4 1 3 3.2 5
procured; and conducted livelihood trainings for Sources
abaca expansion, crop production, animal raising,
and fish production
8000-3-02-004-17* Livelihood Projects for Indigenous People of MAgO, DA 2023 2028 Trading of Agricultural Products, Draft Animals MGOP/ other 33,000.000 33,000.000 1, 4, 11 2.3 3 3.2 5
Pinamalayan dispersal, Abaca Expansion Project, trainings sources
attended/conducted
8000-3-02-004-18 Provision of Alternative Livelihood Activities MAgO, MENRO, SCO 2020 2023 Livelihood activities identified; networking/tie-up with MGOP/ other 2,000.000 2,000.000 1, 4, 20 12.5 3 3.2 5,5.11
from recycled materials NGOS, OGAs, or foundations establsihed; capacity sources
building conducted; and finished products marketed
8000-3-03-003-a-1-2* Commercial Building MOD, MEO 2025 2028 Two storey twin commercial building construced MGOP/ other 105,000.000 105,000.000 1, 4, 9 8 3,4 3.1,3.2 3.2
sources
1 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-03-003-a-1-3* Establishment of Supermall (2-storey MHO 2021 2022 Two storey twin commercial building construced MGOP/ other 220,000.000 220,000.000 1, 4, 9, 15 8 3,4 3.2 3.2
commercial building) sources
8000-3-03-003-a-1-4* Conversion/Upgrading of Municipal Food SB, MAgO, MEO 2025 2027 Food terminal upgraded to regional food terminal MGOP/DA/ Other 20,000.000 20,000.000 1,3,4,8, 15 8 3,4 3.1,3.2 3.1
Terminal to Regional Food Terminal Sources
8000-3-03-003-a-1-5* Establishment of Trading Facility or Local MEO 2022 2026 2,306.45 sqm. Local Exchange Trading Terminal MGOP/Other 15,000.000 15,000.000 1, 4, 9 8 3,4 3.2 3.2
Exchange Trading Terminal (LETT) constructed sources
8000-3-03-003-b-3-1 Installation of Public Address System within MEO 2022 2028 Public address equipment procured and installed MGOP/ other 40,000.000 40,000.000 19 9 4,7 3.2 4.2
Poblacion Area sources
NEW GOVERNMENT CENTER
1000-3-01-006-1 Land banking for government offices (10 ha) MAssO 2023 2026 10 hectares of land purchased MGOP/ Other 20,000.000 20,000.000 1, 4 8 4 3.1 7
Sources
1000-3-01-006-2 New municipal government center MEO 2026 2028 Office Buildings, Parking Area, Sorage Buildings, MGOP/ Other 100,000.000 100,000.000 1, 4 9.1 4 3.1 7
Evacuation Area, Perimter Fence and other facilities Sources
constructed
8000-3-01-010-a-2 Construction of Convention Center MEO 2022 2022 2500 sq.m. lot acquired; 2,000 sq.m. building MGOP/PGOrM/ 50,000.000 50,000.000 4,7,9,19 9 4,6 3.1,3.2 3,5.12
constructed; 500 sq.m parking constructed; Other sources
landscaping
1000-3-01-006-3 Acquisition of Lots for Future Expansion MAssO 2021 2028 50 ha of land acquired MGOP/PGOrM/ 50,000.000 50,000.000 19 9,11,12 3,4 3.1,3.2 6.1
Other sources
PINAMALAYAN PUBLIC MEMORIAL PARK
8000-3-02-004-16 Establishment of New Pinamalayan Public MAssO, MENRO, MEO 2020 2021 5 hectares memorial park developed MGOP/ other 5,500.000 5,500.000 1,4 8, 11.7 4 3.1,3.2 5.12,6.1
Memorial Park sources
1000-3-01-006-4 Land banking for public cemetery (5ha) MAssO 2020 2024 5 hectares of land purchased for the construction of a MGOP/ Other 10,000.000 10,000.000 19 11 4 3.1,3.2 6.1
new public cemetery Sources
8000-3-02-004-20 Establishment of new public spaces or MENRO, MEO 2027 2028 New Public Spaces facility intended for recreation MGOP/ other 9,000.000 9,000.000 10,20 9,11 4 3.1,3.2,6.3 5.12,6.1
recreational park established sources
REHABILITATION, PROTECTION, AND IMPROVEMENT OF
WATERWAYS PROGRAM
8000-3-02-004-7* Construction of Comprehensive Sewerage MENRO, MEO 2020 2024 Comprehensive Sewerage System constructed within MGOP/ other 20,000.000 20,000.000 20,000.000 A214-04 1,4 6.3 4 5.3 5.1-0
System at Poblacion Area the Poblacion, master Septic Tank constructed sources
8000-3-02-004-8 Construction of Centralized Wastewater MENRO, MEO 2020 2021 Building constructed, waste water treatment MGOP/ other 6,500.000 6,500.000 6,500.000 A214-04 1,4, 19 6.3 4 3.2,5.2 5.1-0
Treatment at Poblacion Area machines purchased sources
8000-3-02-004-9 Rehabilitation of flood control dikes, irrigation MDRRMO, NIA 2022 2022 Flood Control Dikes, Irrgiation Canals and Drainages MGOP/ other 5,000.000 5,000.000 5,000.000 A224-02 1, 3, 4, 8, 11 9, 13 4 3.1,5.3 5.1-0
canals and drainages constructed sources
8000-3-01-010-a-2 Rehabilitation of irrigation canals in MEO 2024 2024 Comprehensive Drainage Plan MGOP/NIA/ Other 5,000.000 5,000.000 5,000.000 A114-05 1, 4, 8 2 4 3.1,3.2 3.1
Pinamalayan sources
8000-3-01-010-a-3 Comprehensive Drainage Plan MEO 2022 2028 Drainage plan formulated; existing drainage canals MGOP/ other 322,000.000 322,000.000 322,000.000 A224-01 1, 4 6.3 4 3.2 5.1-0,6
rehabilitated and desilted; natural ways desilted sources
8000-3-01-010-a-4 Construction of Drainage Canal with Curb, MEO 2024 2024 200.5 linear meters of drainage canal with curb, MGOP/ DPWH/ 3,000.000 3,000.000 1, 4 9 4 3.2 5.1-0
Gutter and Box Culvert gutter, and box culvert constructed Other sources
2 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-01-010-a-5 Concreting of Communal Canal MAgO 2020 2024 Communal canals at barangays Calingag, Sta. Isabel, MGOP/NIA/ Other 10,000.000 10,000.000 10,000.000 A114-05 1, 4 2 2,4 3.1,3.2 3.1
Malaya, Maliancog, Pambisan Malaki, Papandayan, sources
Cacawan, Buli, Del Razon & Pambisan Munti
concreted
8000-3-01-010-a-6 Desilting of Drainage Canals within Poblacion MEO 2021 2021 Drainage canal in poblacion area declogged and MGOP/PGOrM/ 700.000 700.000 1, 4 6.3 4 3.1,3.2 5.1-0
desilted Other sources
8000-3-01-010-a-7 Upgrading of drainage canals MEO 2021 2022 Drainage Canal in front of Municipal Compound MGOP/PGOrM/ 1,100.000 1,100.000 1,100.000 A224-01 1, 4, 19 6.3 4 3.2 5.1-0
along Madrid Blvd upgraded Other sources
8000-3-01-010-a-8 Construction of Comprehensive Sewerage MENRO, MEO 2022 2025 Endpoint Master Septic Tank constructed MGOP/PGOrM/ 20,000.000 20,000.000 20,000.000 A232-01 19,20 6,9,11 4 3.2 5.1-0
System Other sources
8000-3-02-004-10* Conduct of a Comprehensive Topographic Zoning Division 2020 2026 Comprehensive Topographic Survey conducted in the MGOP/ other 60,000.000 60,000.000 60,000.000 A631-01 1, 4, 19 9,11 3,4 3.1,3.2 6
Survey Poblacion area sources
8000-3-02-004-11 Construction of Riverbank Protection Dike in all MDRRMO, DPWH 2021 2022 River Protection Dike in all barangays along Pula MGOP/ other 150,000.000 150,000.000 1, 4, 19 6.6, 13, 15 3,4 3.1,3.2,5.3 5.1-0
barangays along Pula River River constructed sources
8000-3-01-010-a-9* Desilting of upstream of Inclanay Dam MEO 2022 2022 Inclanay river banks desilted MGOP/NIA/ Other 50,000.000 50,000.000 50,000.000 A114-05 1, 4 6.6, 15 2,3,4 3.2 5.1-0
sources
8000-3-02-004-12 River Protection Program MDRRMO, MENRO, 2020 2024 River Protection Program created MGOP/ other 50,000.000 50,000.000 50,000.000 M314-07 1, 4, 20 6.6, 15 2,4 5.2 2
DENR sources
8000-3-01-010-a-10 Desilting of natural waterways MENRO, MEO 2020 2021 Obstructions on the natural flow of waters and all MGOP/PGOrM/ 5,500.000 5,500.000 5,500.000 M634-02 1, 4 6.6, 15 3,4 3.1,3.2,5.3 2
structures along banks of rivers and creeks illegally Other sources
constructed removed
8000-3-01-010-a-11 Construction of breakwater MEO 2020 2021 Breakwater constructed MGOP/PGOrM/ 180,000.000 180,000.000 180,000.000 A224-02 11,19 9,11 2,3,4 3.2 5.12,6.1
Other sources
8000-3-01-010-a-12 Construction of Seawall MEO 2022 2022 3,080 meters of seawall cosntructed MGOP/PGOrM/ 200,000.000 200,000.000 200,000.000 A634-01 1,4, 8, 11 13 2 3.2,5.2 5.1-0
Other sources
8000-3-02-004-21 Mangrove Rehabilitation MAgO, MDRRM, 2028 2028 Mangrove areas rehabilitated MGOP/ other 10,000.000 10,000.000 10,000.000 A224-03 1, 4, 20 6.6, 15 1,2,3,4,5 5.2 2
MENRO, DENR sources
HOUSING PROGRAM
3000-3-02-005-2 Core Shelter Assistance Program MSWDO, MEO 2022 2028 150 Core Housing Units constructed; basic amenities MGOP/ other 52,500.000 52,500.000 52,500.000 A424-06 1, 4, 12, 19 11.1 2,4,6 2.4,3.2,6.2 5.4
installed (water, electricity); roadways and drainage sources
canal constructed
3000-3-02-005-3** Socialized Housing Project MSWDO, MEO 2025 2027 5 ha lot developed; 200 housing units constructed MGOP/DSWDO/ 100,000.000 100,000.000 100,000.000 A424-06 10,11,12 11.1 2,4,6 2.4,3.2,6.2 5.4
Other sources
3000-3-02-005-4** Employees’ Housing Program MSWDO, MEO 2024 2028 5 hectares of Land acquired, 100 Socialized Housing MGOP/ other 50,000.000 50,000.000 1, 4, 12, 19 11.1 2,4,6 2.4,3.2,6.2 5.4
Units constructed sources
1000-3-01-006-5 Land Banking for Employees’ Housing MAssO 2023 2024 5 hectares of land purchased for the construction of MGOP/ Other 10,000.000 10,000.000 10,11,12 11 4 3.1,3.2 7
Program Employee's Housing Sources
8000-3-02-004-13 Relocation of informal settlers in coastal areas MDRRMO, DENR 2020 2022 All Informal Settlers along coastal areas relocated to MGOP/ other 10,000.000 10,000.000 10,000.000 A424-13 1, 4, 11, 12 1.5, 11.5 1, 2 3.1,3.2 5.4
safer places sources
HEALTH AND NUTRITION PROGRAM
3000-200-3-03-001-1* Health Card for Pinamalayan Residents MO, MHO 2020 2028 Medicard provided from authorized companies with MGOP/DOH/ Other 200,000.000 200,000.000 200,000.000 A414-06 10,11 1,3 2,4 3.2 1,5.2
100% coverage in 2028 Sources
3 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
3000-200-3-03-001-2 Provision and Installation of Sanitary Toilet MHO 2023 2023 2,500 sanitary toilet facilities provided and installed MGOP/DOH/ Other 2,500.000 2,500.000 2,500.000 A211-05 1, 4, 10 6.2 4 3.2,5.2 5.8
Facilities Sources
3000-200-3-03-001-3 Construction of Social Hygiene Clinic MHO 2019 2020 Social Hygiene clinic constructed; equipmetn MGOP/DOH/ Other 500.000 500.000 1, 4, 10, 13, 3.3 4 3.1,3.2 5.2
purchased; manpower hired and trained Sources 19
3000-200-3-03-001-4 Acquisition of Mobile Clinic MHO 2028 2028 Purchased mobile clinic; manpower added and MGOP/DOH/ Other 10,000.000 10,000.000 1, 4, 10, 13, 4 3.1,3.2 5.2
trained; medical equipment and mediicnes procured Sources 19
3000-200-3-03-001-5 Provision of Anti-Rabies Vaccine MHO 2021 2021 MGOP/DOH/ Other 1,000.000 1,000.000 1, 4, 10, 13 3.8 2,4 3.1,3.2,6.2 5.2
Sources
3000-200-3-03-001-6 Establishment of Public Tertiary Hospital MHO/LGU/DOH 2025 2028 Existing building upgraded; hospital equipment MGOP/DOH/ Other 100,000.000 100,000.000 1, 4, 10, 13, 3 1,2,4 3.1,3.2,6.2 5.2
procured; additional health personnel hired and Sources 19
trained
3000-200-3-03-001-7 Acquisition of Ambulances VMO, SB 2020 2026 Additional unit of ambulance acquired MGOP/DOH/ Other 4,000.000 4,000.000 1, 4, 10, 13 3 2,4 3.1,3.2.6.2 5.2
Sources
3000-200-3-03-001-8 Rehabilitation of West District Health Center MHO, MEO 2019 2022 Existing facility rehabilitated; health staff trained MGOP/DOH/ Other 1,000.000 1,000.000 10,19 3,9 2,4 3.1,3.2,6.2 5.2
Sources
3000-200-3-03-001-9 Establishment of Smoking Cessation Clinic MHO 2019 2019 Smoking Cessation Clinic provided; counselors MGOP/DOH/ Other 100.000 100.000 10 3 4 3.1,3.2 5.2
trained; logistics and supplies provided Sources
3000-200-3-03-001-10 Acquisition of MHO Service Vehicle MHO 2020 2020 1 service vehicle acquired MGOP/DOH/ Other 1,500.000 1,500.000 10 1 4 6.2 1
Sources
PUBLIC EDUCATION DEVELOPMENT PROGRAM
3000-100-3-03-001-1 Establishment of Public Tertiary MGOP/DepEd/ DPWH 2019 2028 Lot acquired; school buildings constructed; MGOP/DepEd/ 90,000.000 90,000.000 1, 4, 10, 13 4.3 4 3.2 5.3
Institution/School equipment, furnitures and fixtures purchased; DPWH/ Other
manpower hired; and vehicle purchased Sources
8000-3-01-010-a-13 Rehabilitation of public school buildings and MEO Public school buildings and facilities rehabilitated MGOP/DepEd/ 60,000.000 60,000.000 60,000.000 A424-12 1, 4, 10, 19 4 4 3.1,3.2 5.3
facilities including roofing, repainting, rehabilitation of existing DPWH/ Other
structures, buildings, and facilities Sources
3000-3-03-001-4-1 Construction of ALS Learning Center in MGOP, TESDA 2019 2022 Building constructed; equipment acquired; and MGOP/DepEd/ 3,000.000 3,000.000 1,10,19 4,8 4 3.1,3.2,6.3,6 5.3
Pinamalayan trainors hired DPWH/ Other .4
Sources
3000-3-03-001-4-2 Construction of TESDA Accredited Training MGOP, TESDA 2019 2020 Building constructed; equipment acquired; and MGOP/TESDA/ 4,000.000 4,000.000 1,10,19 8 4 3.1,3.2,6.3,6
Center trainors hired Other Sources .4
3000-100-3-03-001-b-2-1 Establishment of SPED Center in MASMES DepEd 2019 2020 SPED Center constructed; trainings and seminars of MGOP/DepEd/ 1,400.000 1,400.000 10,19 9 4 3.1,3.2 5.3
qualified SPED teacher conducted; Other Sources
uniforms/shoes/bags/supplies and teaching materials
and equipments provided
3000-100-3-03-001-1-3 E-Eskwela MGOP, ALS 2019 2028 Customized Instruction Models provided; trainors MGOP/DepEd/ 1,000.000 1,000.000 10 4,9 4 3.1,3.2 5.3
equipped; stakeholders training conducted Other Sources
4 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
3000-100-3-03-001-b-1-1 Upgrading of Existing SPED Center DepEd 2019 2022 Existing SPED Center upgraded; equipment MGOP/DepEd/ 2,000.000 2,000.000 10,14 4,10 4 3.1,3.2,6.2 5.3
acquired; qualified SPED teacher hired and trained; Other Sources
uniforms/shoes/bags/supplies and teaching materials
provided
3000-100-3-03-001-a-1 Project SAFE (Secure, Accommodating, MEO, DepED 2019 2028 33 elementary schools, 12 secondary schools, and 2 MGOP/DepEd/ 23,173.000 23,173.000 23,173.000 A424-11 10,14 4,10 4 3.1,3.2,6.2 5.3
Friendly Environment) district offices rehabilitated; school facilities Other Sources
constructed; furnitures and foxtures acquired
3000-100-3-03-001-a-2 Project HEART (Provision of Multimedia MO, DepEd 2019 2028 LED TV, projectors, laptop, desktop computer MGOP/DepEd/ 8,000.000 8,000.000 10,14 4 4 3.1,3.2 5.3
Instructional Materials) acquired; WIFI Connection installed; SHS reference Other Sources
books and other reading materials provided; training
and seminars conducted
8000-3-01-010-a-14 Construction of Overpass in ABADA College MEO 2022 2028 Overpass constructed MGOP/DPWH/ 1,500.000 1,500.000 11,12,19 9,11 4 3.2 4
and Nabuslot National High School DepEd/ Other
Sources
1000-3-03-001-2-17-1 Repair and Improvement of all Office Buildings MEO 2020 2022 Buildings repainted ; windows and doors repaired; MGOP/PGOrM/ 10,000.000 10,000.000 1, 4 9 4 3.1,3.2,6.4 7
and facilities (MTC included and other offices) roofing replaced; and electrical works such as Other sources
rewiring conducted
8000-3-01-010-a-16* Improvement of Municipal Engineering Office MEO 2021 2021 Cubicles and cabinets constructed; ceiling installed; MGOP/ other 1,500.000 1,500.000 1, 4 9 4 3.1,3.2 7
flooring repaired; and door grills installed sources
1000-3-01-007-1 Construction of Stockroom for accounts, MEO, GSD 2021 2023 500 sq.m. stockroom for account, reports and MGOP/ Other 115,000.000 115,000.000 1, 4, 5 16 4 2.2,2.3 7
reports and records records of government offices constructed Sources
1000-3-01-001-a-1 Construction of Warehouse for PPEs and GSD, MEO 2021 2022 1,000 sq.m. warehouse constructed MGOP/ Other 15,000.000 15,000.000 1, 4, 5 16 4 2.2,2.3 7
construction materials Sources
1000-3-01-005-1 Repair and Improvement of Taxpayers' Lounge MTO, MEO 2020 2021 Eight teller booth installed; gender sensitive comfort MGOP/ Other 910.000 910.000 1, 4, 5 9 4 3.1,3.2 7
rooms construted; desktop computers, gang chairs, Sources
water dispenser, TV set, air conditioning unit provided
8000-3-01-010-a-1 Rehabilitation of Perimeter Fence of Municipal MEO 2023 2023 426.8 linear meters of perimteter fence constructed MGOP/ Other 1,500.000 1,500.000 1, 4 9 4 3.1,3.2 7
Compound Sources
8000-3-01-010-a-2 Improvement of manpower development center MEO 2022 2022 Stage upgraded, lightings installed, and building MGOP/ Other 500.000 500.000 1, 4 9 4 3.1,3.2,6.3 7
repainted Sources
TOURISM DEVELOPMENT PROGRAM
8000-3-01-010-a-3 Development of Existing Tourism Sites SCO, MEO 2023 2025 10 tourism sites developed; facilities and amenities MGOP/DOT-TIEZA/ 10,000.000 10,000.000 1, 4 8 3,4,6 3.2,3.35.2,5. 3.3
constructed Other sources 4
5 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-01-010-a-4 Construction of Access Roads leading to MEO 2019 2028 20 access roads constructed MGOP/DOT-TIEZA/ 50,000.000 50,000.000 1, 4, 19 9 4 3.2 3.3
Tourisms Sites Other sources
8000-3-01-010-a-17* Development of Potential Tourism SCO, MEO 2027 2028 10 tourism sites developed MGOP/DOT-TIEZA/ 10,000.000 10,000.000 1, 4 8 3,4,6 3.2,3.3,5.2,5 3.3
Attractions/Destinations Other sources .4
3000-3-03-001-1-1* Rehabilitation of Municipal Park and MEO 2023 2026 perimeter fence and children's playground repaired MGOP/ other 20,000.000 20,000.000 1, 4 11.7 4 3.1 1,5.12
Playground and repainted sources
8000-3-01-010-a-5 Establishment of Mangrove Eco Park MAgO/ MENRO 2023 2023 Mangrove Conservation Eco Park developed MGOP/BFAR/ Other 2,000.000 2,000.000 2,000.000 A224-03 1, 4, 20 8 2,5 5.4 3.3
Sources
8000-3-01-010-a-18* Establishment of Trails for Tourist Spot MEO, SCO 2023 2023 Steps with steel guard rails constructed MGOP/DOT-TIEZA/ 1,600.000 1,600.000 1, 4, 19 9 4 3.2 3.3
Other sources
8000-3-02-004-19 Establishment of Wildlife Facility or Sanctuary MENRO, CENRO 2020 2021 Wildlife Rescue Facility constructed, Hiring of MGOP/ other 2,300.000 2,300.000 2,300.000 M314-02 20 6 1,3,4 3.1,5.2,5.3 2
Technical Personnel and Caretaker sources
CENTRALIZED GRAND TERMINAL
1000-3-01-006-6 Land banking for grand terminal MAssO 2023 2024 4 ha of lot purhcased MGOP/ Other 8,000.000 8,000.000 1, 4 8 4 3.1,3.2 7
Sources
8000-3-01-010-a-19* Construction of Grand Terminal MEO 2019 2022 Perimeter fence, road networks, drainage canal, MGOP/DPWH/ 606,000.000 606,000.000 1, 3, 4 9.1 3,4 3.2 4
administrative building, waiting areas, pasalubong DOTR/ Other
center, and eatery constructed Sources
8000-3-01-010-a-20 Construction of Lumambayan bridges I, II, III, MEO 2022 2028 Lumambayan Bridge I (L=30m, W=6m); Bridge II ( MGOP/PGOrM/ 190,000.000 190,000.000 190,000.000 A224-02 1, 3, 4, 19 9 4 3.2 4
Sta. Isabel 60m , W=6m); Bridge III ( L=30m, W=6m); and DPWH/ Other
Sta.Isabel Bridge ( L=10m, W=3.6m) constructed Sources
8000-3-01-010-a-21 Coastal Greenway MEO 2022 2028 7.5 km coastal greenway constructed MGOP/PGOrM/ 150,000.000 150,000.000 1, 3, 4, 19 9 4 3.2 4
DPWH/ Other
Sources
8000-3-01-010-a-22 Concreting of Municipal Roads MEO 2023 2023 509.59 or 702 meters of municipal road concreted MGOP/PGOrM/ 1,065.000 1,065.000 1,065.000 A634-04 1, 3, 4, 19 9 4 3.2 4
DPWH/ Other
Sources
8000-3-01-010-a-23 Rehabilitation of Roads MEO 2019 2028 34.59 km of roads rehabilitated MGOP/PGOrM/ 126,000.000 126,000.000 126,000.000 A634-04 1, 3, 4, 19 9 4 3.2 4
DPWH/ Other
Sources
6 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-01-010-a-24 Concreting of Barangay Roads MEO 2019 2028 41.49 km concreted barangay roads MGOP/PGOrM/ 105,000.000 105,000.000 105,000.000 A634-04 1, 3, 4 9 4 3.2 4
DPWH/ Other
Sources
8000-3-01-010-a-25 Opening of proposed roads MEO 2022 2028 6 km of roads opened MGOP/PGOrM/ 70,000.000 70,000.000 140,004.050 19 9 4 3.1,3.2 4,6
DPWH/ Other
Sources
8000-3-01-010-a-26 Installation of Road Signs (Warning Signs, MEO, DPWH 2019 2028 50 pcs warning Signs and 50 pcs regulatory signs MGOP/ Other 1,330.000 1,330.000 18,19 9,11 3,4 3.1,3.2 4,5.12
Regulatory Signs) installed Sources
8000-3-01-010-a-27 Construction of dropped curb at pedestrian MEO 2022 2022 Additional ramp for PWD constructed; pedestrian MGOP/ Other 600.000 600.000 18,19 9,11 4 3.2 4
crossing and at the end of walkways of access lane provided; island fo the pedestrian lane removed; Sources
roads and signage for pedestrian lane and PWDE provided
8000-3-01-010-a-28 Pedestrian Crossings MEO, DPWH 2019 2028 40 pcs pedestrian crossings provided MGOP/ Other 864.000 864.000 864.000 M631-04 18,19 9,11 4 3.2 4
Sources
8000-3-01-010-a-29 Upgrading of Existing Roads MEO 2022 2028 MGOP/PGOrM/ 358,380.000 358,380.000 358,380.000 A634-04 1, 3, 4, 19 9 4 3.1,3.2 4
DPWH/ Other
Sources
8000-3-01-010-a-30 Construction of Multi-purpose hall/covered MEO 2019 2028 33 multi-purpose hall buildings constructed MGOP/ other 82,500.000 82,500.000 1, 4 11.7 4,5,7 3.1,3.2,6.3 7
court in every barangay (33 barangays) soources
8000-3-01-010-a-31 Rehabilitation of Road Shoulder MEO 2022 2022 Obstruction encroachment removed; and gravel MGOP/PGOrM/ 500.000 500.000 500.000 A634-06 1, 3, 4, 19 9 4 3.2 4
shoulder resurfaced; road shoulder rehabilitated DPWH/ Other
Sources
8000-3-01-010-a-32 Improvement of Marfrancisco Triangle MEO 2021 2021 Tiles set; pathway with curb concreted; stairs railing MGOP/PGOrM/ 1,000.000 1,000.000 1, 4, 7 9 3,4 6.1 3.3
constructed; concrete logo installed; lighting added; DPWH/ Other
landscaping and repainting of the triangle Sources
8000-3-01-010-a-33 Installation or Fabrication of Streetlights MEO 2026 2028 348 units LED streetlights installed MGOP/PGOrM/ 15,000.000 15,000.000 1, 4 7 4 3.1,3.2 5.9
DPWH/ Other
Sources
8000-3-01-010-a-34 Electrification program ORMECO 2019 2028 197 poles installed MGOP/NEA/ Other 10,835.000 10,835.000 1, 4 7.1 4 3.1,3.2 5.9
Sources
8000-3-01-010-a-35 Formulation of Comprehensive Road Network MEO 2022 2028 Topographic survey conducted; surveying instrument MGOP/ Other 15,000.000 15,000.000 1, 3, 4, 19 9 4 3.1,3.2 5
Plan acquired Sources
8000-3-01-010-a-36 Rehabilitation/upgrading of existing port MEO 2022 2028 Port facilities rehabilitated MGOP/PGOrM/ 200,000.000 200,000.000 19 9,11 4 3.1,3.2 4.1,6.1
facilities DPWH/ Other
Sources
8000-3-01-010-a-37 Purchase of appropriate heavy equipment MEO 2019 2022 4 units 6 wheeler dumptruck, 1 Pay Loader, and 1 MGOP/ Other 40,000.000 40,000.000 1, 4,19 9 4 3.1,3.2 7
Road Grader aggregates purchased Sources
8000-3-01-010-a-38 Rehabilitation or upgrading of existing NIA MEO 2022 2028 NIA roads rehabilitated MGOP/NIA/ Other 160,000.000 160,000.000 160,000.000 A634-04 8,19 9 4 3.2 3.1,4.2
Roads sources
8000-3-01-010-a-39 Expansion of airport MEO 2022 2028 Elevated runway; embankment; pavement concreted; MGOP/DOTR/ 135,000.000 135,000.000 135,000.000 A634-04 19 9,11 4 3.1,3.2 4.1,6.1
lightings installed; building constructed; station of DPWH/ Other
building upgraded Sources
7 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
8000-3-02-004-23 Rehabilitation of Existing Public Cemetery MENRO, MEO, MAssO 2019 2020 Crematorium/Columbarium constructed at Barangay MGOP/ other 15,000.000 15,000.000 19 6,11 4 3.1,3.2 5.8,6.1
Papandayan sources
8000-3-01-010-a-40 Construction and Furnishing of Tricycle for Hire MDRRMO, MEO, PNP, 2021 2022 Public comfort room constructed; 28 pcs. gang MGOP/ other 5,000.000 5,000.000 19 9 4 3.1,3.2 4
Terminal PLD seaters procured; public address system and CCTV sources
installed; and Public Assistance Complaints Desk
(PACD) provided
3000-3-03-001-3-2* Establishment of Modern Sports Complex MEO 2022 2028 Lot purhcased; track and field oval developed; MGOP/PGOrM/ 200,000.000 200,000.000 1, 4 11.7 4 3.1,3.2 5.12
grandstand, swimming pool, dormitory, and covered DPWH/ Other
court constructed Sources
3000-3-02-005-7 Conversion of Convention Center into Crisis MEO 2019 2020 Building rehabilitated; equipment purchased MGOP/DSWD/ 6,000.000 6,000.000 1, 4, 10 3 4 3.1, 3.2 5
Center Other Sources
1000-3-01-006-7 Land Banking for social services such as MAssO, MENRO, 2022 2028 25 hectares of lot acquired MGOP/DSWD/ 25,000.000 25,000.000 1, 4 8,11 4 3.1,3.2 7
MSWDO compound, PRTO and other CSOs, MSWDO Other Sources
Police outposts, BFP lot (25 ha)
3000-3-02-005-2-4-1 Construction of Additional Barangay Senior MEO 2019 2028 10 Senior Citizens Affairs Centers constructed MGOP/DSWD/ 5,500.000 5,500.000 1, 4 9 4 3.1,3.2 5
Citizens Affairs Centers Other Sources
3000-3-02-005-8 Construction of Pinamalayan Retired Teachers MEO 2019 2020 100 sqm one-story building constructed MGOP/DSWD/ 1,500.000 1,500.000 1, 4 9 4 3.1,3.2 7
Organization (PRTO) Building Other Sources
3000-3-02-005-9 Establishment of Persons with Disability Affairs MAssO 2019 2028 PDA officer hired; IDs & Booklets procured; MGOP/DSWD/ 4,000.000 4,000.000 1, 4,11 10.3 4 3.1,3.2,6.2,6 5
Office (PDAO) Orientation on Magna Carta for PWDs (Benefits and Other Sources .3
Privileges of PWD) conducted; Business Forum on
the Rights of Persons with Disabilities conducted;
Livelihood Assistance (Salted Egg Production)
provided; PWD of Sta. Rita organized; Medical
Mission and other activities conducted
8 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
3000-3-02-005-10 Acquisition of MSWDO Service Vehicle MSWDO 2020 2020 Service vehicle acquired MGOP/ Other 1,500.000 1,500.000 1, 4, 13 3 2,4 3.1,3.2,6.2 5
Sources
3000-3-02-005-11 Construction of Local Council for Women MEO, LCW 2020 2021 24m x 40m multi-purpose hall constructed MGOP/DSWD/ 17,280.000 17,280.000 10,19 5,9 4 3.1,3.2,6.3 5.12
Office with Multi-Purpose Hall Other Sources
CROP/LIVESTOCK DEVELOPMENT PROGRAM
8000-3-02-003-5 Crop Development Program MAgO, DA, MEO, 2019 2028 Facility constructed; mechanical dryer purchased and MGOP/DA/ 41,000.000 41,000.000 41,000.000 A114-03 1,4,8 2.4 3,4,7 3.1,3.2,5.3 3.1
(Construction/Installation of mechanical dryer; PhilFIDA installed; vegetables seeds and organic fertilizers PhilFIDA/ Other
Vegetable Production; Construction of Small purchased; trained beneficiaries; small water sources
Water Impounding Facility; Abaca Production) impounding facility constructed; abaca planting
materials and abaca fiber extraction machines and
equipment purchased
8000-3-02-003-6 Livestock Development Program MAgO 2026 2026 Piglets purchased and dispersed MGOP/ other 500.000 500.000 500.000 A414-04 1,4, 8 2 3 3.1,3.2 3.1
sources
8000-3-02-003-7 Establishment of Auction Market with holding MAgO, MEO 2028 2028 Auction Market with temporary Holding Pen GF 40,000.000 40,000.000 4, 8 2 3,4 3.1,3.2 3.1
pen constructed
8000-3-03-003-a-2-1* Upgrading of the Slaughterhouse Building and SOD, MEO, MAssO 2022 2026 Municipal Slaughterhouse to"Double A" Category MGOP/ NMIS/ Other 5,278.500 5,278.500 1, 4 8 4 3.1,3.2 3.1
Facilities accreditated ; Backyard pavement concreted; Sources
Perimeter concrete fence constructed; Waiting Area
with comfort rooms outside the Slaughterhouse
building constructed; Septic Tank (Biodegradable and
Non-biodegradable) constructed; Roofing of Animals
Holding/Dispatching Area (Auxiliary Part of the Main
Building) installed; Stainless inspection table
fabricated; and acquired leg spreader, beef shackle,
carwash machine, booster blower, grass cutter,
weighing cale, pressurized motor pump, dehairing
machine, and refrigerated delivery van
8000-3-02-003-8 Construction of Multi-purpose Farmers MAgO 2028 2028 Multi-Purpose Farmers Training Center constructed MGOP/DA/ 10,000.000 10,000.000 1,4, 8 2 3,4 3.1,3.2 3.1
Training Center PhilFIDA/ Other
sources
8000-3-02-003-9 Farm Mechanization Program MAgO, DA 2019 2028 Hand Tractor with Trailer acquired; Shallow Tube MGOP/DA/ 18,300.000 18,300.000 1,4, 8 2 3,4 3.1,3.2 3.1
Well installed; Rice Combine Harvester procured; and PhilFIDA/ Other
Four Wheeled Farm Tractor procured sources
8000-3-02-003-10 Construction of Building (Office/Function Hall MAgO, DA 2019 2021 Building for Farmers’ Federation Office, Function MGOP/DA/ 10,000.000 10,000.000 1,4, 8 2 3,4 3.1,3.2 3.1
and Garage for farm equipment) Hall, and Garage for farm Equipment constructed PhilFIDA/ Other
sources
8000-3-02-004-24 Establishment of Tree Nursery MAgO, DA 2019 2020 Tree Nursery established at AC/BS Sto. Niño MGOP/ other 3,000.000 3,000.000 3,000.000 M314-04 1, 4, 20 6.6, 15 1,3,4 3.1,5.2,5.3 2
sources
9 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
1000-3-01-009-1* Updating of community-based disaggregated MPDO, CBMS-TWG 2022 2026 CBMS Database updated; CBMS-Based Municipal MGOP/PGOrM/ 10,000.000 10,000.000 5,13 1,2,3,4,8,10 1,2 3.1,3.2,6.2 5
data and Barangay Profile and Development Plan updated Other Sources
1000-3-01-006-8 Updating of Inventory of Real Property Units MAssO 2026 2026 Accurate and updated inventory of real properties MGOP/ Other 650.000 650.000 1, 4, 5 16 3,4 3.1,3.2 7
(RPUs) Sources
1000-3-01-009-1 Computerization Program/Information and MO 2020 2028 ICT Office with permanent positions established; ICT MGOP/ Other 15,000.000 15,000.000 1, 3, 4, 19 17.18 4 3.2 4
Communications Technology (ICT-CeC) Administration Building constructed furnished with Sources
Project needed IT equipment, office equipment, furniture and
fixtures, transportation vehicles, etc.; Agency
Information Kiosk developed; Centralized Local Area
Network and Information System established; and e-
Billboard installed and functional
1000-3-01-002-1 Establishment of municipal eLibrary VMO, SB 2021 2021 Study Tour conucted; hardware & software procured; MGOP/ Other 1,040.000 1,040.000 1, 4, 5 16 4 3.2 7
system and internet installed; orientation & briefing Sources
conducted
1000-3-03-001-2-13-2* Modernizing of Firefighting Tools, Apparatus, MO 2019 2028 Protective gears, fire axe, chainsaw, hydraulic MGOP/BFP/ Other 800.000 800.000 1, 4 11 1,2,3,4 3.1,3.2 5.6
and Equipment spreader, rescue ropes with carabiners, pulleys and Sources
other high angle rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty flashlights,
laddered firetruck procured
1000-3-03-001-2-13-3* Installation of Additional Fire Hydrants BFP, MEO 2019 2028 fire hydrants installed MGOP/BFP/ Other 1,000.000 1,000.000 11,18 11 4 3.1,3.2 5.6
Sources
1000-3-03-001-2-13-4* Upgrading of BFP Building and Facilities BFP 2019 2028 Office, personnel quarters, gate and fence repainted; MGOP/BFP/ Other 600.000 600.000 18 9,11,16,17 4 3.1,3.2 5.6
and stockroom upgraded Sources
1000-3-03-001-2-12-1 Construction of 8 Mobile Police Outpost in MEO, PNP 2019 2028 8 mobile police outputs constructed MGOP/PNP/ Other 4,000.000 4,000.000 10,17,18 9,11 4 1.1,1.2,1.3,1
Strategic Locations Sources .4,3.1
1000-3-03-001-2-12-2 Acquisition of 1 unit Mobile Patrol Vehicle PNP 2020 2020 Mobile patrol vehicle acquired MGOP/PNP/ Other 2,000.000 2,000.000 10 1 4 6.2 1,5
Sources
10 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
☐ No Climate Change Expenditure (Please tick box if your LGU does not have any climate change expenditure
AIP Maintenance
Program/Project/Activity Title Implementing Expected Funding Climate
Reference Personal and Other
/Description (2) Office/ Department (3) Completion Output Source Capital Total Climate Change Climate Change Change PDP SDG SenNDAI NSP PDPFP
Code (1) Start Date (4) Services Operating
Date (5) Outlay (10) (8+9+10) Adaptation Mitigation Typology (15) (16) (17) (18) (19)
(PS) (8) Expenses
Code
(MOOE) (9)
1000-3-03-001-2-12-3 Upgrading of PNP Building and Facilities MEO, PNP 2019 2022 Conference room constructed with fixed table and MGOP/PNP/ Other 2,500.000 2,500.000 6,17,18 9,11,16,17 4 1.1,1.2,1.3,1 5.5,5.7
chair that can accommodate up to 70 persons; Sources .4,3.1,3.2
whiteboard, projector screen, conference microphone
system, audio conference system, and video
conference system purchased and installed;
conference room wall, window, and door glass
constructed; and air conditioning system conference
room installed
Prepared by: Attested by: Certified correct and approved by the LDC:
EnP ROSENIO A. TORIANO ZAIDA D. MICIANO PLARIDEL S. CUPIADO ARISTEO APASAN BALDOS, JR.
Municipal Planning and Development Coordinator Local Budget Officer Local Treasurer Municipal/LDC Chairman
11 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
AIP PROJECTS FOR 2019 MGOP/ Other 2019 2019 - MGOP/ Other - - - 42,006.437 - - -
sources sources
BARANGAY DEVELOPMENT PROGRAM MGOP/ Other 2020 2022*** - MGOP - - - 66,600.000 - - -
Sources
WASTE MANAGEMENT PROGRAM
8000-3-02-004-1 Construction of Zero Waste Facility MEO, MENRO 2020 2022 Building constructed, zero waste MGOP 30,000.000 30,000.000 30,000.000 M324-02
machines purchased (DRRMF) /
Other sources
8000-3-01-010-a- Concreting of Roads within Sanitary Land Fill MEO, MENRO 2021 2021 150 linear meters of road constructed MGOP/ Other 3,600.000 3,600.000
1 sources
8000-3-02-004-2 Construction of Treatment Facility for MENRO, MEO 2020 2021 Biulding/storage facility intended to MGOP/ Other 2,500.000 2,500.000
Hazardous and Toxic Wastes separate hazardous and toxic waste sources
8000-3-02-004-3 Construction of Facility within Sanitary MENRO, MEO 2020 2020 Building constructed, waste treatment MGOP/ Other 1,800.000 1,800.000
Landfill for Toxic Wastes machinery purchased sources
8000-3-02-004-4 Establishment of recycling facility MENRO, MEO 2021 2021 Building and seggregating structures MGOP/ Other 3,500.000 3,500.000 3,500.000 M324-02
constructed sources
8000-3-02-004-5 Construction of Guard house within Sanitary MENRO, MEO 2020 2020 Guard House constructed at the entrance MGOP/ Other 1,500.000 1,500.000
Landfill Site of the Sanitary Landfill sources
8000-3-02-004-6 Purchase of high-end garbage separator MENRO 2020 2021 1 unit Garbage Separator - Compactor MGOP/ Other 6,500.000 6,500.000
trucks Truck purchased sources
LIVELIHOOD PROGRAM
3000-3-02-005-1 Livelihood Program for Disadvantaged MSWDO, ALS 2020 2020 Community-Based Skills Training MGOP/ Other 3,000.000 3,000.000
Sectors conducted to beneficiaries sources
12 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-003- Fishery Livelihood Program MAgO 2019 2022*** Fish Aggregating devices purchased; MGOP/ BFAR 20,000.000 20,000.000 20,000.000 A113-08
1* (Fish Aggregating Devices, Aquasilvi Culture, fishing boats with complete set of gill net
Fishing Boats with complete set of gill net (motorized & non-motorized & hook &
(motorized & non-motorized, hook and line); line) provided; Tilapia and Bangus fry
Fish processing) dispersed; and Aquasilvi farm developed
8000-3-02-003- Barangay Livelihood MAgO 2019 2022*** Processing center constructed; MGOP/BFAR 37,000.000 37,000.000
2* processing equipment procured; and
conducted livelihood trainings for abaca
expansion, crop production, animal
raising, and fish production
8000-3-02-003-3 Provision of Alternative Livelihood Activities MAgO, MENRO, 2020 2022** Livelihood activities identified; MGOP/ Other 2,000.000 2,000.000
from recycled materials SCO networking/tie-up with NGOS, NGAs, or sources
foundations establsihed; capacity building
conducted; and finished products
marketed
8000-3-03-003-a- Redevelopment/modernization of the Private Sector 2019 2022** 1.6 ha. multi-storey building constructed PPP 105,000.000 105,000.000
1-1* declared Public Economic Enterprise (Public
Market)
3000-200-3-03- Establishment of Supermall (2-storey MHO 2021 2022 Two storey twin commercial building MGOP/ other 220,000.000 220,000.000
001-1* commercial building) construced sources
PINAMALAYAN PUBLIC MEMORIAL PARK
8000-3-01-010-a- Establishment of New Pinamalayan Public MAssO, MENRO, 2020 2021 5 hectares memorial park developed MGOP/ Other 5,500.000 5,500.000
2 Memorial Park MEO sources
1000-3-01-006-1 Land banking for public cemetery (5ha) MAssO 2020 2022** 5 hectares of land purchased for the MGOP/ Other 10,000.000 10,000.000
construction of a new public cemetery Sources
13 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-004- Construction of Comprehensive Sewerage MENRO, MEO 2020 2022** Comprehensive Sewerage System MGOP/ other 20,000.000 20,000.000 20,000.000 A214-04
7* System at Poblacion Area constructed within the Poblacion, master sources
Septic Tank constructed
8000-3-02-004-8 Construction of Centralized Wastewater MENRO, MEO 2020 2021 Building constructed, waste water MGOP/ Other 6,500.000 6,500.000 6,500.000 A214-04
Treatment at Poblacion Area treatment machines purchased sources
8000-3-02-004-9 Rehabilitation of flood control dikes, irrigation MDRRMO, NIA 2022 2022 Flood Control Dikes, Irrgiation Canals and MGOP/ other 5,000.000 5,000.000 5,000.000 A224-02
canals and drainages Drainages constructed sources
8000-3-01-010-a- Comprehensive Drainage Program MEO 2020 2022** Drainage plan formulated; existing MGOP/PGOrM/ 322,000.000 322,000.000 322,000.000 A224-01
3* drainage canals rehabilitated and DPWH/ Other
desilted; sources
natural ways desilted
8000-3-02-003- Concreting of Communal Canal MAgO 2020 2022** Communal canals at barangays Calingag, NIA 10,000.000 10,000.000 10,000.000 A114-05
3* Sta. Isabel, Malaya, Maliancog, Pambisan
Malaki, Papandayan, Cacawan, Buli, Del
Razon & Pambisan Munti concreted
8000-3-01-010-a- Desilting of Drainage Canals within Poblacion MEO 2021 2021 Drainage canal in poblacion area MGOP/PGOrM/ 700.000 700.000
4 declogged and desilted DPWH/ Other
sources
8000-3-01-010-a- Upgrading of Drainage Canals MEO 2021 2022 Drainage Canal in front of Municipal MGOP/PGOrM/ 1,100.000 1,100.000 1,100.000 A224-01
5 Compound along Madrid Blvd upgraded DPWH/ Other
sources
8000-3-01-010-a- Construction of Comprehensive Sewerage MENRO, MEO 2022 2022** Endpoint Master Septic Tank constructed MGOP/Other 20,000.000 20,000.000 20,000.000 A232-01
6* System Sources
8000-3-02-004- Conduct of a Comprehensive Topographic Zoning Division 2020 2022*** Comprehensive Topographic Survey MGOP/ Other 60,000.000 60,000.000 60,000.000 A631-01
10* Survey conducted in the Poblacion area sources
14 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-004- Construction of Riverbank Protection Dike in MDRRMO, DPWH 2021 2022 River Protection Dike in all barangays MGOP/ Other 150,000.000 150,000.000 *
11 all barangays along Pula River along Pula River constructed sources
8000-3-01-010-a- Desilting of Upstream of Inclanay Dam MEO 2022 2022*** Inclanay river banks desilted MGOP/PGOrM/ 50,000.000 50,000.000 50,000.000 A114-05
7* DPWH/ Other
sources
8000-3-02-004- River Protection Program MDRRMO, 2020 2022** River Protection Program created MGOP/ other 50,000.000 50,000.000 50,000.000 M314-07
12* MENRO, DENR sources
8000-3-01-010-a- Desilting of Natural Waterways MENRO, MEO 2020 2021 Obstructions on the natural flow of waters MGOP/Other 5,500.000 5,500.000 5,500.000 M634-02
8 and all structures along banks of rivers Sources
and creeks illegally constructed removed
8000-3-01-010-a- Construction of Breakwater MEO/PEO/DPWH 2022 2022*** Breakwater constructed MGOP/PGOrM/ 180,000.000 180,000.000 180,000.000 A224-02
9* DPWH/ Other
sources
HOUSING PROGRAM
3000-3-02-005- Core Shelter Assistance Program MSWDO, MEO 2022 2022*** 150 Core Housing Units constructed; MGOP/ other 52,500.000 52,500.000 52,500.000 A424-06
2* basic amenities installed (water, sources
electricity); roadways and drainage canal
constructed
8000-3-02-004- Relocation of Informal Settlers in Coastal MDRRMO, DENR 2020 2022 All Informal Settlers along coastal areas MGOP/ other 10,000.000 10,000.000 10,000.000 A424-13
13 Areas relocated to safer places sources
8000-3-01-010-a- Construction of Seawall MEO/PEO/DPWH 2022 2022 3,080 meters of seawall cosntructed MGOP/PGOrM/ 200,000.000 200,000.000 200,000.000 A634-01
10 DPWH/ Other
sources
8000-3-03-003-a- Establishment of Supermall (2-storey MOD, MEO 2021 2022 Two storey twin commercial building MGOP/ Other 220,000.000 220,000.000
1-2 commercial building) construced sources
15 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-200-3-03- Health Card for Pinamalayan Residents MO, MHO 2020 2022*** Medicard provided from authorized MGOP/DOH 200,000.000 200,000.000 200,000.000 A414-06
001-1* companies with 100% coverage in 2028
3000-100-3-03- Establishment of Public Tertiary MGOP/PGOrM/Dep 2019 2022*** Lot acquired; school buildings MGOP/DepED/ 90,000.000 90,000.000
001-1-1* Institution/School Ed constructed; equipment, DPWH
furnitures and fixtures purchased;
manpower hired; and vehicle purchased
8000-3-01-010-a- Upgrading of Municipal Power Supply MEO/PEO/NEA 2019 2022 1 Unit 500 KVA Generator Set purhcased; MGOP/PGOrM/ 50,000.000 50,000.000
11* System offices rewired; feeder lines for existing NEA/ Other
buildings installed; and powerhouse Sources
constructed
1000-3-03-001-2- Repair and Improvement of all Office MEO 2020 2022 Buildings repainted ; windows and doors MGOP/PGOrM/ 10,000.000 10,000.000
17-1 Buildings and facilities repaired; roofing replaced; DepEd/ Other
(MTC included and other offices) and electrical works such as rewiring Sources
conducted
8000-3-01-010-a- Improvement of Municipal Engineering MEO 2021 2021 Cubicles and cabinets constructed; ceiling MGOP/Other 1,500.000 1,500.000
12 Office installed; flooring repaired; and door grills Sources
installed
1000-3-01-001-a- Construction of Stockroom for Accounts, MEO, GSD 2021 2022 500 sq.m. stockroom for account, reports MGOP/ Other 115,000.000 115,000.000
1* Reports and Records and records of government offices Sources
constructed
1000-3-01-001-a- Construction of Warehouse for PPEs and GSD, MEO 2021 2022 1,000 sq.m. warehouse constructed MGOP/Other 15,000.000 15,000.000
2 construction materials Sources
16 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-01-005-1 Repair and Improvement of Taxpayers' MTO, MEO 2020 2021 Eight teller booth installed; gender MGOP/Other 910.000 910.000
Lounge sensitive comfort rooms construted; Sources
desktop computers, gang chairs, water
dispenser, TV set, air conditioning unit
provided
8000-3-01-010-a- Construction of Convention Center MEO/PEO 2022 2022 2500 sq.m. lot acquired; 2,000 sq.m. MGOP/PGOrM/ 50,000.000 50,000.000
13 building constructed; 500 sq.m parking Other Sources
constructed; landscaping
8000-3-01-010-a- Construction of Access Roads leading to MEO/PEO/DOT 2019 2022*** 20 access roads constructed MGOP/PGOrM/ 50,000.000 50,000.000
14* Tourisms Sites DOT
CENTRALIZED GRAND TERMINAL
8000-3-01-010-a- Construction of Grand Terminal MEO/Private Sector 2019 2022 Perimeter fence, road networks, drainage MGOP/PGOrM/ 606,000.000 606,000.000
15 canal, administrative building, waiting Other Sources
areas, pasalubong center, and eatery
constructed
8000-3-01-010-a- Coastal Greenway MEO/PEO/DPWH 2022 2022*** 7.5 km coastal greenway constructed MGOP/PGOrM/ 150,000.000 150,000.000
16* DPWH/ Other
sources
8000-3-02-004- Rehabilitation of Babahurin Watershed Area MENRO, CENRO, 2020 2020 Tree seedlings planted along denuded MGOP/ other 2,000.000 2,000.000 2,000.000 A314-09
14 NGOs area of Babahurin River sources
8000-3-02-004- Babahurin and Pula Watershed MENRO, LGU 2020 2020 200 hectares of Pula Watershed MGOP/ other 1,550.000 1,550.000 1,550.000 M314-01
15 Rehabilitation rehabilitated, sources
__ hectares of Babahurin Watershed
rehabilitated
17 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Construction of Lumambayan bridges I, II, III, MEO/PEO/DPWH 2020 2022*** Lumambayan Bridge I (L=30m, W=6m); MGOP/PGOrM/ 190,000.000 190,000.000 190,000.000 A224-02
17* Sta. Isabel Bridge II ( 60m , W=6m); Bridge III ( DPWH/ Other
L=30m, W=6m); and sources
Sta.Isabel Bridge ( L=10m, W=3.6m)
constructed
8000-3-02-003- Crop Development Program MAgO, DA, MEO, 2019 2022*** Facility constructed; mechanical dryer DA/PhilFIDA 41,000.000 41,000.000 41,000.000 A114-03
4* (Construction/Installation of mechanical PhilFIDA purchased and installed; vegetables
dryer; Vegetable Production; Construction of seeds and organic fertilizers purchased;
Small Water Impounding Facility; Abaca trained beneficiaries; small water
Production) impounding facility constructed; abaca
planting materials and abaca fiber
extraction machines and equipment
purchased
1000-3-01-009- Updating of Community-Based MPDO, 2022 2022*** CBMS Database updated; CBMS-Based MGOP/PGOrM 10,000.000 10,000.000
1* Disaggregated Data CBMS-TWG Municipal and Barangay Profile and
Development Plan updated
8000-3-01-010-a- Rehabilitation of Roads MEO/PEO/DPWH 2019 2022*** 34.59 km of roads rehabilitated MGOP/PGOrM/ 126,000.000 126,000.000 126,000.000 A634-04
18* DPWH/ Other
sources
3000-200-3-03- Construction of Social Hygiene Clinic MHO 2019 2020 Social Hygiene clinic constructed; PhilHealth/DOH 500.000 500.000
001-2 equipment purchased; manpower hired
and trained
1000-3-03-001-2- Fire Safety and Security System in the BFP/MEO 2019 2020 60 units HCFC Type Fire Extinguisher (10 MDRRMF 1,000.000 1,000.000
13-1 Municipal Compound lbs.), 30 units Exit Signs, 4 units Fire Exit
Ladder with landing, 24 units Fire alarm
bell (battery operated),
1 unit Manual Pull Station, and 12 units
smoke detector installed
18 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Concreting of Barangay Roads MEO/PEO/DPWH 2019 2022*** 41.49 km concreted barangay roads MGOP/PGOrM/ 105,000.000 105,000.000 105,000.000 A634-04
19* DPWH/ Other
sources
3000-3-02-005-3 Conversion of Convention Center into Crisis MEO/PEO/DPWH 2019 2020 Building rehabilitated; equipment MGOP/Other 6,000.000 6,000.000
Center purchased Sources
8000-3-01-010-a- Rehabilitation of Public School Buildings and MEO/PEO/DPWH/D 2022 2022*** Public school buildings and facilities MGOP/PGOrM/ 60,000.000 60,000.000 60,000.000 A424-12
20* Facilities epEd rehabilitated including roofing, repainting, DPWH/ DepED/
rehabilitation of existing structures, Other sources
buildings, and facilities
8000-3-03-003-a- Upgrading of the Slaughterhouse Building SOD, MEO, MAssO 2022 2022*** Municipal Slaughterhouse to"Double A" MGOP/PGOrM/ 5,278.500 5,278.500
2-1* and Facilities Category accreditated ; Backyard Other Sources
pavement concreted; Perimeter concrete
fence constructed; Waiting Area with
comfort rooms outside the
Slaughterhouse building constructed;
Septic Tank (Biodegradable and Non-
biodegradable) constructed; Roofing of
Animals Holding/Dispatching Area
(Auxiliary Part of the Main Building)
installed; Stainless inspection table
fabricated; and acquired leg spreader,
beef shackle, carwash machine, booster
blower, grass cutter, weighing cale,
pressurized motor pump, dehairing
machine, and refrigerated delivery van
3000-200-3-03- Provision of Anti-Rabies Vaccine MHO 2021 2021 MGOP/Other 1,000.000 1,000.000
001-3 Sources
19 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Opening of Proposed Roads MEO/PEO/DPWH 2022 2022*** 6 kilometers of roads opened MGOP/PGOrM/ 70,000.000 70,000.000
21* DPWH/ Other
sources
3000-3-03-001-3- Establishment of Modern Sports Complex MEO/PEO 2022 2022*** Lot purchased; track and field oval MGOP/PGOrM/ 200,000.000 200,000.000
1* developed; DPWH/ Other
grandstand, swimming pool, dormitory, sources
and covered court constructed
8000-3-01-010-a- Improvement of Marfrancisco Triangle MEO/PEO/DPWH 2021 2021 Tiles set; pathway with curb concreted; MGOP/PGOrM/ 1,000.000 1,000.000
22 stairs railing constructed; concrete logo DPWH/ Other
installed; lighting added; landscaping and sources
repainting of the triangle
1000-3-01-006- Acquisition of Lots for Future Expansion of MAssO 2021 2022*** 50 hectares of land acquired MGOP/Other 50,000.000 50,000.000
2* Urban Development Sources
8000-3-02-003- Farm Mechanization Program MAgO, DA 2019 2022*** Hand Tractor with Trailer acquired; DA 18,300.000 18,300.000
6* Shallow Tube Well installed; Rice
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
1000-3-01-006-3 Land Banking for social services such as MAssO, MENRO, 2022 2022*** 25 hectares of lot acquired MGOP/Other 25,000.000 25,000.000
MSWDO compound, PRTO and other CSOs, MSWDO Sources
Police outposts, BFP lot (25 ha)
20 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-03-001-2- Modernizing of Firefighting Tools, Apparatus, MO/MDRRMO/BFP 2019 2022*** Protective gears, fire axe, chainsaw, MGOP/Other 800.000 800.000
13-2* and Equipment hydraulic spreader, rescue ropes with Sources
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2- Installation of Additional Fire Hydrants BFP, 2019 2022*** Fire hydrants installed MDRRMF 1,000.000 1,000.000
13-3* MEO/MDRRMO
1000-3-03-001-2- Upgrading of BFP Building and Facilities BFP 2019 2022*** Office, personnel quarters, gate and BFP 600.000 600.000
13-4* fence repainted; and stockroom
upgraded
8000-3-01-010-a- Construction and Furnishing of Tricycle for MDRRMO, MEO, 2021 2022 Public comfort room constructed; 28 pcs. MGOP/Other 5,000.000 5,000.000
23 Hire Terminal PNP, PLD gang seaters procured; public address Sources
system and CCTV installed; and Public
Assistance Complaints Desk (PACD)
provided
8000-3-02-003-7 Construction of Building (Office/Function Hall MAgO, DA 2019 2021 Building for Farmers’ Federation Office, DA 10,000.000 10,000.000
and Garage for farm equipment) Function Hall, and Garage for farm
Equipment constructed
3000-3-02-005-2- Construction of Additional Barangay Senior MEO 2019 2022*** 10 Senior Citizens Affairs Centers MGOP/Other 5,500.000 5,500.000
4-1 Citizens Affairs Centers constructed Sources
8000-3-01-010-a- Installation or Fabrication of Streetlights MEO 2022 2022 348 units LED streetlights installed 15,000.000 15,000.000
24
1000-3-01-002-1 Establishment of municipal eLibrary VMO, SB 2021 2020 Study Tour conucted; hardware & MGOP/Other 1,040.000 1,040.000
software procured; system and internet Sources
installed; orientation & briefing conducted
21 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
OTHERS
8000-3-01-010-a- Improvement of Marfrancisco Triangle MEO 2019 2020 Tiles set; pathway with curb concreted; MGOP/PGOrM/ 1,000.000 1,000.000
32 stairs railing constructed; concrete logo Other sources
installed; lighting added; landscaping and
repainting of the triangle
1000-3-01-006-3 Acquisition of Lots for Future Expansion MAssO 2021 2022*** 50 ha of land acquired MGOP/ Other 50,000.000 50,000.000
sources
8000-3-02-003-9 Farm Mechanization Program MAgO, DA 2019 2022*** Hand Tractor with Trailer acquired; MGOP/DA/ 18,300.000 18,300.000
Shallow Tube Well installed; Rice Other Sources
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
1000-3-01-006-7 Land Banking for social services such as MAssO, MENRO, 2019 2022*** 25 hectares of lot acquired MGOP/ Other 25,000.000 25,000.000
MSWDO compound, MSWDO sources
PRTO and other CSOs, Police outposts,
BFP lot (25 ha)
1000-3-03-001-2- Modernizing of Firefighting Tools, Apparatus, MO 2019 2022*** Protective gears, fire axe, chainsaw, MGOP/ Other 800.000 800.000
13-2 and Equipment hydraulic spreader, rescue ropes with sources
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2- Installation of Additional Fire Hydrants BFP, MEO 2019 2022*** fire hydrants installed MGOP/BFP 1,000.000 1,000.000
13-3
1000-3-03-001-2- Upgrading of BFP Building and Facilities BFP 2019 2022*** Office, personnel quarters, gate and MGOP/BFP 600.000 600.000
13-4 fence repainted; and stockroom
upgraded
22 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Construction and Furnishing of Tricycle for MDRRMO, MEO, 2019 2019 Public comfort room constructed; 28 pcs. MGOP/ Other 5,000.000 5,000.000
40 Hire Terminal PNP, PLD gang seaters procured; public address sources
system and CCTV installed; and Public
Assistance Complaints Desk (PACD)
provided
8000--3-02-003- Construction of Building (Office/Function Hall MAgO, DA 2019 2021 Building for Farmers’ Federation Office, MGOP/DA/ 10,000.000 10,000.000
10 and Garage for farm equipment) Function Hall, and Garage for farm Other Sources
Equipment constructed
3000-3-02-005-2- Construction of Additional Barangay Senior MEO 2019 2022*** 10 Senior Citizens Affairs Centers MGOP/ Other 5,500.000 5,500.000
4-1 Citizens Affairs Centers constructed sources
8000-3-01-010-a- Installation or Fabrication of Streetlights MEO 2022 2022 348 units LED streetlights installed MGOP/ Other 15,000.000 15,000.000
33 sources
1000-3-01-002-1 Establishment of municipal eLibrary VMO, SB 2019 2020 Study Tour conucted; hardware & MGOP/ Other 1,040.000 1,040.000
software procured; system and internet sources
installed; orientation & briefing conducted
8000-3-01-010-a- Installation of Road Signs (Warning Signs, MEO, DPWH 2019 2022*** 50 pcs warning Signs and 50 pcs MGOP/ Other 1,330.000 1,330.000
26 Regulatory Signs) regulatory signs installed sources
8000-3-01-010-a- Construction of dropped curb at pedestrian MEO 2022 2022 Additional ramp for PWD constructed; MGOP/PGOrM/ 600.000 600.000
27 crossing and at the end of walkways of pedestrian lane provided; island fo the Other sources
access roads pedestrian lane removed; and signage for
pedestrian lane and PWDE provided
8000-3-01-010-a- Pedestrian Crossings MEO, DPWH 2019 2022*** 40 pcs pedestrian crossings provided MGOP/DPWH/ 864.000 864.000 864.000 M631-04
28 Other Sources
8000-3-01-010-a- Rehabilitation of Road Shoulder MEO 2022 2022 Obstruction encroachment removed; and MGOP/PGOrM/ 500.000 500.000 500.000 A634-06
31 gravel shoulder resurfaced; road shoulder Other sources
rehabilitated
23 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-01-006-7 Construction of Pinamalayan Retired MEO 2019 2020 100 sqm one-story building constructed MGOP/ Other 1,500.000 1,500.000
Teachers Organization (PRTO) Building sources
3000-3-02-005- Construction of Local Council for Women MEO, LCW 2020 2021 24m x 40m multi-purpose hall constructed MGOP/ Other 17,280.000 17,280.000
11 Office with Multi-Purpose Hall sources
3000-200-3-03- Acquisition of Ambulances VMO, SB 2020 2022*** Additional unit of ambulance acquired MGOP/ DOH/ 4,000.000 4,000.000
001-7 Other sources
8000-3-03-003-a- Establishment of Trading Facility or Local MEO 2022 2022*** 2,306.45 sqm. Local Exchange Trading MGOP/ Other 15,000.000 15,000.000
1-5 Exchange Trading Terminal (LETT) Terminal constructed sources
3000-3-02-005-9 Establishment of Persons with Disability MAssO 2019 2022*** PDA officer hired; IDs & Booklets MGOP/ Other 4,000.000 4,000.000
Affairs Office (PDAO) procured; Orientation on Magna Carta for sources
PWDs (Benefits and Privileges of PWD)
conducted; Business Forum on the Rights
of Persons with Disabilities conducted;
Livelihood Assistance (Salted Egg
Production) provided; PWD of Sta. Rita
organized; Medical Mission and other
activities conducted
1000-3-01-009-1 Computerization Program/Information and MO 2020 2022*** ICT Office with permanent positions MGOP/ Other 15,000.000 15,000.000
Communications Technology (ICT-CeC) established; ICT Administration Building sources
Project constructed furnished with needed IT
equipment, office equipment, furniture
and fixtures, transportation vehicles, etc.;
Agency Information Kiosk developed;
Centralized Local Area Network and
Information System established; and e-
Billboard installed and functional
24 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Improvement of manpower development MEO 2022 2022 Stage upgraded, lightings installed, and MGOP/PGOrM/ 500.000 500.000
2 center building repainted Other sources
8000-3-02-004- Establishment of Tree Nursery MAgO, DA 2019 2020 Tree Nursery established at AC/BS Sto. MGOP/ other 3,000.000 3,000.000 3,000.000 M314-04
24 Niño sources
8000-3-02-004- Establishment of Wildlife Facility or Sanctuary MENRO, CENRO 2020 2021 Wildlife Rescue Facility constructed, MGOP/ other 2,300.000 2,300.000 2,300.000 M314-02
19 Hiring of Technical Personnel and sources
Caretaker
3000-3-02-005- Acquisition of MSWDO Service Vehicle MSWDO 2020 2020 Service vehicle acquired GF 1,500.000 1,500.000
10
8000-3-02-004- Rehabilitation of Existing Public Cemetery MENRO, MEO, 2019 2020 Crematorium/Columbarium constructed at MGOP/ other 15,000.000 15,000.000
23 MAssO Barangay Papandayan sources
8000-3-01-010-a- Upgrading of Existing Roads MEO 2022 2022*** MGOP/PGOrM/ 358,380.000 358,380.000 358,380.000 A634-04
29 Other sources
3000-3-03-001-4- Construction of ALS Learning Center in MGOP, TESDA 2019 2022 Building constructed; equipment acquired; MGOP/ TESDA/ 3,000.000 3,000.000
1 Pinamalayan and trainors hired other sources
3000-3-03-001-4- Construction of TESDA Accredited Training MGOP, TESDA 2019 2020 Building constructed; equipment acquired; MGOP/ TESDA/ 4,000.000 4,000.000
2 Center and trainors hired other sources
8000-3-01-010-a- Electrification program ORMECO 2019 2022*** 197 poles installed MGOP/NEA/ 10,835.000 10,835.000
34 other sources
3000-200-3-03- Rehabilitation of West District Health Center MHO, MEO 2019 2022 Existing facility rehabilitated; health staff MGOP/ DOH/ 1,000.000 1,000.000
001-8 trained Other sources
8000-3-01-010-a- Construction of Multi-purpose hall/covered MEO 2019 2022*** 33 multi-purpose hall buildings MGOP/ other 82,500.000 82,500.000
30 court in every barangay (33 barangays) constructed soources
25 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-200-3-03- Establishment of Smoking Cessation Clinic MHO 2019 2019 Smoking Cessation Clinic provided; MGOP/ other 100.000 100.000
001-9 counselors trained; logistics and supplies soources
provided
8000-3-01-010-a- Formulation of Comprehensive Road Network MEO 2022 2022*** Topographic survey conducted; surveying MGOP/PGOrM/ 15,000.000 15,000.000
35 Plan instrument acquired Other sources
1000-3-03-001-2- Construction of 8 Mobile Police Outpost in MEO, PNP 2019 2022*** 8 mobile police outputs constructed MGOP/PNP/oth 4,000.000 4,000.000
12-1 Strategic Locations er sources
3000-100-3-03- Establishment of SPED Center in MASMES DepEd 2019 2020 SPED Center constructed; trainings and MGOP/ other 1,400.000 1,400.000
001-b-2-1 seminars of qualified SPED teacher soources
conducted; uniforms/shoes/bags/supplies
and teaching materials and equipments
provided
3000-100-3-03- E-Eskwela MGOP, ALS 2019 2022*** Customized Instruction Models provided; MGOP/ other 1,000.000 1,000.000
001-1-3 trainors equipped; stakeholders training soources
conducted
8000-3-01-010-a- Purchase of appropriate heavy equipment MEO 2019 2022 4 units 6 wheeler dumptruck, 1 Pay MGOP/ other 40,000.000 40,000.000
37 Loader, and 1 Road Grader aggregates soources
purchased
3000-100-3-03- Upgrading of Existing SPED Center DepEd 2019 2022 Existing SPED Center upgraded; MGOP/DepEd/ 2,000.000 2,000.000
001-b-1-1 equipment acquired; qualified SPED other sources
teacher hired and trained;
uniforms/shoes/bags/supplies and
teaching materials provided
3000-100-3-03- Project SAFE (Secure, Accommodating, MEO, DepED 2019 2022*** 33 elementary schools, 12 secondary MGOP/DepEd/ 23,173.000 23,173.000 23,173.000 A424-11
001-a-1 Friendly Environment) schools, and 2 district offices other sources
rehabilitated; school facilities constructed;
furnitures and foxtures acquired
26 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Rehabilitation/upgrading of existing port MEO 2022 2022*** Port facilities rehabilitated MGOP/PGOrM/ 200,000.000 200,000.000
36 facilities Other sources
8000-3-01-010-a- Rehabilitation or upgrading of existing NIA MEO 2022 2022*** NIA roads rehabilitated MGOP/PGOrM/ 160,000.000 160,000.000 160,000.000 A634-04
38 Roads Other sources
1000-3-03-001-2- Acquisition of 1 unit Mobile Patrol Vehicle PNP 2020 2020 Mobile patrol vehicle acquired MGOP/PNP/oth 2,000.000 2,000.000
12-2 er sources
8000-3-01-010-a- Expansion of airport MEO 2022 2022*** Elevated runway; embankment; pavement MGOP/PGOrM/ 135,000.000 135,000.000 135,000.000 A634-04
39 concreted; lightings installed; building DOTR/ DPWH/
constructed; station of building upgraded Other sources
3000-200-3-03- Acquisition of MHO Service Vehicle MHO 2020 2020 1 service vehicle acquired MGOP/ other 1,500.000 1,500.000
001-10 soources
3000-100-3-03- Project HEART (Provision of Multimedia MO, DepEd 2019 2022*** LED TV, projectors, laptop, desktop MGOP/DepEd/ 8,000.000 8,000.000
001-a-2 Instructional Materials) computer acquired; WIFI Connection other sources
installed; SHS reference books and other
reading materials provided; training and
seminars conducted
8000-3-03-003-b- Installation of Public Address System within MEO 2022 2022*** Public address equipment procured and MGOP/PGOrM/ 40,000.000 40,000.000
3-1 Poblacion Area installed Other sources
27 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-03-001-2- Upgrading of PNP Building and Facilities MEO, PNP 2019 2022 Conference room constructed with fixed MGOP/ other 2,500.000 2,500.000
12-3 table and chair that can accommodate up soources
to 70 persons; whiteboard, projector
screen, conference microphone system,
audio conference system, and video
conference system purchased and
installed; conference room wall, window,
and door glass constructed; and air
conditioning system conference room
installed
8000-3-01-010-a- Construction of Overpass in ABADA College MEO 2022 2022*** Overpass constructed MGOP/PGOrM/ 1,500.000 1,500.000
14* and Nabuslot National High School DPWH/ Other
sources
Coding:
*** (three red asterisk on completion date) - project will continue for the 2nd and third terms
** (two red asterisk on completion date) - project will continue for 2nd term only
* (one red asterisk on start date) - project already started on the previous term
Prepared by: Attested by: Certified correct and approved by the LDC:
EnP ROSENIO A. TORIANO ZAIDA D. MICIANO PLARIDEL S. CUPIADO ARISTEO APASAN BALDOS, JR.
Municipal Planning and Development Coordinator Local Budget Officer Local Treasurer Municipal/LDC Chairman
28 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-004- Construction of Cluster Sanitary Landfill MENRO, MEO 2023 2025 Sanitary landfill complete with the MGOP/ other 30,000.000 30,000.000
16 required amenities sources
LIVELIHOOD PROGRAM
8000-3-02-003- Fishery Livelihood Program (Fish MAgO/BFAR 2023* 2025* Fish Aggregating devices purchased; MGOP/ 20,000.000 20,000.000 20,000.000 A113-08
1** Aggregating Devices, Aquasilvi Culture, fishing boats with complete set of gill net PGOrM/ BFAR
Fishing Boats with complete set of gill net (motorized & non-motorized & hook &
(motorized & non-motorized, hook and line); line) provided; Tilapia and Bangus fry
Fish processing) dispersed; and Aquasilvi farm developed
8000-3-02-003- Barangay Livelihood MAgO/BFAR 2023* 2025* Processing center constructed; MGOP/ 37,000.000 37,000.000
2** processing equipment procured; and PGOrM/ BFAR
conducted livelihood trainings for abaca
expansion, crop production, animal
raising, and fish production
8000-3-02-004- Livelihood Projects for Indigenous People of MAgO, DA 2023 2025* Trading of Agricultural Products, Draft MGOP/ Other 33,000.000 33,000.000
17* Pinamalayan Animals dispersal, Abaca Expansion sources
Project, trainings attended/conducted
8000-3-02-004- Provision of Alternative Livelihood Activities MAgO, MENRO, 2023* 2023 Livelihood activities identified; MGOP/ Other 2,000.000 2,000.000
18 from Recycled Materials SCO networking/tie-up with NGOS, OGAs, or sources
foundations establsihed; capacity building
conducted; and finished products
marketed
8000-3-03-003-a- Redevelopment/Modernization of the Private Sector 2023* 2025 1.6 ha. multi-storey building constructed PPP 105,000.000 105,000.000
1-1** Declared Public Economic Enterprise
(Public Market)
29 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Establishment of Trading Facility or Local MEO 2023* 2025* 2,306.45 sqm. Local Exchange Trading MGOP/Other 15,000.000 15,000.000
Exchange Trading Terminal (LETT) Terminal constructed sources
Installation of Public Address System within MEO 2023* 2025* Public address equipment procured and MGOP/ other 40,000.000 40,000.000
Poblacion Area installed sources
NEW GOVERNMENT CENTER
1000-3-01-006- Land banking for government offices (10 ha) MAssO 2023 2025* 10 hectares of land purchased MGOP/ Other 20,000.000 20,000.000
4* Sources
PINAMALAYAN PUBLIC MEMORIAL PARK
1000-3-01-006- Land banking for public cemetery (5ha) MAssO 2023* 2025 5 hectares of land purchased for the MGOP/ Other 10,000.000 10,000.000
1** construction of a new public cemetery Sources
REHABILITATION, PROTECTION, AND IMPROVEMENT OF
WATERWAYS
8000-3-02-004- Construction of Comprehensive Sewerage MENRO, MEO 2023* 2024 Comprehensive Sewerage System MGOP/ 20,000.000 20,000.000 20,000.000 A214-04
7** System at Poblacion Area constructed within the Poblacion, master PGOrM/ DPWH/
Septic Tank constructed Other sources
8000-3-01-010-a- Rehabilitation of irrigation canals in MEO/PEO/NIA 2024 2024 Comprehensive Drainage Plan MGOP/ 5,000.000 5,000.000 5,000.000 A114-05
25 Pinamalayan PGOrM/ NIA/
Other sources
8000-3-01-010-a- Comprehensive Drainage Program MEO/PEO/DPWH 2023* 2025* Drainage plan formulated; existing MGOP/ 322,000.000 322,000.000 322,000.000 A224-01
3** drainage canals rehabilitated and PGOrM/ DPWH/
desilted; natural ways desilted Other sources
8000-3-01-010-a- Construction of Drainage Canal with Curb, MEO/PEO/DPWH 2024 2024 200.5 linear meters of drainage canal with MGOP/ 3,000.000 3,000.000
26 Gutter and Box Culvert curb, gutter, and box culvert constructed PGOrM/ DPWH/
Other sources
30 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-003- Concreting of Communal Canal MAgO/DA 2020 2024 Communal canals at barangays Calingag, NIA 10,000.000 10,000.000 10,000.000 A114-05
4** Sta. Isabel, Malaya, Maliancog, Pambisan
Malaki, Papandayan, Cacawan, Buli, Del
Razon & Pambisan Munti concreted
8000-3-01-010-a- Construction of Comprehensive Sewerage MENRO, MEO 2023* 2025 Endpoint Master Septic Tank constructed MGOP/ 20,000.000 20,000.000 20,000.000 A232-01
6** System PGOrM/ DPWH/
Other sources
8000-3-02-004- Conduct of a Comprehensive Topographic Zoning Division 2023* 2025* Comprehensive Topographic Survey MGOP/ 60,000.000 60,000.000 60,000.000 A631-01
10** Survey conducted in the Poblacion area PGOrM/ DPWH/
Other sources
8000-3-01-010-a- Desilting of upstream of Inclanay Dam NIA 2023* 2025* Inclanay river banks desilted NIA 50,000.000 50,000.000 50,000.000 A114-05
7**
8000-3-02-004- River Protection Program MDRRMO, MENRO, 2023* 2024 River Protection Program created MGOP/ 50,000.000 50,000.000 50,000.000 M314-07
12** DENR PGOrM/ NIA/
DPWH/ Other
sources
8000-3-01-010-a- Construction of breakwater MEO/PEO/DPWH 2023* 2025* Breakwater constructed MGOP/ 180,000.000 180,000.000 180,000.000 A224-02
9** PGOrM/ DPWH/
Other sources
HOUSING PROGRAM
3000-3-02-005- Core Shelter Assistance Program MSWDO, MEO 2023* 2025* 150 Core Housing Units constructed; MGOP/ 52,500.000 52,500.000 52,500.000 A424-06
2** basic amenities installed (water, PGOrM/ Other
electricity); roadways and drainage canal sources
constructed
31 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-3-02-005- Socialized Housing Project MSWDO, MEO 2025* 2025* 5 ha lot developed; 200 housing units MGOP/PGOrM/ 100,000.000 100,000.000 100,000.000 A424-06
3* constructed DSWD
3000-3-02-005- Employees’ Housing Program MSWDO, MEO 2024 2025* 5 hectares of Land acquired, 100 MGOP/ other 50,000.000 50,000.000
4* Socialized Housing Units constructed sources
1000-3-01-006-5 Land Banking for Employees’ Housing MAssO 2023 2024 5 hectares of land purchased for the MGOP/ Other 10,000.000 10,000.000
Program construction of Employee's Housing Sources
8000-3-03-003-a- Commercial Building MOD, MEO 2025* 2025* Two storey twin commercial building MGOP/ other 105,000.000 105,000.000
1-3* construced sources
3000-200-3-03- Health Card for Pinamalayan Residents MO, MHO 2023* 2025* Medicard provided from authorized MGOP/ DOH/ 200,000.000 200,000.000 200,000.000 A414-06
001-1** companies with 100% coverage in 2028 Other Sources
3000-100-3-03- Establishment of Public Tertiary MGOP/PGOrM/ 2023* 2025* Lot acquired; school buildings MGOP/ 90,000.000 90,000.000
001-1-1** Institution/School National constructed; equipment, furnitures and PGOrM/
fixtures purchased; manpower hired; and DepEd/ DPWH/
vehicle purchased Other Sources
8000-3-01-010-a- Upgrading of Municipal Power Supply MEO/PEO/NEA 2023* 2025* 1 Unit 500 KVA Generator Set purhcased; MGOP/PGOrM/ 50,000.000 50,000.000
11** System offices rewired; feeder lines for existing Other Sources
buildings installed; and powerhouse
constructed
1000-3-01-001-a- Construction of Stockroom for Accounts, MEO, GSD 2023* 2023* 500 sq.m. stockroom for account, reports MGOP/ Other 115,000.000 115,000.000
1** Reports and Records and records of government offices Sources
constructed
8000-3-01-010-a- Rehabilitation of Perimeter Fence of MEO/PEO 2023 2023 426.8 linear meters of perimteter fence MGOP/ 1,500.000 1,500.000
27 Municipal Compound constructed PGOrM/ Other
Sources
32 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-01-001-f- Development of Existing Tourism Sites SCO, MEO 2023 2025 10 tourism sites developed; facilities and TIEZA 10,000.000 10,000.000
1 amenities constructed
8000-3-01-010-a- Construction of Access Roads leading to MEO/PEO/DOT 2023* 2025* 20 access roads constructed MGOP/PGOrM/ 50,000.000 50,000.000
14** Tourisms Sites DOT/ Other
Sources
3000-3-03-001-1- Rehabilitation of Municipal Park and MEO 2023 2025* perimeter fence and children's playground MGOP/ other 20,000.000 20,000.000
1* Playground repaired and repainted sources
8000-3-02-003-8 Establishment of Mangrove Eco Park DA, MENRO 2023 2023 Mangrove Conservation Eco Park MGOP/PGOrM/ 2,000.000 2,000.000 2,000.000 A224-03
developed BFAR/ Other
Sources
8000-3-01-010-a- Establishment of Trails for Tourist Spot MEO, SCO 2023 2023 Steps with steel guard rails constructed MGOP/ DOT 1,600.000 1,600.000
28
CENTRALIZED GRAND TERMINAL
1000-3-01-006-6 Land banking for grand terminal MAssO 2023 2024 4 ha of lot purhcased MGOP/ other 8,000.000 8,000.000
sources
8000-3-01-010-a- Coastal Greenway MEO/PEO/DPWH 2023* 2025* 7.5 km coastal greenway constructed MGOP/PGOrM/ 150,000.000 150,000.000
16** DPWH/ Other
Sources
8000-3-02-004- Reacquisition of titled/privately owned lands MO, MENRO/DENR 2023 2025* All lots within the Babahurin Watershed MGOP/ other 40,000.000 40,000.000
19* within Babahurin Watershed reacquired sources
8000-3-01-010-a- Construction of Lumambayan bridges I, II, MEO/PEO/DPWH 2023* 2025* Lumambayan Bridge I (L=30m, W=6m); MGOP/PGOrM/ 190,000.000 190,000.000 190,000.000 A224-02
17** III, Sta. Isabel Bridge II ( 60m , W=6m); Bridge III ( DPWH/ Other
L=30m, W=6m); and Sta.Isabel Bridge ( Sources
L=10m, W=3.6m) constructed
33 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-200-3-03- Provision and Installation of Sanitary MHO 2023 2023 2,500 sanitary toilet facilities provided and MGOP/PGOrM/ 2,500.000 2,500.000 2,500.000 A211-05
001-4 Toilet Facilities installed DOH/ Other
Sources
3000-3-02-005- Construction of Child Development MEO, MSWDO 2023 2025* 61 Child Development Centers MGOP/PGOrM/ 61,000.000 61,000.000 61,000.000 A424-12
5* Centers/Day Care Centers constructed DSWD/ Other
Sources
3000-3-03-001-3- Upgrading of Pinamalayan Gym MEO/PEO/DPWH 2025 2025* Roofing replaced; 10 units airconditioner MGOP/PGOrM/ 35,000.000 35,000.000
2* (1 tonner), 24 units LED light bulbs, DPWH/ Other
wooden floor, acoustical ceiling and wall Sources
panel installed; balcony, electrical room,
and constrol room constructed; lobby and
stage rehabilitated; comfort room
renovated; bleachers upgraded; fire exit
steel door installed; existing steel door
replaced; generator and monitor
purchased; and gym repainted
8000-3-02-003- Crop Development Program MAgO, DA, MEO, 2023* 2025* Facility constructed; mechanical dryer MGOP/ 41,000.000 41,000.000 41,000.000 A114-03
5** (Construction/Installation of mechanical PhilFIDA purchased and installed; vegetables PGOrM/ DA/
dryer; Vegetable Production; Construction seeds and organic fertilizers purchased; PhilFIDA/ Other
of Small Water Impounding Facility; Abaca trained beneficiaries; small water Sources
Production) impounding facility constructed; abaca
planting materials and abaca fiber
extraction machines and equipment
purchased
1000-3-01-002-2 Establishment of legislative Tracking VMO, SB 2023 2023 Hardware and software purhcased and MGOP 500.000 500.000
system/Creation of Archive for Legislative installed; OVM staff trained
Actions
34 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a- Concreting of Municipal Roads MEO/PEO/DPWH 2023 2023 702 meters of municipal road concreted MGOP/PGOrM/ 1,065.000 1,065.000 1,065.000 A634-04
29 DPWH/ Other
Sources
8000-3-02-003- Conversion/Upgrading of Municipal Food SB, MAgO, MEO 2025 2025* Food terminal upgraded to regional food MGOP/PGOrM/ 20,000.000 20,000.000
9* Terminal to Regional Food Terminal terminal DA
3000-3-02-005- Establishment of One Compound for MEO, MSWDO 2025 2025* MSWDO, OSCA, PDAO, LCW Office, MGOP/PGOrM/ 28,000.000 28,000.000
6* Social Welfare Services Home for the Aged, Crisis Center, and DSWD/ Other
Reception and Action Center constructed Sources
in 5 ha of lot
8000-3-01-010-a- Rehabilitation of Roads MEO/PEO/DPWH 2023* 2025* 34.59 km of roads rehabilitated MGOP/PGOrM/ 126,000.000 126,000.000 126,000.000 A634-04
18** DPWH/ Other
Sources
8000-3-01-010-a- Concreting of Barangay Roads MEO/PEO/DPWH 2023* 2025* 41.49 km concreted barangay roads MGOP/PGOrM/ 105,000.000 105,000.000 105,000.000 A634-04
19** DPWH/ Other
Sources
8000-3-01-010-a- Rehabilitation of Public School Buildings MEO/PEO/DPWH 2023* 2025* Public school buildings and facilities MGOP/PGOrM/ 60,000.000 60,000.000 60,000.000 A424-12
20** and Facilities rehabilitated including roofing, repainting, DepED/ Other
rehabilitation of existing structures, Sources
buildings, and facilities
3000-200-3-03- Establishment of Public Tertiary Hospital MHO/LGU/DOH 2025 2025* Existing building upgraded; hospital MGOP/PGOrM/ 100,000.000 100,000.000
001-4* equipment procured; additional health DOH
personnel hired and trained
35 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-03-003-a- Upgrading of the Slaughterhouse Building SOD, MEO, MAssO 2023* 2023* Municipal Slaughterhouse to"Double A" MGOP/ 5,278.500 5,278.500
2-1** and Facilities Category accreditated ; Backyard PGOrM/ NMIC/
pavement concreted; Perimeter concrete Other Sources
fence constructed; Waiting Area with
comfort rooms outside the
Slaughterhouse building constructed;
Septic Tank (Biodegradable and Non-
biodegradable) constructed; Roofing of
Animals Holding/Dispatching Area
(Auxiliary Part of the Main Building)
installed; Stainless inspection table
fabricated; and acquired leg spreader,
beef shackle, carwash machine, booster
blower, grass cutter, weighing cale,
pressurized motor pump, dehairing
machine, and refrigerated delivery van
8000-3-01-010-a- Opening of proposed roads MEO/PEO/DPWH 2023* 2025* 6 km of roads opened MGOP/PGOrM/ 70,000.000 70,000.000
21** DPWH/ Other
Sources
3000-3-03-001-3- Establishment of Modern Sports Complex MEO/PEO/DPWH 2023* 2025* Lot purhcased; track and field oval MGOP/PGOrM/ 200,000.000 200,000.000
1** developed; grandstand, swimming pool, Other Sources
dormitory, and covered court constructed
1000-3-01-006- Acquisition of Lots for Future Expansion MAssO 2023* 2025* 50 ha of land acquired MGOP/Other 50,000.000 50,000.000
2* of Urban Development Sources
36 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-02-003- Farm Mechanization Program MAgO, DA 2023* 2025* Hand Tractor with Trailer acquired; MGOP/PGOrM/ 18,300.000 18,300.000
6** Shallow Tube Well installed; Rice DA
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
1000-3-03-001-2- Modernizing of Firefighting Tools, MO/MDRRMO/BFP 2023* 2025* Protective gears, fire axe, chainsaw, MDRRMF 800.000 800.000
13-2** Apparatus, and Equipment hydraulic spreader, rescue ropes with
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2- Installation of Additional Fire Hydrants BFP/MDRRMO 2023* 2025* fire hydrants installed MDRRMF/BFP 1,000.000 1,000.000
13-3**
1000-3-03-001-2- Upgrading of BFP Building and Facilities BFP 2023* 2025* Office, personnel quarters, gate and BFP/ Other 600.000 600.000
13-4** fence repainted; and stockroom Sources
upgraded
3000-3-02-005-2- Construction of Additional Barangay MEO 2023* 2025* 10 Senior Citizens Affairs Centers MGOP/Other 5,500.000 5,500.000
4-1* Senior Citizens Affairs Centers constructed Sources
OTHERS
1000-3-01-006-3 Acquisition of Lots for Future Expansion MAssO 2023* 2025* 50 ha of land acquired MGOP/ Other 50,000.000 50,000.000
sources
8000-3-02-003-9 Farm Mechanization Program MAgO, DA 2023* 2025* Hand Tractor with Trailer acquired; MGOP/DA/ 18,300.000 18,300.000
Shallow Tube Well installed; Rice Other Sources
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
37 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-01-006-7 Land Banking for social services such as MAssO, MENRO, 2023* 2025* 25 hectares of lot acquired MGOP/ Other 25,000.000 25,000.000
MSWDO compound, MSWDO sources
PRTO and other CSOs, Police outposts,
BFP lot (25 ha)
1000-3-03-001-2-13-2
Modernizing of Firefighting Tools, Apparatus, MO 2023* 2025* Protective gears, fire axe, chainsaw, MGOP/ Other 800.000 800.000
and Equipment hydraulic spreader, rescue ropes with sources
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2-13-3
Installation of Additional Fire Hydrants BFP, MEO 2023* 2025* fire hydrants installed MGOP/BFP 1,000.000 1,000.000
1000-3-03-001-2-13-4
Upgrading of BFP Building and Facilities BFP 2023* 2025* Office, personnel quarters, gate and MGOP/BFP 600.000 600.000
fence repainted; and stockroom
upgraded
3000-3-02-005-2-4-1
Construction of Additional Barangay Senior MEO 2023* 2025* 10 Senior Citizens Affairs Centers MGOP/ Other 5,500.000 5,500.000
Citizens Affairs Centers constructed sources
8000-3-01-010-a-26
Installation of Road Signs (Warning Signs, MEO, DPWH 2023* 2025* 50 pcs warning Signs and 50 pcs MGOP/ Other 1,330.000 1,330.000
Regulatory Signs) regulatory signs installed sources
8000-3-01-010-a-28
Pedestrian Crossings MEO, DPWH 2023* 2025* 40 pcs pedestrian crossings provided MGOP/DPWH/ 864.000 864.000 864.000 M631-04
Other Sources
3000-200-3-03-001-7
Acquisition of Ambulances VMO, SB 2023* 2025* Additional unit of ambulance acquired MGOP/ DOH/ 4,000.000 4,000.000
Other sources
8000-3-03-003-a-1-5
Establishment of Trading Facility or Local MEO 2023* 2025* 2,306.45 sqm. Local Exchange Trading MGOP/ Other 15,000.000 15,000.000
Exchange Trading Terminal (LETT) Terminal constructed sources
38 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-3-02-005-9 Establishment of Persons with Disability MAssO 2023* 2025* PDA officer hired; IDs & Booklets MGOP/ Other 4,000.000 4,000.000
Affairs Office (PDAO) procured; Orientation on Magna Carta for sources
PWDs (Benefits and Privileges of PWD)
conducted; Business Forum on the Rights
of Persons with Disabilities conducted;
Livelihood Assistance (Salted Egg
Production) provided; PWD of Sta. Rita
organized; Medical Mission and other
activities conducted
1000-3-01-009-1 Computerization Program/Information and MO 2023* 2025* ICT Office with permanent positions MGOP/ Other 15,000.000 15,000.000
Communications Technology (ICT-CeC) established; ICT Administration Building sources
Project constructed furnished with needed IT
equipment, office equipment, furniture
and fixtures, transportation vehicles, etc.;
Agency Information Kiosk developed;
Centralized Local Area Network and
Information System established; and e-
Billboard installed and functional
8000-3-01-010-a-29
Upgrading of Existing Roads MEO 2023* 2025* MGOP/PGOrM/ 358,380.000 358,380.000 358,380.000 A634-04
Other sources
8000-3-01-010-a-34
Electrification program ORMECO 2023* 2025* 197 poles installed MGOP/NEA/ 10,835.000 10,835.000
other sources
8000-3-01-010-a-30
Construction of Multi-purpose hall/covered MEO 2023* 2025* 33 multi-purpose hall buildings MGOP/ other 82,500.000 82,500.000
court in every barangay (33 barangays) constructed soources
39 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a-35
Formulation of Comprehensive Road Network MEO 2023* 2025* Topographic survey conducted; surveying MGOP/PGOrM/ 15,000.000 15,000.000
Plan instrument acquired Other sources
1000-3-03-001-2-12-1
Construction of 8 Mobile Police Outpost in MEO, PNP 2023* 2025* 8 mobile police outputs constructed MGOP/PNP/oth 4,000.000 4,000.000
Strategic Locations er sources
3000-100-3-03-001-1-3
E-Eskwela MGOP, ALS 2023* 2025* Customized Instruction Models provided; MGOP/ other 1,000.000 1,000.000
trainors equipped; stakeholders training soources
conducted
3000-100-3-03-001-a-1
Project SAFE (Secure, Accommodating, MEO, DepED 2023* 2025* 33 elementary schools, 12 secondary MGOP/DepEd/ 23,173.000 23,173.000 23,173.000 A424-11
Friendly Environment) schools, and 2 district offices other sources
rehabilitated; school facilities constructed;
furnitures and foxtures acquired
8000-3-01-010-a-36
Rehabilitation/upgrading of existing port MEO 2023* 2025* Port facilities rehabilitated MGOP/PGOrM/ 200,000.000 200,000.000
facilities Other sources
8000-3-01-010-a-38
Rehabilitation or upgrading of existing NIA MEO 2023* 2025* NIA roads rehabilitated MGOP/PGOrM/ 160,000.000 160,000.000 160,000.000 A634-04
Roads Other sources
8000-3-01-010-a-39
Expansion of airport MEO 2023* 2025* Elevated runway; embankment; pavement MGOP/PGOrM/ 135,000.000 135,000.000 135,000.000 A634-04
concreted; lightings installed; building DOTR/DPWH
constructed; station of building upgraded Other sources
3000-100-3-03-001-a-2
Project HEART (Provision of Multimedia MO, DepEd 2023* 2025* LED TV, projectors, laptop, desktop MGOP/DepEd/ 8,000.000 8,000.000
Instructional Materials) computer acquired; WIFI Connection other sources
installed; SHS reference books and other
reading materials provided; training and
seminars conducted
40 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-03-003-b-3-1
Installation of Public Address System within MEO 2023* 2025* Public address equipment procured and MGOP/PGOrM/ 40,000.000 40,000.000
Poblacion Area installed Other sources
8000-3-01-010-a-14*
Construction of Overpass in ABADA College MEO 2023* 2025* Overpass constructed MGOP/PGOrM/ 1,500.000 1,500.000
and Nabuslot National High School DPWH/ Other
sources
Prepared by: Attested by: Certified correct and approved by the LDC:
EnP ROSENIO A. TORIANO ZAIDA D. MICIANO PLARIDEL S. CUPIADO ARISTEO APASAN BALDOS, JR.
Municipal Planning and Development Coordinator Local Budget Officer Local Treasurer Municipal/LDC Chairman
41 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
LIVELIHOOD PROGRAM
8000-3-02-003-1***Fishery Livelihood Program (Fish MAgO 2026* 2028 Fish Aggregating devices purchased; MGOP/PGOrM/ 20,000.000 20,000.000 20,000.000 A113-08
Aggregating Devices, Aquasilvi Culture, fishing boats with complete set of gill net BFAR/ Other
Fishing Boats with complete set of gill net (motorized & non-motorized & hook & Sources
(motorized & non-motorized, hook and line); line) provided; Tilapia and Bangus fry
Fish processing) dispersed; and Aquasilvi farm developed
8000-3-02-003-2***Barangay Livelihood MAgO 2026* 2028 Processing center constructed; MGOP/BFAR 37,000.000 37,000.000
processing equipment procured; and
conducted livelihood trainings for abaca
expansion, crop production, animal
raising, and fish production
8000-3-02-004-17**
Livelihood Projects for Indigenous People of MAgO, DA 2026* 2028 Trading of Agricultural Products, Draft MGOP/PGOrM/ 33,000.000 33,000.000
Pinamalayan Animals dispersal, Abaca Expansion Other sources
Project, trainings attended/conducted
Establishment of Trading Facility or Local MEO 2026* 2026 2,306.45 sqm. Local Exchange Trading MGOP/Other 15,000.000 15,000.000
Exchange Trading Terminal (LETT) Terminal constructed sources
Installation of Public Address System within MEO 2026* 2028 Public address equipment procured and MGOP/ other 40,000.000 40,000.000
Poblacion Area installed sources
NEW GOVERNMENT CENTER
1000-3-01-006- Land banking for government offices (10 ha) MAssO 2026* 2026 10 hectares of land purchased MGOP/ Other 20,000.000 20,000.000
4** Sources
1000-3-01-006-7 New municipal government center MAssO 2026 2028 Office Buildings, Parking Area, Storage MGOP/ Other 100,000.000 100,000.000
Buildings, Evacuation Area, Perimeter Sources
Fence and other facilities constructed
42 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a-3***
Comprehensive Drainage Plan MEO 2026* 2028 Drainage plan formulated; existing MGOP/PGOrM/ 322,000.000 322,000.000 322,000.000 A224-01
drainage canals rehabilitated and DPWH/ Other
desilted; natural ways desilted Sources
8000-3-02-004-10***
Conduct of a Comprehensive Topographic Zoning Division 2026* 2026 Comprehensive Topographic Survey MGOP/PGOrM/ 60,000.000 60,000.000 60,000.000 A631-01
Survey conducted in the Poblacion area DPWH/ Other
Sources
8000-3-01-010-a-7***
Desilting of upstream of Inclanay Dam MEO 2026* 2028 Inclanay river banks desilted NIA 50,000.000 50,000.000 50,000.000 A114-05
8000-3-01-010-a-9***
Construction of breakwater MEO 2026* 2028 Breakwater constructed MGOP/PGOrM/ 180,000.000 180,000.000 180,000.000 A224-02
DPWH/ Other
Sources
HOUSING PROGRAM
3000-3-02-005- Core Shelter Assistance Program MSWDO, MEO 2026* 2028 150 Core Housing Units constructed; MGOP/PGOrM/ 52,500.000 52,500.000 52,500.000 A424-06
2*** basic amenities installed (water, DPWH/ DSWD/
electricity); roadways and drainage canal Other Sources
constructed
3000-3-02-005- Socialized Housing Project MSWDO, MEO 2026* 2027 5 ha lot developed; 200 housing units MGOP/PGOrM/ 100,000.000 100,000.000 100,000.000 A424-06
3** constructed DPWH/ DSWD/
Other Sources
3000-3-02-005- Employees’ Housing Program MSWDO, MEO 2026* 2028 5 hectares of Land acquired, 100 MGOP/ other 50,000.000 50,000.000
4** Socialized Housing Units constructed sources
8000-3-03-003-a- Commercial Building MOD, MEO 2026* 2028 Two storey twin commercial building MGOP/Other 105,000.000 105,000.000
1-3** construced Sources
3000-200-3-03- Health Card for Pinamalayan Residents MO, MHO 2026* 2028* Medicard provided from authorized MGOP/ DOH/ 200,000.000 200,000.000 200,000.000 A414-06
001-1*** companies with 100% coverage in 2028 Other Sources
43 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-100-3-03- Establishment of Public Tertiary Institution/ MGOP/PGOriental 2026* 2028* Lot acquired; school buildings MGOP/PGOrM/ 90,000.000 90,000.000
001-1-1*** School Mindoro/National constructed; equipment, furnitures and DepEd/ Other
Government fixtures purchased; manpower hired; and Sources
vehicle purchased
8000-3-01-010-a-30
Development of Potential Tourism SCO, MEO 2027 2028 10 tourism sites developed MGOP/PGOrM/ 10,000.000 10,000.000
Attractions/Destinations DOT/ Other
Sources
3000-3-03-001-1-1**
Rehabilitation of Municipal Park and MEO 2026* 2026 perimeter fence and children's playground MGOP/ Other 20,000.000 20,000.000
Playground repaired and repainted Sources
8000-3-02-004-20 Establishment of new public spaces or MENRO, MEO 2027 2028 New Public Spaces facility intended for MGOP/ other 9,000.000 9,000.000
recreational park recreation established sources
Coastal Greenway
8000-3-01-010-a-16*** MEO 2026* 2028 7.5 km coastal greenway constructed MGOP/PGOrM/ 150,000.000 150,000.000
DPWH/ Other
Sources
44 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a-17***
Construction of Lumambayan bridges I, II, III, MEO 2026* 2028 Lumambayan Bridge I (L=30m, W=6m); MGOP/PGOrM/ 190,000.000 190,000.000 190,000.000 A224-02
Sta. Isabel Bridge II (60m , W=6m); Bridge III ( DPWH/ Other
L=30m, W=6m); and Sta.Isabel Bridge ( Sources
L=10m, W=3.6m) constructed
3000-3-02-005- Construction of Child Development MEO, MSWDO 2026* 2028 61 Child Development Centers MGOP/PGOrM/ 61,000.000 61,000.000 61,000.000 A424-12
5** Centers/Day Care Centers constructed DPWH/DSWD/
Other Sources
3000-3-03-001-3- Upgrading of Pinamalayan Gym MEO 2025 2028 Roofing replaced; 10 units airconditioner MGOP/PGOrM/ 35,000.000 35,000.000
2** (1 tonner), 24 units LED light bulbs, DPWH/ Other
wooden floor, acoustical ceiling and wall Sources
panel installed; balcony, electrical room,
and constrol room constructed; lobby and
stage rehabilitated; comfort room
renovated; bleachers upgraded; fire exit
steel door installed; existing steel door
replaced; generator and monitor
purchased; and gym repainted
8000-3-02-003-5***Crop Development Program MAgO, DA, MEO, PhilFIDA 2026* 2028 Facility constructed; mechanical dryer DA; PhilFIDA; 41,000.000 41,000.000 41,000.000 A114-03
(Construction/Installation of mechanical purchased and installed; vegetables Other Sources
dryer; Vegetable Production; Construction of seeds and organic fertilizers purchased;
Small Water Impounding Facility; Abaca trained beneficiaries; small water
Production) impounding facility constructed; abaca
planting materials and abaca fiber
extraction machines and equipment
purchased
8000-3-02-003-9**Conversion/Upgrading of Municipal Food SB, MAgO, MEO 2026* 2027 Food terminal upgraded to regional food DA, PhilFIDA, 20,000.000 20,000.000
Terminal to Regional Food Terminal terminal Other Sources
45 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-3-02-005- Establishment of One Compound for Social MEO, MSWDO 2026* 2028 MSWDO, OSCA, PDAO, LCW Office, MGOP/PGOrM/ 28,000.000 28,000.000
6** Welfare Services Home for the Aged, Crisis Center, and DSWD/Other
Reception and Action Center constructed Sources
in 5 ha of lot
1000-3-01-009- Updating of Community-Based MPDO, CBMS-TWG 2026* 2026* CBMS Database updated; CBMS-Based MGOP/PGOrM/ 10,000.000 10,000.000
1** disaggregated data Municipal and Barangay Profile and Other Sources
Development Plan updated
8000-3-01-010-a-18***
Rehabilitation of Roads MEO 2026* 2028 34.59 km of roads rehabilitated MGOP/PGOrM/ 126,000.000 126,000.000 126,000.000 A634-04
National/Otherl
Sources
8000-3-01-010-a-19***
Concreting of Barangay Roads MEO 2026* 2028 41.49 km concreted barangay roads MGOP/PGOrM/ 105,000.000 105,000.000 105,000.000 A634-04
National/Other
Sources
8000-3-02-003-10 Livestock Development Program MAgO 2026 2026 Piglets purchased and dispersed MGOP/PGOrM/ 500.000 500.000 500.000 A414-04
Other sources
8000-3-01-010-a-20***
Rehabilitation of public school buildings and MEO 2026* 2028 Public school buildings and facilities MGOP/PGOrM/ 60,000.000 60,000.000 60,000.000 A424-12
facilities rehabilitated including roofing, repainting, DPWH/DepEd/
rehabilitation of existing structures, Other Sources
buildings, and facilities
8000-3-02-003-11 Establishment of Auction Market with holding MAgO, MEO 2028 2028 Auction Market with temporary Holding MGOP/PGOrM 40,000.000 40,000.000
pen Pen constructed Other Sources
3000-200-3-03- Acquisition of Mobile Clinic MHO 2028 2028 Purchased mobile clinic; manpower MGOP/PGOrM/ 10,000.000 10,000.000
001-5 added and trained; medical equipment DOH
and mediicnes procured
46 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
1000-3-01-006-8 Updating of Inventory of Real Property Units MAssO 2026 2026 Accurate and updated inventory of real MGOP/DOH 650.000 650.000
(RPUs) properties
8000-3-03-003-a- Upgrading of the Slaughterhouse Building SOD, MEO, MAssO 2026* 2026 Municipal Slaughterhouse to"Double A" MGOP/ Other 5,278.500 5,278.500
2-1*** and Facilities Category accreditated ; Backyard Sources
pavement concreted; Perimeter concrete
fence constructed; Waiting Area with
comfort rooms outside the
Slaughterhouse building constructed;
Septic Tank (Biodegradable and Non-
biodegradable) constructed; Roofing of
Animals Holding/Dispatching Area
(Auxiliary Part of the Main Building)
installed; Stainless inspection table
fabricated; and acquired leg spreader,
beef shackle, carwash machine, booster
blower, grass cutter, weighing cale,
pressurized motor pump, dehairing
machine, and refrigerated delivery van
3000-200-3-03- Establishment of Public Tertiary Hospital MHO/LGU/DOH 2026* 2028 Existing building upgraded; hospital MGOP/DOH/ 100,000.000 100,000.000
001-4** equipment procured; additional health External
personnel hired and trained Sources
8000-3-01-010-a-21***
Opening of proposed roads MEO 2026* 2028 6 km of roads opened MGOP/PGOrM/ 70,000.000 70,000.000
National/Extern
al Sources
8000-3-02-003-12 Construction of Multi-purpose Farmers MAgO 2028 2028 Multi-Purpose Farmers Training Center MGOP/DA 10,000.000 10,000.000
Training Center constructed
47 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-3-03-001-3- Establishment of Modern Sports Complex MEO 2026* 2028 Lot purhcased; track and field oval MGOP/PGOrM/ 200,000.000 200,000.000
1*** developed; grandstand, swimming pool, Other Sources
dormitory, and covered court constructed
8000-3-02-004-21 Mangrove Rehabilitation MAgO, MDRRM, 2028 2028 Mangrove areas rehabilitated MGOP/ other 10,000.000 10,000.000 10,000.000 A224-03
MENRO, DENR sources
1000-3-01-006- Acquisition of Lots for Future Expansion of MAssO 2026* 2028 50 ha of land acquired MGOP/ Other 50,000.000 50,000.000
2*** Urban Development Sources
8000-3-02-003-7***Farm Mechanization Program MAgO, DA 2026* 2028 Hand Tractor with Trailer acquired; MGOP/DA/ 18,300.000 18,300.000
Shallow Tube Well installed; Rice Other sources
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
1000-3-03-001-2- Modernizing of Firefighting Tools, BFP 2026* 2028 Protective gears, fire axe, chainsaw, DRRMF/BFP 800.000 800.000
13-2*** Apparatus, and Equipment hydraulic spreader, rescue ropes with
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2- Installation of Additional Fire Hydrants BFP, MEO 2026* 2028 Fire hydrants installed DRRMF/BFP 1,000.000 1,000.000
13-3***
1000-3-03-001-2- Upgrading of BFP Building and Facilities BFP 2026* 2028 Office, personnel quarters, gate and BFP 600.000 600.000
13-4*** fence repainted; and stockroom
upgraded
3000-3-02-005-2-4-1**
Construction of Additional Barangay Senior MEO 2026* 2028 10 Senior Citizens Affairs Centers MGOP/ Other 5,500.000 5,500.000
Citizens Affairs Centers constructed Sources
48 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
OTHERS
1000-3-01-006-3 Acquisition of Lots for Future Expansion MAssO 2026* 2028 50 ha of land acquired MGOP/ Other 50,000.000 50,000.000
sources
8000-3-02-003-9 Farm Mechanization Program MAgO, DA 2026* 2028 Hand Tractor with Trailer acquired; MGOP/DA/ 18,300.000 18,300.000
Shallow Tube Well installed; Rice Other Sources
Combine Harvester procured; and Four
Wheeled Farm Tractor procured
1000-3-01-006-7 Land Banking for social services such as MAssO, MENRO, 2026* 2028 25 hectares of lot acquired MGOP/ Other 25,000.000 25,000.000
MSWDO compound, MSWDO sources
PRTO and other CSOs, Police outposts,
BFP lot (25 ha)
1000-3-03-001-2-13-2
Modernizing of Firefighting Tools, Apparatus, MO 2026* 2028 Protective gears, fire axe, chainsaw, MGOP/ Other 800.000 800.000
and Equipment hydraulic spreader, rescue ropes with sources
carabiners, pulleys and other high angle
rescue accessories, self-contained
breathing apparatus (SCBA), heavy-duty
flashlights, laddered firetruck procured
1000-3-03-001-2-13-3
Installation of Additional Fire Hydrants BFP, MEO 2026* 2028 fire hydrants installed MGOP/BFP 1,000.000 1,000.000
1000-3-03-001-2-13-4
Upgrading of BFP Building and Facilities BFP 2026* 2028 Office, personnel quarters, gate and MGOP/BFP 600.000 600.000
fence repainted; and stockroom
upgraded
3000-3-02-005-2-4-1
Construction of Additional Barangay Senior MEO 2026* 2028 10 Senior Citizens Affairs Centers MGOP/ Other 5,500.000 5,500.000
Citizens Affairs Centers constructed sources
8000-3-01-010-a-26
Installation of Road Signs (Warning Signs, MEO, DPWH 2026* 2028 50 pcs warning Signs and 50 pcs MGOP/ Other 1,330.000 1,330.000
Regulatory Signs) regulatory signs installed sources
8000-3-01-010-a-28
Pedestrian Crossings MEO, DPWH 2023* 2025* 40 pcs pedestrian crossings provided MGOP/DPWH/ 864.000 864.000 864.000 M631-04
Other Sources
49 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-200-3-03-001-7
Acquisition of Ambulances VMO, SB 2026 2026 Additional unit of ambulance acquired MGOP/ DOH/ 4,000.000 4,000.000
Other sources
8000-3-03-003-a-1-5
Establishment of Trading Facility or Local MEO 2026 2026 2,306.45 sqm. Local Exchange Trading MGOP/ Other 15,000.000 15,000.000
Exchange Trading Terminal (LETT) Terminal constructed sources
3000-3-02-005-9 Establishment of Persons with Disability MAssO 2026* 2028 PDA officer hired; IDs & Booklets MGOP/ Other 4,000.000 4,000.000
Affairs Office (PDAO) procured; Orientation on Magna Carta for sources
PWDs (Benefits and Privileges of PWD)
conducted; Business Forum on the Rights
of Persons with Disabilities conducted;
Livelihood Assistance (Salted Egg
Production) provided; PWD of Sta. Rita
organized; Medical Mission and other
activities conducted
1000-3-01-009-1 Computerization Program/Information and MO 2026* 2028 ICT Office with permanent positions MGOP/ Other 15,000.000 15,000.000
Communications Technology (ICT-CeC) established; ICT Administration Building sources
Project constructed furnished with needed IT
equipment, office equipment, furniture
and fixtures, transportation vehicles, etc.;
Agency Information Kiosk developed;
Centralized Local Area Network and
Information System established; and e-
Billboard installed and functional
8000-3-01-010-a-29
Upgrading of Existing Roads MEO 2026* 2028 MGOP/PGOrM/ 358,380.000 358,380.000 358,380.000 A634-04
Other sources
8000-3-01-010-a-34
Electrification program ORMECO 2026* 2028 197 poles installed MGOP/NEA/ 10,835.000 10,835.000
other sources
50 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
8000-3-01-010-a-30
Construction of Multi-purpose hall/covered MEO 2026* 2028 33 multi-purpose hall buildings MGOP/ other 82,500.000 82,500.000
court in every barangay (33 barangays) constructed soources
8000-3-01-010-a-35
Formulation of Comprehensive Road Network MEO 2026* 2028 Topographic survey conducted; surveying MGOP/PGOrM/ 15,000.000 15,000.000
Plan instrument acquired Other sources
1000-3-03-001-2-12-1
Construction of 8 Mobile Police Outpost in MEO, PNP 2026* 2028 8 mobile police outputs constructed MGOP/PNP/oth 4,000.000 4,000.000
Strategic Locations er sources
3000-100-3-03-001-1-3
E-Eskwela MGOP, ALS 2026* 2028 Customized Instruction Models provided; MGOP/ other 1,000.000 1,000.000
trainors equipped; stakeholders training soources
conducted
3000-100-3-03-001-a-1
Project SAFE (Secure, Accommodating, MEO, DepED 2026* 2028 33 elementary schools, 12 secondary MGOP/DepEd/ 23,173.000 23,173.000 23,173.000 A424-11
Friendly Environment) schools, and 2 district offices other sources
rehabilitated; school facilities constructed;
furnitures and foxtures acquired
8000-3-01-010-a-36
Rehabilitation/upgrading of existing port MEO 2026* 2028 Port facilities rehabilitated MGOP/PGOrM/ 200,000.000 200,000.000
facilities Other sources
8000-3-01-010-a-38
Rehabilitation or upgrading of existing NIA MEO 2026* 2028 NIA roads rehabilitated MGOP/PGOrM/ 160,000.000 160,000.000 160,000.000 A634-04
Roads Other sources
8000-3-01-010-a-39
Expansion of airport MEO 2026* 2028 Elevated runway; embankment; pavement MGOP/PGOrM/ 135,000.000 135,000.000 135,000.000 A634-04
concreted; lightings installed; building DOTR/ DPWH/
constructed; station of building upgraded Other sources
51 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
3000-100-3-03-001-a-2
Project HEART (Provision of Multimedia MO, DepEd 2026* 2028 LED TV, projectors, laptop, desktop MGOP/DepEd/ 8,000.000 8,000.000
Instructional Materials) computer acquired; WIFI Connection other sources
installed; SHS reference books and other
reading materials provided; training and
seminars conducted
8000-3-03-003-b-3-1
Installation of Public Address System within MEO 2026* 2028 Public address equipment procured and MGOP/PGOrM/ 40,000.000 40,000.000
Poblacion Area installed Other sources
8000-3-01-010-a-14*
Construction of Overpass in ABADA College MEO 2026* 2028 Overpass constructed MGOP/PGOrM/ 1,500.000 1,500.000
and Nabuslot National High School DPWH/ Other
sources
Prepared by: Attested by: Certified correct and approved by the LDC:
EnP ROSENIO A. TORIANO ZAIDA D. MICIANO PLARIDEL S. CUPIADO ARISTEO APASAN BALDOS, JR.
Municipal Planning and Development Coordinator Local Budget Officer Local Treasurer Municipal/LDC Chairman
52 | Page
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
53 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to : Feasibility study
produce the desired output : Site validation
54 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to February 2020-preparation of plans and programs and bidding
: March 2020 to June 2021 is the construction of the project
Requirements needed to be done to Engineering designs
produce the desired output
55 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment /construction
Requirements needed to be done to : Feasibility study
produce the desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
Materials Php 3,765,000.00
Human Resources (Labor) 2,510,000.00
Estimated
Equipment 125,000.00
Costs
Others 100,000.00
TOTAL Php 6,500,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Based on the RA 9003 which mandates every LGU to manage their solid wastes, it is
CLUP/CDP also mandated that wastewater should also be given priority by proposing programs and
projects to address problems in wastewater.
Major Problem being addressed Wastewater Management
What are the effects of the project to social All individuals are entitled to have a safe and clean evironment. Environment includes
and economic activities? And in what natural waters therefore we are also needs safe and clean natural waters either for
locations? drinking and/or leisure purposes.
E. Target beneficiaries LGU’s inhabitants and business sectors in poblacion areas
F. Target Output / Success Indicator : Clean and Safe Natural Waters and Environment
: Reduced Water-borne diseases
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible Public-Private partnership
56 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to : Feasibility study
produce the desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
Materials Php 1,440,000.00
Human Resources (Labor) 960,000.00
Estimated
Equipment 50,000.00
Costs
Others 50,000.00
TOTAL Php 2,500,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Waste Management is very important in every LGU’s. RA 9003 mandates LGU’s to
CLUP/CDP establish waste management facilities to cater bulk of wastes being produced by their
different establishments. Hazardous and toxic wastes or what we call special wastes
need to address on how to handle by securing it so that it will not cause harm to
anybody. One way is to commission hauler to transfer it to treatment facility in Metro
Manila but being an island province like we are it is very expensive and more than that
there is a possibility that no hauler will be available because of a very little amount of
special wastes. Establishing waste treatment facility is a more possible solution to this
problem.
Major Problem being addressed Special Waste Management
What are the effects of the project to social Will spare our constituents on the effect of harmful hazardous and toxic wastes.
and economic activities? And in what
locations?
E. Target beneficiaries LGU’s inhabitants
F. Target Output / Success Indicator : Clean and Safe Environment
: Reduced airborne diseases
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible Public-Private partnership
57 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
58 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 1st week of August intended for aquisition of seedlings and coordination with different
stakeholders or participants
: 2nd week of August is the implementation of the project
Requirements needed to be done to Selection of desired/suitable area
produce the desired output
: First day is the hauling of materials on the site location
Steps or procedure of the project : Second day is the tree planting activities
: Third day is the construction of tree guard
Implementing Arm MENRO/CENRO/NGO’s
Monitoring and Evaluation personnel/group MENRO/MPDO
Frequency of monitoring and evaluation Twice a month after the tree planting
Materials Php 1,200,000.00
Human Resources (Labor) 500,000.00
Estimated
Equipment 200,000.00
Costs
Others 100,000.00
TOTAL Php 2,000,000.00
Funding Source 20% DF
Is the Project expected to be financially No
self-sustaining?
D. Justification of the Project
Rationale/ Objective derived from : Every human being is entitled for a safe drinking water
CLUP/CDP : By 2022, water quality with DENR standard
Major Problem being addressed Insufficient supply of drinking water
What are the effects of the project to social Good water supply is one of the requirements of some investors
and economic activities? And in what
locations?
E. Target beneficiaries Inhabitants of barangays being served of drinking water from Babahurin river
F. Target Output / Success Indicator : Suitable drinking water supply
: Babahurin river protected
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible private sector cooperation including NGO
59 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
EN7 | Construction of Riverbank Protection Dike in all barangays along Pula River
Name of Project CONSTRUCTION OF RIVERBANK PROTECTION DIKE IN ALL BARANGAYS
ALONG PULA RIVER
A. Brief Description Construction of riverbank protection dike in all barangays along Pula River for flood
control
B. Location of the Project All barangays along Pula River - Inclanay, Marayos, Pagalagala, Pambisan Malaki,
Sabang, Sta. Maria and Sto. Nino
C. Program Components : Site inspection
: Preparation of construction materials
: Project implementation
- Construction of riverbank protection dike
- Monitoring and evaluation
Proponents Municipal Government of Pinamalayan - MDRRMO
Program Term 2021 to 2022 (1 year and 3 months)
60 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
61 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
EN27 | Construction of Storage Facility within Sanitary Landfill for Toxic Wastes
Name of Project CONSTRUCTION OF FACILITY WITHIN SANITARY LANDFILL FOR TOXIC
WASTES
A. Brief Description It is a building/storage facility intended for the safekeeping of hazardous and toxic
waste to separate these from other wastes to secure the safety of the people
engaging in the operation of sanitary landfill.
B. Location of the project Brgy. Maningcol, Pinamalayan, Or. Mindoro
C. Program Components : Building
: Division of Different Hazardous/Toxic Waste
Proponents Mun. Gov’t./ MENRO
Program Term 2020-2022
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to produce the : Feasibility study
desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
Materials Php 1,005,000.00
Estimated Human Resources (Labor) 670,000.00
Costs Equipment 75,000.00
Others 50,000.00
TOTAL Php 1,800,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP Waste Management is very important in every LGU’s. RA 9003 mandates LGU’s to
establish waste management facilities to cater bulk of wastes being produced by
their different establishments. Hazardous and toxic wastes or what we call special
wastes need to address on how to handle by securing it so that it will not cause
harm to anybody.
Major Problem being addressed Special Waste Management
What are the effects of the project to social and Will spare our constituents on the effect of harmful hazardous and toxic wastes.
economic activities? And in what locations?
E. Target beneficiaries LGU’s inhabitants
F. Target Output / Success Indicator : Clean and Safe Environment
: Reduced airborne diseases
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible Public-Private partnership
62 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to produce : Feasibility study
the desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
Materials Php 2,025,000.00
Human Resources (Labor) 1,350,000.00
Estimated
Equipment 75,000.00
Costs
Others 50,000.00
TOTAL Php 3,500,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP Waste Management is very important in every LGU’s. RA 9003 mandates LGU’s to
establish waste management facilities to cater bulk of wastes being produced by their
different establishments. Different schemes implemented by every LGU such as no-
segregation-no-colletion, establishment of sanitary landfills, mrf’s and others but still
wastes problems are still cannot be solved as easy as we could emagine.
Establishment of recycling facility is one way of reducing our wastes being hauled to
dumping site or SLF.
Major Problem being addressed Waste Management
What are the effects of the project to social Will develop income to nearby folks and scavengers on the recycling of waste
and economic activities? And in what materials.
locations?
E. Target beneficiaries LGU’s inhabitants and business sectors
F. Target Output / Success Indicator : Clean and Safe Environment
: Reduced airborne diseases
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible Public-Private partnership
63 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-Purchase of Equipment
Requirements needed to be done to produce : Canvassing of modern type of garbage compactor with separator
the desired output
64 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
65 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : April to December 2023 (9 months) - identification of relocation sites
: January 2024 to June 2025 (1 year and 6 months) - relocation
Requirements needed to be done to produce : Site inspection
the desired output : Identification of relocation sites
: Means for relocation
66 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to produce : Feasibility study
the desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
Materials Php 870,000.00
Human Resources 580,000.00
(Labor)
Estimated Costs
Equipment 25,000.00
Others 25,000.00
TOTAL Php 1,500,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP Waste Management is very important in every LGU’s. RA 9003 mandates LGU’s to
establish waste management facilities to cater bulk of wastes being produced by their
different establishments. Establishment of Sanitary Landfill is also mandated to each
LGU. When SLF is already established, maintenanance should also considered. One
way to maintain this establishment is to make sure that no outsider will allow to enter
its premise and disposal of garbage on the landfill other than from the LGU’s
equipments are not allowed. Establishment of guardhouse that will serve as shelter to
dumpsite carataker is very necessary.
Major Problem being addressed Maintenance and safeguarding of Sanitary Landfill
What are the effects of the project to social If there is a decent shelter to our dumpsite catetaker such as guardhouse, this will give
and economic activities? And in what boost to him to further do his job and therefore no more outsiders will enter the
locations? dumpsite premise so that they will be spare of harmful effect of dumpsite facility.
E. Target beneficiaries LGU’s dumpsite caretaker, inhabitants near the site and garabage collector
F. Target Output / Success Indicator Maintained SLF Facility
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Since guarding the SLF Site will prohibit the entrance of outsiders, will also mean less
effect of the facility to inhabitants therefore possitve effect on the different sectors.
67 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : October to December 2019 (3 months) – appointment and agreement with the FLA
holders for the reversion
: January to June 2020 onwards – procurement of seedlings, establishment of nursery
and rehabilitation of mangrove area
Requirements needed to be done to produce : Feasibility Study
the desired output : Appointment with the fishpond operators with inactive and expired FLA
: Area for Nursery
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Costs Php 10,000,000.00
Funding Source FFS - DENR
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP : This aims to rehabilitate and reforest the denuded mangrove areas of Pinamalayan.
: By 2026, rehabilitated mangrove forest by 100%
: By 2022, declaration of additional protected areas (e.g. mangroves)
: By 2022, reinstated LGU management of mangrove forest
: By 2028, fully developed potential eco-tourism site/s (mangrove forest) and serve as
source of livelihood
Major Problem being addressed Denudation and continuous conversion of mangrove areas to fishponds
What are the effects of the project to social Every ecosystem plays a very important role in our environment which maintains
and economic activities? And in what equilibrium. Reforestation of this type of environment may increase the spawning
locations? grounds of our fishery resources. Healthy and good vegetation of this area may lead to
the development of tourism in the Municipality thus establishing employment in the
area.
E. Target beneficiaries Community around the mangrove areas
F. Target Output / Success Indicator : Increase area of Mangrove
: Increase mangrove species inventory
: Reverted unproductive fishponds with FLA to mangrove area
G. Possible Risks : Lack of funds
: Lack of political will
: Incoordination of community stakeholders
H. Expected Private Sector Response Possibility for a Partnership with various CSOs, POs, and NGOs
68 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
69 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to March 2026 (3 months) - creation of the program and the implementing
body
: April 2026 to December 2028 (2 years and 9 months) - program implementation
Requirements needed to be done to produce Legal action to form the program and the implementing body thru an ordinance
the desired output
: Creation of the program and of the implementing body thru an ordinance
Steps or procedure of the project : Program implementation - conservation of rivers in Pinamalayan
Implementing Arm Municipal Government of Pinamalayan - MDRRMO; MENRO; DENR
Monitoring and Evaluation personnel/group Municipal Planning and Development Office (MPDO)
Frequency of monitoring and evaluation Monthly and Quarterly Monitoring>Evaluation at the start, at the middle and at the end
of the project.
Materials
Human Resources (Labor)
Estimated
Equipment
Costs
Others
TOTAL Php 50,000,000.00
Funding Source General Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/Objective derived from the By 2028, enhanced conservation and sustainable utilization of water resources
CLUP/CDP
Major Problem/s being addressed Increased marine pollution
What are the effects of the project to social Social impact: Improved overall well-being of communities living near rivers.
and economic activities? And in what Economic impact: This project can help increase economic income since more
locations? investors will become interested due to the improved marine environment.
E. Target Beneficiaries The beneficiaries of this project are all the constituents of Pinamalayan, especially
those living near rivers.
F. Target Output/Success Indicator : Decrease in marine pollution
: Improved water quality of rivers
G. Possible Risks Lack of funding and political will
H. Expected Private Sector Response Possibility of partnership with the private sector regarding the implementation of the
river protection program.
70 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to June 2019 (6 months) preparation of project proposal and other
documents and coordination to concern agency
: July to December 2019 (6 months) project implementation
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
71 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
72 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
73 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to April 2019 (4 months) preparation of project proposal and other
documents and coordination to concern agency (DA)
: May 2019 to December 2020 (1 year and 8 months) establishment of tree nursery
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
74 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : July to September 2019 procurement of materials and feasibility study
: October to June 2020 (6 months) – construction of facility
: July 2020 – 2021 maintenance of the facility
Requirements needed to be done to produce : Construction of a wildlife rescue center
the desired output : Procurement of supplies and facilities/cages
: Procurement of wildlife species
: Hiring of a caretaker
: Hiring of a veterinarian
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Costs Materials Php 1,000,000.00
Human Resources (Labor) 500,000.00
Equipment 300,000.00
Others 500,000.00
TOTAL Php 2,300,000.00
Funding Source LGU General Fund
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP Establishment of wildlife rescue facility that help improve and sustain biodiversity in
the municipality
Major Problem being addressed : Depletion of biodiversity
: Ecological imbalance
What are the effects of the project to social and This would ensure a diversified and abundant biodiversity in the municipality,
economic activities? And in what locations?
E. Target beneficiaries Barangays
F. Target Output / Success Indicator : Increase awareness on the different flora and fauna
: Additional income for the POs,
: Increase in biodiversity
G. Possible Risks : Lack of funds
: Lack of political will
H. Expected Private Sector Response Possibility for a Partnership with various CSOs, POs, and NGOs regarding the
breeding of exotic flora and fauna
75 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
76 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Requirements needed to be done to produce the : Feasibility study
desired output : Site validation
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the
project
Materials Php 1,740,000.00
Human Resources (Labor) 1,160,000.00
Estimated Costs Equipment 100,000.00
Others 6,000,000.00
TOTAL Php 9,000,000.00
Funding Source 20% DF
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP Since our existing public spaces/recreational areas has limited capacity it is but
necessary to find other locations and improve its ammenities for the leisure of
our constituents.
Major Problem being addressed Recreational Facility for the inhabitants of Pinamalayan
What are the effects of the project to social and Public spaces and/or recreational parks if properly manage will have a possitive
economic activities? And in what locations? effect socially and somehow contributing factor to attract immigration which will
help in the investment industry.
E. Target beneficiaries LGU’s inhabitants
F. Target Output / Success Indicator Well spacing recreational facility/public leisure areas
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possible Public-Private partnership
77 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
SOCIAL SECTOR
78 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
79 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Steps or procedure of the project : Installation of basic amenities (water system, electric system)
: Construction of recreational areas
: Roadways, drainage canal
Implementing Arm Municipal Engineering Office, MSWDO
Monitoring and Evaluation personnel/group Municipal Planning and Development Office
80 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
81 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
82 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
83 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
84 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
C.2.1 Phasing and Timeline : Preparation of Program of Works (POWs) and Plans
- January 2022
: Project Implementation
- Upgrading of Pinamalayan Gymnasium
- March-May,2022
: Project Monitoring and Evaluation
- May-December 2022
Proponents : Procurement of materials of the above stated proposed project
: Feasibility study
Program Term Municipal Engineering Office
Steps or procedure of the project : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 11,000,000.00
Human Resources (Labor) 6,000,000.00
Estimated
Costs Equipment 3,000,000.00
Others
TOTAL Php 20,000,000.00
Funding Source General Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from The proposed project calls for the rehabilitation of Municipal Park and Playground, and
CLUP/CDP will include repair of perimeter fence in the pathways, repair of children’s playground
and repainting. Implementation of said project will inject new energy into the people. It
will serve as a both leisure and pleasure activities for the local residents while at the
same time encouraging physical activity and social interaction.
Major Problem being addressed Repair of park and playground
What are the effects of the project to social A well-planned public recreational space could make an enormous difference to our
and economic activities? And in what lives and it encourages local residents of all ages to maintain a healthy lifestyle close to
locations? home without added financial strain.
E. Target beneficiaries All residents of Pinamalayan
F. Target Output / Success Indicator Proposed project completed on the period of duration.
G. Possible Risks To effectively manage the risks in construction projects, it is necessary for the Project
management/implementers to identify important risk and to provide a tool to measure
their effects. In addition, it is very important to take into consideration the external
environment which is outside people’s control which is the weather patterns and its
changing effects due to climate change, the un-seasonal or excessive wet weather. Due
to this type of risk projects are being hampered by inclement weather, bringing some
construction projects to a halt and delaying their supposed target completion and
sometimes fallen slightly behind schedule. Conclusively, during the construction phase,
85 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
H. Expected Private Sector Response This will have a positive response from the private sectors since they will also be
benefitted for this proposed project.
86 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
The LGU will construct housing units wherein interested applicants may apply to avail
the unit through housing loan with a duration of 15 years.
B. Location of the project Proposed location are Guinhawa, Pili, Sta. Isabel, Cacawan, Papandayan and
Pambisan Munti
C. Program Components : Acquisition of 5 ha of Lot
: Construction of 100 Socialized Housing units
Proponents MSWDO
Program Term 2019-2028
87 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
88 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
89 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline 2019: Crisis Center, Reception & study center, PDAO, and LCW
2020: MSWDO
2025: Home for the Aged and Senior Citizen Office
Requirements needed to be done to Acquisition of 5 hectares of land
produce the desired output
90 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
91 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials
Human Resources (Labor)
Estimated Equipment
Costs
Others
TOTAL Php 35,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP The Upgrading of Pinamalayan Gymnasium is the proposed project of the Municipality
of Pinamalayan. The present structure used for some events but it really needs to be
upgraded to provide accommodation and convenience to big events. The Municipality
of Pinamalayan presently utilized the existing Pinamalayan Gymnasium as the
municipal venue for holding of event or activities of massive participation and
attendance. Once upgraded it can accommodate several number of people. The need
92 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
93 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Steps or procedure of the project : Procurement of medical equipment, office furniture, logistic supplies, test kits
: Training/seminar/IEC to the access of Social Hygiene Clinic
Implementing Arm MHO
Monitoring and Evaluation personnel/group MHO
94 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
95 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
96 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
97 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
98 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 110,000,000.00
Human Resources (Labor) 60,000,000.00
Estimated
Equipment 30,000,000.00
Costs
Others
TOTAL Php 200,000,000.00
Funding Source LGU, PGOM
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP : To establish and implement a Comprehensive Sports Development Program
: To empowered youth to have high regards to community development
: To expand sports and recreation-related facilities
Major Problem being addressed Absence of modern sports complex to cater major sport activities
What are the effects of the project to social Youth empowerment with an active life and a brighter future ahead. Eventually the
and economic activities? And in what program will increase its economic status and its sustainability as an income
locations? generating program.
E. Target beneficiaries All Pinamaleño Youth and other municipalities of Oriental Mindoro bridging and
expanding to MIMAROPA Region.
F. Target Output / Success Indicator Modern Sports Complex established
G. Possible Risks To effectively manage the risks in construction projects, it is necessary for the Project
management/implementers to identify important risk and to provide a tool to measure
their effects. In addition to, it is very important to take into consideration the external
environment which is outside people’s control which is the weather patterns and its
changing effects due to climate change, the un-seasonal or excessive wet weather.
Due to this type of risk projects are being hampered by inclement weather, bringing
some construction projects to a halt and delaying their supposed target completion
and sometimes fallen slightly behind schedule. Conclusively, during the construction
phase, safety and health in public works undertakings shall be ensured at all times
H. Expected Private Sector Response This will have a positive response from the private sectors since they will also be
99 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
100 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
101 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
102 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
103 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Steps or procedure of the project : Justification for acquisition of additional unit of ambulance
: Hiring of ambulance driver
Implementing Arm MHO
Monitoring and Evaluation personnel/group MHO
104 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
105 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
106 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
107 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
108 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
109 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
110 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
111 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
112 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
113 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
S32 | E-Eskwela
Name of Project E-ESKWELA
A. Brief Description The project aims “to provide disadvantaged youth with useful educational
opportunities to help reduce the digital divide and enhance their capacity to be
successful participants in a global and knowledge-based economy.” A center
equipped with computer units, printers, and projectors to be located at ALS learning
center (Juan Morente Compound)
B. Location of the project ALS Learning Center, Juan Morente Compound
C. Program Components Customized Instruction Models
Attendance to Training of Trainors
Stakeholders Training
Proponents ALS/LGU
Program Term 2019-2028
114 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
115 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
116 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
S21 | Construction of Local Council for Women Office with Multi-Purpose Hall
Name of Project CONSTRUCTION OF LOCAL COUNCIL FOR WOMEN OFFICE WITH MULTI-
PURPOSE HALL
A. Brief Description The project aims to construct the office of the Local Council for Women for its
operations with Multi-purpose hall built for livelihood training program. The propose
project is measuring 24m x 40m.
B. Location of the project Sta. Rita
C. Program Components : Pre-Implementation Phase
- Site Investigation and Engineering Survey
- Preparation of Plan and Detailed Engineering Design, Program of Works
and Cost Estimates
- Procurement Process – Possible source of materials, Local Suppliers and
or Suppliers from other Locality
: Implementation Phase
- Construction of Office and Multi-Purpose Hall
- Lay Stakeout and Excavation for foundation of footing, column and CHB
wallings
- Masonry Works, Carpentry Works
- Doors and windows, Tinsmithry, such as roof framing, and ceiling
: Post-Implementation Phase
- Monthly monitoring and monthly submission of report
Proponents Local Council for Women
Program Term 2020-2021
117 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
118 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
119 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
120 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
121 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
122 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
123 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
ECONOMIC SECTOR
124 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
125 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring must be periodic but not less than twice per month
: Evaluation must be at the start, middle and completion of the project
Estimated Materials Php 26,250,000.00
Cost Human Resources (Labor) 21,000,000.00
Equipment 262,250,000.00
Others 31,500,000.00
TOTAL Php 105,000,000.00
Funding Source GENERAL FUND
Is the Project expected to be financially self- NO
sustaining?
D. Justification of the Project
Rationale/Objective derived from CLP/CDP Address expansion needs of the public enterprise as well as its revenue generating
capacity
Major Problem being addressed : LGU revenue generation/local fiscal management
: Congestion of the present market facilities to the growing needs of investors
What are the effects of the project to social Primarily, this would generate needed income for the LGU, open opportunities for new
and economic activities? And in what locators, investors and convenience to other/ all stakeholders
locations?
E. Target beneficiaries Local businessmen, locators, new investors, market goers and the general public
F. Target Output/Success Indicator : Decreased occupants of market alleys and market roads
: Decongested market facilities
G. Possible Risks : Lack of funds
: Political will
H. Expected Private Sector Response Possibility for a PPP scheme
126 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring must be periodic but not less than twice a month
: Evaluation must be at the start, middle and completion of the project
Materials Php 55,000,000.00
Human Resources(Labor) 44,000,000.00
Estimated
Equipment 55,000,000.00
Cost
Others 66,000,000.00
TOTAL Php 220,000,000.00
Funding Source GENERAL FUND
Is the Project expected to be financially self- NO
sustaining?
D. Justification of the Project
Rationale/Objective derived from CLP/CDP Address expansion needs of the public enterprise as well as its revenue generating
capacity
Major Problem being addressed : LGU revenue generation/local fiscal management
: Congestion of the present market facilities to the growing needs of investors
What are the effects of the project to social Primarily, this would put things in proper order, generate needed income for the LGU,
and economic activities? And in what opportunities for new locators, investors and convenience to other/ all stakeholders
locations?
E. Target beneficiaries Local businessmen, locators, new investors, market-goers and the general public
F. Target Output/Success Indicator : Decreased occupants of market alleys and market roads
: Decongested market facilities
G. Possible Risks : Lack of funds
: Weak Political will
H. Expected Private Sector Response Possibility for a PPP scheme
127 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
128 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
: Implementation Phase
- Clearing/Cleaning up
- Construction of necessary structures for existing tourism areas
- Intensify IEC for tourism promotion
- Monitoring and Maintenance
Proponents LGU Pinamalayan
Program Term 2019-2028
129 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
130 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
131 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
132 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
133 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline February to March 2019 (2 months) preparation of project proposal and documents for
the purchase of inputs
Requirements needed to be done to : April to May 2019 (2 months) training and purchase of inputs
produce the desired output : June to December 2019 implementation, monitoring and evaluation
: Same activities for the succeeding years
134 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to July 2020 (6 months) preparation of project proposal and other documents
and coordination with DA
: August to December 2020 (5 months) acquisition of materials and establishment of
facility
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
135 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
EC9 | Crop Development Program
Name of Project CROP DEVELOPMENT PROGRAM
A. Brief Description Abaca Production Development
B. Location of the Project Upland areas of the municipality
C. Program Components : Procurement of abaca planting materials (suckers)
: Procurement of abaca fiber extraction machines and equipment
Proponents Municipal Government – MAgO
Program Term 2019 to 2028
Phasing and Timeline : Procurement/Provision of planting materials to abaca farmers, one year (2019)
: Establishment of abaca planting sites, two years (2020-2022)
: Procurement/provision of abaca fiber extraction machines and equipment, one year
(2023)
: Provision of technical assistance to farmers of abaca farmers (trainings/capacity
enhancement, monitoring and evaluation), 6 years (2024-2028)
Requirements needed to be done to Project proposal
produce the desired output
Frequency of monitoring and evaluation : Monitoring will be done upon delivery of planting materials
: Evaluation will be conducted at the start, middle and end of the project
Estimated Cost PhP 10,000,000.00
Funding Source FFS (PhilFIDA)
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/Objective derived from : To contribute to the reduction of rising temperature due to climate change
CLUP/CDP : To increase farmers’ income
Major problem being addressed Lack planting materials, equipment, machineries, facilities and trainings for abaca
growers
What are the effects of the project to social : Will provide additional income to farmers
and economic activities? And in what : Promotion of high value and climate resilient crop
locations?
E. Target beneficiaries Local abaca farmers
F. Target Output / Success Indicator Increased supply of abaca fibers and fiber crafts
G. Possible Risk : Lack of funds or national government assistance
: Least priority of the administration
H. Expected Private Sector Response Possibility for Public-Private Partnership
136 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to December, 2025 (one year) Formulation of SB resolution, feasibility
study/project proposal and engineering measurement activities
: January, 2026 to July, 2027 (1 ½ year) Acquisition of materials,
construction/upgrading of Food Terminal and others
Requirements needed to be done to produce : Project Proposal/Feasibility study
the desired output : Engineering evaluation and measurements
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be conducted at the start, middle and end of the construction
Estimated Cost Php 20,000,000.00 (contracted)
Funding Source FFS (Department of Agriculture)
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/Objective derived from CLUP/CDP To establish linkages with other market outlets and secure marketing contracts
Major problem being addressed : Lack of upgraded facilities for marketing and cold storage of agricultural products
: Least prospect market linkages (traders and consumers)
What are the effects of the project to social : Will provide ease on marketing and storage of agricultural products to producers and
and economic activities? And in what traders thru upgraded Food Terminal facilities
locations? : Centralized trade of agricultural products
: Prices will be regulated
: Post harvest lost will be minimized
: Will provide another source of local revenue
E. Target beneficiaries Local and outside traders of agricultural products
F. Target Output / Success Indicator : Improved exchange of products with other town and provinces
: Lessened post-harvest losses of agricultural products
G. Possible Risk : Lack of fund assistance from National Government
: Support from producers group
H. Expected Private Sector Response Possibility for Public-Private Partnership
137 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to December 2019 (1 year) preparation of project proposal, site and
beneficiary selection
: January to December (2028) project implementation
Requirements needed to be done to : Project proposal
produce the desired output : Fund support
: Community Participation
Frequency of monitoring and evaluation : Monitoring will be done monthly or quarterly/ depends on the type of program or
project
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Cost PhP 15,000,000.00
Funding Source MGDP-GF (BFAR)
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/Objective derived from This project aims to address the need of assistance and help to increase the degraded
CLUP/CDP fishery resources of Municipal Waters of Pinamalayan wherein, it will directly increase
the fishing productivity and uplift the economic stability of fishing communities.
Major problem being addressed Degradation of Fishery Resources and Poverty among Coastal Areas
What are the effects of the project to social : Decrease the poverty and unemployment rate among coastal and fishing communities
and economic activities? And in what : Fishery Resources and production will also increase due to conservation efforts of the
locations? organizations and communities, thus ensure the financial stability and economic
competitiveness of the front line community
E. Target beneficiaries Fisherfolks of Pinamalayan
F. Target Output / Success Indicator : Decreased incidence of illegal fishing
: Increase fish catch and production
: Decrease poverty rate in fishing communities
G. Possible Risk : Lack of funds
: Lack of political will
: Lack of Community participation
H. Expected Private Sector Response Possibility for a Partnership with various CSOs, POs, and NGOs regarding conservation
and fishery sector empowerment
138 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to December 2019 (1 year) preparation of project proposal, site and
beneficiary selection
: January to December (2020) project stablishment
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
: Community Participation
139 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to March 2019 (2 months) preparation of project proposal and documents for
the purchase of piglets
: April to December 2019 (9 months) identification of recipients, procurement of piglets,
project implementation and monitoring and evaluation
Requirements needed to be done to : Selection of prospective recipients
produce the desired output : Project proposal
140 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to June 2019 (7 months) Acquisition of lot, feasibility study, and other
measurement activities
: August 2019 to June 2020 (11 months) Acquisition of materials, construction of
Auction Market Facility, furnishing and others
Requirements needed to be done to produce : Project proposal
the desired output : Engineering evaluation and measurements
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be conducted at the start, middle and end of the project
Human Resource (Labor) Php 40,000,000.00 (contracted)
Estimated Equipment
Cost Others
TOTAL Php 40,000,000.00
Funding Source MGDP-General Fund
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/Objective derived from CLUP/CDP : To expand the market outlet of livestock
: To extend service capacity (holding pen) of slaughter
Major problem being addressed : Lack auction market with holding pen for poultry and livestock
: Dispersed/uncontrolled marketing of animals
What are the effects of the project to social : Will provide convenience marketing of animals to producers and traders thru holding
and economic activities? And in what pen
locations? : Centralized trade for animals
: Prices will be regulated
: Will provide another source of local revenue
E. Target beneficiaries : Local and outside traders of animals
F. Target Output / Success Indicator : Increased supply of farm animals
: Decreased number of traders within prohibited areas
G. Possible Risk : Lack of funds
: Least priority of the administration
H. Expected Private Sector Response Possibility for Public-Private Partnership
141 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline Difficult to identify because said project components depend on availability of funds
Requirements needed to be done to Assessment of the MAssO and Assessment of the MEO
produce the desired output
142 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
143 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : February to July 2019 (6 months) preparation of project proposal and other
documents
: Coordination with Department of Agriculture
: August 2019 -2021 (2 years and 5 months) acquisition of materials, construction of
Multi-Purpose Farmers Training Center facility
Requirements needed to be done to produce Project proposal
the desired output
144 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to June 2019 (6 months) preparation of project proposal and other
documents and coordination with DA
: July to December 2019 (6 months) acquisition of farm machineries, equipment and
identification of recipients
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
145 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
EC24 | Construction of Building (Farmers’ Federation Office, Function Hall and Garage for farm Equipment)
Name of Project CONSTRUCTION OF BUILDING (FARMERS’ FEDERATION OFFICE, FUNCTION
HALL AND GARAGE FOR FARM EQUIPMENT)
A. Brief Description This project is a joint project of LGU and DA for the farmers of Pinamalayan. This
would serve as their official building for proper delivery of services to farmers.
B. Location of the Project Municipality Pinamalayan, Oriental Mindoro
C. Program Components : Construction of Farmers’ Building
: Procurement and installation of mechanical dyer
Proponents Bahaghari Farmers’ Federation
Program Term 3 years (2019 - 2021)
Phasing and Timeline : January to April 2019 (4 months) preparation of project proposal and other
documents and coordination to concern agency (DA)
: May to December 2021 (2 years and 8 months) acquisition of materials and
construction of Farmers’ Building
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
146 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to December 2019 (1 year) preparation of project proposal, site and
beneficiary selection
: January to December (2020) project establishment
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
: Community Participation
147 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to July 2020 (6 months) preparation of project proposal and other documents
and coordination with DA
: August to December 2020 (5 months) acquisition of materials and establishment of
facility
Requirements needed to be done to produce : Project proposal
the desired output : Fund support
148 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
: Remains to be a major thoroughfare where public conveyance may still ply the
same route on a “pick-and-drop” basis
H. Expected Private Sector Response : Increase more investments from private sector
149 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 275,000.00
Costs Human Resources(Labor) 150,000.00
Equipment 75,000.00
Others
TOTAL Php 500,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP
Major Problem being addressed Currently, the Manpower Development Center caters only limited number of people
for various events. With this project, MDC will be able to serve large number of
participants.
What are the effects of the project to social and This will increase the economic growth of locality and improve the events center for
economic activities? And in what locations? the people of Pinamalayan.
E. Target beneficiaries Municipal Employees and Clients
F. Target Output / Success Indicator to complete the project from the period of duration
150 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
151 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 825,000.00
Costs Human Resources(Labor) 450,000.00
Equipment 225,000.00
Others
TOTAL Php 1,500,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP To rehabilitate 426.8 linear meters of perimeter fence inside the Municipal
Compound of Pinamalayan
Major Problem being addressed Security of the municipal compound, its properties, and the employees working in
the municipal government
What are the effects of the project to social and This would improve the safety and welfare of the people in the municipality
economic activities? And in what locations?
E. Target beneficiaries : Municipal Employees and Clients
152 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
153 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
154 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 3,000,000.00
Costs Human Resources (Labor) 900,000.00
Equipment 1,100,000.00
Others 500,000.00
TOTAL Php 5,500,000.00
Funding Source General Fund/FFS (For Funding Source)
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
Rationale/ Objective derived from To establish a new public memorial park by 2022
CLUP/CDP
Major Problem being addressed Burial ground for the LGU as the old cemetery is already congested
What are the effects of the project to social This will serve as another source of income for the municipality
and economic activities? And in what
locations?
E. Target beneficiaries Residents within Pinamalayan and nearby municipalities
F. Target Output / Success Indicator The cemetery will be established by year 2022
G. Possible Risks Lack of funding
H. Expected Private Sector Response This might elicit positive response since all existing cemeteries are nearing full capacity
or have been closed.
155 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
156 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 110,000,000.00
Costs Human Resources (Labor) 60,000,000.00
Equipment 30,000,000.00
Others
TOTAL Php 200,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Construction of a seawall requires quality materials, advanced technology, and
CLUP/CDP experienced craftsmanship to prevent erosion and withstand strong winds and high
waves. We encourage the installation of vinyl seawalls over conventional materials for
increased longevity and environmental protection.
Major Problem being addressed wave erosion and threatened by shoreline recession particularly during and storm
events.
What are the effects of the project to social : Reduced recreational beach amenity
and economic activities? And in what : reduced public access to beaches
locations? : public safety risks from the seawall, including effects of wave overtopping due to
smooth and hard structures
: benefits through erosion protection of property located landward of the seawall
: potential benefits through provision of additional, improved or more secure public
recreational space landward of the seawall, which could be integrated with recreational
facilities, for example, a cycleway.
E. Target beneficiaries residents of Zone I to Quinabigan
157 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
158 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials PHP 27,500,000.00
Costs Human Resources (Labor) 15,000,000.00
Equipment 7,500,000.00
Others
TOTAL Php 50,000,000.00 (2019-2020)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from To ensure stable and adequate supply to service growing demand
CLUP/CDP
Major Problem being addressed : Inadequate utility service
: Heavy power draw in area / facility
: Poor electrical circuit design
: Overheating and stress on equipment
What are the effects of the project to social : Comfortable working condition between the clients and the government employees
and economic activities? And in what : Fast and efficient service to the clients
159 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
160 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 27,500,000.00
Human Resources(Labor) 15,000,000.00
Equipment 7,500,000.00
Others
TOTAL Php 50,000,000.00 (2022)
Estimated
Costs Materials Php 27,500,000.00
Human Resources(Labor) 15,000,000.00
Equipment 7,500,000.00
Others
TOTAL Php 50,000,000.00 (2026)
Materials Php 27,500,000.00
161 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
162 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
IF32 | Construction of Lumambayan bridges I, II, III, and Macanlig Bridge in Sta. Isabel
Name of Project CONSTRUCTION OF LUMAMBAYAN BRIDGE I, II, III AND IN BRGY. STA. ISABEL
A. Brief Description : 2022 - Construction of Lumambayan Bridge I (L=30m, W=6m) Bridge II ( 60m , W=6m)
Bridge III ( L=30m, W=6m) and in Brgy. Sta.Isabel Bridge ( L=10m, W=3.6m)
: 2026 - Construction of Lumambayan Bridge I (L=30m, W=6m) Bridge II ( 60m , W=6m)
Bridge III ( L=30m, W=6m) and in Brgy. Sta.Isabel Bridge ( L=10m, W=3.6m)
: 2028 - Construction of Lumambayan Bridge I (L=30m, W=6m) Bridge II ( 60m , W=6m)
Bridge III ( L=30m, W=6m) and in Brgy. Sta.Isabel Bridge ( L=10m, W=3.6m)
B. Location of the project Brgy. Lumambayan and Brgy. Sta. Isabel
C. Program Components 1.Pre-Implementation Phase
a. Site Investigation and Engineering Survey
b. Preparation of Plan and Detailed Engineering Design,
Program of Works and Cost Estimates
c. Procurement Process – Possible source of materials, Local
Suppliers and or Suppliers from other Locality
2. Implementation Phase
a. Construction of Lumambayan Bridge I, II, III; and in Brgy.
Sta. Isabel
3. Post-Implementation Phase
a. Monthly monitoring and monthly submission of report
Proponents : Municipal Government - MEO
Program Term 2022, 2026, 2028
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 57,200,000.00
Human Resources(Labor) 31,200,000.00
Equipment 15,600,000.00
Others
Estimated
TOTAL Php 104,000,000.00 (2022)
Costs
Materials 23,650,000.00
Human Resources (Labor) 12,900,000.00
Equipment 6,450,000.00
Others
163 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Name of Project CONSTRUCTION OF LUMAMBAYAN BRIDGE I, II, III AND IN BRGY. STA. ISABEL
TOTAL Php 43,000,000.00 (2026)
Materials Php 23,650,000.00
Human Resources (Labor) 12,900,000.00
Equipment 6,450,000.00
Others
TOTAL Php 43,000,000.00 (2028)
GRAND TOTAL PHP 190,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from The proposed project will surely help the residents for easy access of goods and basic
CLUP/CDP services
Major Problem being addressed bridge cannot be passed due to heavy floods during rainy season
What are the effects of the project to social Improve bridge crossing, improved access to the community, improve vehicle and
and economic activities? And in what pedestrian safety and access
locations?
E. Target beneficiaries Residents of Lumambayan and Sta.Isabel and other nearest barangays and general
public passers by
F. Target Output / Success Indicator Proposed project will be completed from the period of duration
G. Possible Risks The weather condition and natural calamities are considered as major risks that could
cause delay in the implementation. This may cause undue delay for project duration and
completion
H. Expected Private Sector Response An absolute positive response is expected since this will not only benefit the people and
the community but it will also contribute to the socio-economic development of the area
164 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 2,750,000.00
Costs Human Resources (Labor) 1,500,00.00
Equipment 750,000.00
Others
TOTAL Php 5,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Irrigation has contributed significantly to poverty alleviation, food security, and improving
CLUP/CDP the quality of life for rural populations. However, the sustainability of irrigated agriculture
is being questioned, both economically and environmentally. It is essential that irrigation
projects be planned and managed in the context of overall river basin and municipal
development plans.
Major Problem being addressed : Failure to achieve water equitable distribution of water and environmental factors
related to soil salinity, water logging, and public health.
What are the effects of the project to social : To help grow agricultural crops, maintain landscapes, and revegetate disturbed soils in
and economic activities? And in what dry areas and during periods of less than average rain fall.
locations?
E. Target beneficiaries The target beneficiaries of this projects are the residents of the rural area of this
municipality
F. Target Output / Success Indicator : increase in irrigated area
165 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
166 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 84,700,000.00
Human Resources (Labor) 46,200,000.00
Equipment 23,100,000.00
Estimated
Others 2,000,000.00 (Consultant Services and Deliverables)
Costs
TOTAL Php 154,000,000.00 (2020)
Materials 53,900,000.00
Human Resources (Labor) 29,400,000.00
Equipment 14,700,000.00
167 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
168 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
169 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
IF15 | Construction of Drainage Canal with Curb, Gutter and Box Culvert
Name of Project CONSTRUCTION OF DRAINAGE CANAL WITH CURB AND GUTTER (BOX
CULVERT)
A. Brief Description By 2022 - 200.5 linear meters of drainage canal with curb and gutter with box culvert
constructed amounting to P 3,000,000.00
B. Location of the project Cor. Francisco St. and Quezon St., Pinamalayan, Or. Mindoro
C. Program Components 1. Pre-Implementation Phase
a. Site Investigation and Engineering Survey
b. Preparation of Plan and Detailed Engineering Design, Program
of Works and Cost Estimates
c. Procurement Process – Possible source of materials, Local
Suppliers and or Suppliers from other Locality
2. Implementation Phase
a. Construction of Drainage Canal with Curb and Gutter (Box
Culvert)
3. Post-Implementation Phase
a. Monthly monitoring and monthly submission of report
Proponents Municipal Government - MEO
Program Term 2019-2022
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 1,650,000.00
Costs Human Resources (Labor) 900,000.00
Equipment 450,000.00
Others
TOTAL Php 3,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Flooding is the most significant problem identified during the rainy seasons and it
CLUP/CDP causes property damages, interruption to the public health and mobility. Incapacity of a
well -built drainage system is the major cause of the problem occurrence. Once the
rainy season begins, problem of flooding will begin concurrently as well. Even though a
drainage system is existed in certain areas, it is not functional due to several reasons
such as lack of engineering, incomplete network.
Major Problem being addressed Flooded area
What are the effects of the project to social Flood free road networks and better drainage systems
and economic activities? And in what
170 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Name of Project CONSTRUCTION OF DRAINAGE CANAL WITH CURB AND GUTTER (BOX
CULVERT)
locations?
E. Target beneficiaries All residents of Poblacion area and business sectors, commuters, transport groups, and consumers.
F. Target Output / Success Indicator Minimized Health Hazard: Threats from mosquito breeding grounds and contamination
water due to sewage and solid waste are minimized. Damages to roads and building is
prevented as the flooding is reduced.
G. Possible Risks : To effectively manage the risks in construction projects, it is necessary for the Project
management/implementers to identify important risk and to provide a tool to measure
their effects.
: In addition to, it is very important to take into consideration the external environment
which is outside people’s control which is the weather patterns and its changing effects
due to climate change, the un-seasonal or excessive wet weather. Due to this type of
risk projects are being hampered by inclement weather, bringing some construction
projects to a halt and delaying their supposed target completion and sometimes fallen
slightly behind schedule.
: Another factor to consider is the traffic accidents in road construction site, hence it is
necessary to install road safety sign and knowledgeable flagmen for the smooth flow of
traffic in the project site. Continuous monitoring and integrations of new technologies
such as a good traffic light system would provide a better and safer direction to both the
contractor and public. Conclusively, during the construction phase, safety and health in
public works undertakings shall be ensured at all times.
H. Expected Private Sector Response This will have a positive response from the private sectors since they will also be
benefitted from the improved and maintained roads.
171 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials Php 195,250.00
Costs Human Resources (Labor) 106,500.00
Equipment 53,250.00
Others
TOTAL 355,000.00 (2022)
Materials Php 390,500.00
Human Resources (Labor) 213,000.00
Equipment 106,500.00
Others
TOTAL Php 710,000.00 (2026)
172 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
173 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 23,100,000.00
Human Resources (Labor) 12,600,000.00
Equipment 6,300,000.00
Others
Estimated TOTAL Php 42,000,000.00 (2022)
Costs Materials 46,200,000.00
Human Resources (Labor) 25,200,000.00
Equipment 12,600,000.00
Others
TOTAL Php 84,000,000.00(2026)
Materials 69,000,000.00
Human Resources (Labor) 37,800,000.00
174 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
175 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 19,250,000.00
Human Resources (Labor) 10,500,000.00
Equipment 5,250,000.00
Estimated Others
Costs TOTAL Php 35,000,000.00 (2022)
Materials 19,250,000.00
Human Resources (Labor) 10,500,000.00
Equipment 5,250,000.00
Others
176 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
177 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 11,000,000.00
Human Resources (Labor) 6,000,000.00
Equipment 3,000,000.00
Others
TOTAL Php 20,000,000.00 (2022)
Estimated
Materials Php 11,000,000.00
Costs
Human Resources (Labor) 6,000,000.00
Equipment 3,000,000.00
Others
TOTAL Php 20,000,000.00 (2026)
Materials Php 11,000,000.00
178 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
179 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 27,500,000.00
Human Resources(Labor) 15,000,000.00
Estimated
Equipment 7,500,000.00
Costs
Others
TOTAL Php 50,000,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from The program supports the efforts of municipality to increase economic activities and
CLUP/CDP improve public access to infrastructure and services through a participatory process,
involving various community stakeholders from the private and business sectors,
national government agencies, provincial government as well as key municipal
government department and offices.
Major Problem being addressed Displacement of tribal people, loss of non-forest land, landslides, sedimentation and
siltation occurs, stagnation and water logging round reservoirs retards plant growth,
breeding of vectors and vector borne diseases, Reservoir Induced Seismicity (RIS)
causes earthquakes, navigation and aquaculture can be developed in the dam area.
What are the effects of the project to social : Dams are built to control flood and store flood water
180 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
181 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 11,000,000.00
Human Resources (Labor) 6,000,000.00
Equipment 3,000,000.00
Others
Estimated TOTAL Php 20,000,000.00 (2022)
Costs Materials Php 22,000,000.00
Human Resources (Labor) 12,000,000.00
Equipment 6,000,000.00
Others
TOTAL Php 40,000,000.00 (2026)
Materials Php 5,500,000.00
182 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
What are the effects of the project to social : Social effects are the Mobility benefits, Rising land value, Improved quality of Life while
and economic activities? And in what on Economic benefits are Less Cost, Wider reach to business, Better and Diverse
locations? products and Increased Competition
: Constituents of Pinamalayan
E. Target beneficiaries Constituents of Pinamalayan and general public
F. Target Output / Success Indicator 2 kilometers of roads opened from Cacawan to Sta. Rita Evacuation Center
G. Possible Risks : To effectively manage the risks in construction projects, it is necessary for the Project
management/implementers to identify important risk and to provide a tool to measure
their effects
: In addition to, it is very important to take into consideration the external environment
which is outside people’s control which is the weather patterns and its changing effects
due to climate change, the un-seasonal or excessive wet weather. Due to this type of
risk projects are being hampered by inclement weather, bringing some construction
projects to a halt and delaying their supposed target completion and sometimes fallen
slightly behind schedule. Conclusively, during the construction phase, safety and health
in public works undertakings shall be ensured at all times.
H. Expected Private Sector Response : This will have a positive response from the private sectors since they will also be
benefitted for the upgraded of drainage canal.
183 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimate Materials Php 550,000.00
d Costs Human Resources (Labor) 300,000.00
Equipment 150,000.00
Others
TOTAL Php 1,000,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from To promote the Municipality’s image, identity, sense of place, and to foster civic pride.
CLUP/CDP
Major Problem being addressed Lack of lightnings to the area that caused vehicular accidents to the
motorists
What are the effects of the project to social : Tourist attraction and safety for travelers passes by
and economic activities? And in what : Marfrancisco Triangle, Pinamalayan
locations?
E. Target beneficiaries Tourists and all residents of Pinamalayan
F. Target Output / Success Indicator : Proposed project will completed as scheduled
G. Possible Risks :To effectively manage the risks in construction projects, it is necessary for the Project
184 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
185 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials
Human Resources (Labor)
Estimated
Equipment
Costs
Others
TOTAL 5,000,000.00
Funding Source General Fund
Is the Project expected to be financially self- Yes
sustaining?
D. Justification of the Project
186 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Major Problem being addressed : To avoid clogging of public pavements and roads within the vicinity of the public
market and other identified areas.
: To provide a more reliable and organized approach in the commuting system and
traffic management system.
: To monitor public places that need monitoring and protection.
: To provide comfort for commuters in terms of physiological needs and social needs all
in one area.
What are the effects of the project to social : Provide safety and security to the public as they commute in and out the town proper
and economic activities? And in what of Pinamalayan.
locations? : Increase satisfaction of operators, drivers and commuters in terms of a safer public
transportation system.
: Provide a much more organized system for public transportation that will benefit not
only the operators and drivers but also the commuters. A one stop and go for
commuters to avoid clogging of identified areas that will in turn lead to better
accommodation of other business establishments to boost their profit.
E. Target beneficiaries Constituents of Municipal Government of Pinamalayan
F. Target Output / Success Indicator : Total no. of gang seaters for the comfort of commuters.
: Total no. of social desks for the well-being of commuters.
: Total no. of CCTV cameras and monitoring system for the safety of commuters.
: Public comfort rooms created.
: Public address systems installed.
G. Possible Risks Availability of the fund
H. Expected Private Sector Response Most of the residents of Pinamalayan commute to wherever they want to go on a daily
basis may it be for school, business, work or other individual reasons. Therefore, the
establishment of Tricycle for Hire Terminal will definitely gain positive responses from
the private sector. Aside from providing an organized terminal for the benefit of all
concerned, it will also provide a wide opportunity for businesses to boost their profit due
to better access of customers to their establishments by means of unclogged
pavements and roads. A better-established public transportation system for tricycle
operators will also serve a better purpose to all private sectors in avoiding unfair
distribution of service to the public.
187 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 8,250,000.00
Human Resources (Labor) 4,500,000.00
Estimated
Equipment 2,250,000.00
Costs
Others
TOTAL Php 15,000,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from Street lighting is a situational crime prevention measure that focuses on reducing
CLUP/CDP opportunity and increasing risk through modification of the physical environment. It
strengthens informal social control and community cohesion through the promotion of
social interaction and investment in neighborhood infrastructure.
Major Problem being addressed Poor lightning system
What are the effects of the project to social : Improved lighting deters potential offenders by increasing the risk that they will be
and economic activities? And in what seen or recognized when committing crimes.
locations? : Police become more visible, thus leading to a decision to desist from crime.
188 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
189 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Monitoring will be done once every month
Evaluation will be conducted at the start, middle, and end of the project
Materials
Human Resources (Labor)
Estimated
Equipment
Costs
Others
TOTAL Php 1,330,000.00
Funding Source National Government
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from : Warning Signs and Regulatory Signs, make a crucial instrument to safety of motorist
CLUP/CDP and travelers. Lack of Warning Signs and Regulatory Signs significantly increases
accident rates and property lost.
: To develop and bring benefits to road users through safe and comfort travel. For these
benefits to be sustained, Warning Signs and Regulatory Signs must be in its proper
place and must be well maintained.
Major Problem being addressed This can help reduce the occurrence of accidents along the SRNH, especially that there
is a rising trend of reported accidents in recent years.
What are the effects of the project to social : Improved and safe access to travelers and passersby.
and economic activities? And in what : Improvements in health leading to more safe and productive days of different
locations? workforce.
E. Target beneficiaries All commuters of the Municipality of Pinamalayan and the travelling public.
F. Target Output / Success Indicator Reduced incidences of road accidents
G. Possible Risks Sub-allotment Release Order, Lacking of Documents, Weather Condition
H. Expected Private Sector Response To create a safe and better living condition in the community we live in.
190 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
IF4 | Construction of dropped curb at pedestrian crossing and at the end of walkways of access roads
Name of Project CONSTRUCTION OF DROPPED CURB AT PEDESTRIAN CROSSING AND AT THE
END OF THE WALKWAYS OF ACCESS ROADS
A. Brief Description 2022: Additional ramp for PWD, Provision of Pedestrian Lane (white paint), Removal of
Island for the Pedestrian Lane and Provision of Signage for the Pedestrian Lane and
PWD.
B. Location of the project Along Madrid Blvd., Pinamalayan, Oriental Mindoro
C. Program Components 1.Pre-Implementation Phase
a. Site Investigation and Engineering Survey
b. Preparation of Plan and Detailed Engineering Design, Program
of Works and Cost Estimates
c. Procurement Process – Possible source of materials, Local
Suppliers and or Suppliers from other Locality
2. Implementation Phase
a. Construction of Dropped Curb at Pedestrian Crossing and at the
end of the walkways of access roads
3. Post-Implementation Phase
a. Monthly monitoring and monthly submission of report
Proponents Municipal Government - MEO
Program Term 2022
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials Php 330,000.00
Human Resources (Labor) 180,000.00
Estimated
Equipment 90,000.00
Costs
Others
TOTAL Php 600,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP : To improve conditions for people who are currently walking (including improved
accessibility to sidewalk facilities for pedestrians with disabilities)
: To increase levels of walking
: To reduce the number of crashes involving pedestrians.
Major Problem being addressed Lack of safe infrastructure for pedestrians and inadequate visibility of pedestrians
What are the effects of the project to social : Improved dropped curb facilities for pedestrians.
and economic activities? And in what : Reduced pedestrian crashes.
locations? : along Madrid Blvd.
E. Target beneficiaries Constituents of the Municipality of Pinamalayan
F. Target Output / Success Indicator Achieving a sustainable infrastructure project is a key to poverty alleviation.
Furthermore, community organizing and the active participation of beneficiaries and
other stakeholders in various activities during project implementation can encourage
sustainability in the realization of the project. For the sustainability of the project, the
Municipal Local Government Unit thru the Municipal Engineering Office shall ensure
that Detailed Engineering Design and Specifications are carefully followed.
191 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
192 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Proponents DPWH
Program Term 2019-2028
193 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
194 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
195 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
196 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 109,505,000.00
Human Resources (Labor) PHP 59,730,000.00
Equipment PHP 29,865,000.00
Others
TOTAL PHP 199,100,000.00 (2022)
Materials PHP 54,752,500.00
Estimated Human Resources (Labor) PHP 29,865,000.00
Costs Equipment PHP 14,932,500.00
Others
TOTAL PHP 99,550,000.00 (2026)
Materials PHP 32,851,500.00
Human Resources (Labor) PHP 17,919,000.00
Equipment PHP 8,959,500.00
Others
197 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
198 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : 2020- invitation of supplier, orientation, project briefing, processing of papers
: 2020-2021 establishment/construction
Frequency of monitoring and evaluation : Monitoring will be done twice every month
: Evaluation will be done every 30% accomplishment and at the end of the project
199 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 385,000.00
Human Resources (Labor) PHP 210,000.00
Estimated Equipment PHP 105,000.00
Costs Others
TOTAL Php 700,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP In line with the National Government’s thrusts and the LGU’s goal of poverty reduction
through more improved infrastructure, the main objective of the project is to create a
more conducive and business-friendly environment within the Poblacion area, thus,
encourage the growth of entrepreneurial activities that will help reduce the rate of
poverty incidence.
Major Problem being addressed Flooded area
What are the effects of the project to social Flood free road networks and better drainage systems
and economic activities? And in what
200 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
201 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
: Feasibility Study
Steps or procedure of the project : Procurement of Materials and Equipment
: Project Implementation
: Monitoring and Evaluation
Implementing Arm ORMECO
Monitoring and Evaluation personnel/group ORMECO
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials
Human Resources (Labor)
Estimated Equipment
Costs Others
TOTAL Php 10,835,000.00
Funding Source FFS
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP To increase number of energized sitios as well as to provide electricity to unserved
households
Major Problem being addressed Lack of electricity in some households/barangays in Pinamalayan
What are the effects of the project to social This will provide electricity to some far-flung households/sitios in 21 barangays. Since
and economic activities? And in what power is a necessary utility, this will help residents to live more convenient lives.
locations?
E. Target beneficiaries Residents of the aforementioned 29 sitios in 21 barangays
F. Target Output / Success Indicator : By 2021, 100% of sitios have access to electricity
: By 2024, 70% of unserved households have access to electricity
: By 2028, 90% of unserved households have access to electricity
G. Possible Risks Lack of funding
H. Expected Private Sector Response This will elicit a positive response since provision of power is necessary for daily living
202 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 605,000.00
Human Resources (Labor) PHP 330,000.00
Estimated
Equipment PHP 165,000.00
Costs
Others
TOTAL PHP 1,100,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP The propose project is Upgrading of Drainage Canal that will replace the existing
covered canal within the Poblacion .These existing canals are mostly silted, shallow
and non-functioning during rainy season thus causing floods and stagnant rain water
in the area. Further, these canal causes environment and health hazards to the
community, such as accidents and dengue and/or cholera outbreaks frequently
occurs in the area. This project is part of the Municipal Drainage Plan that’s a
continuing focus of concern of the municipality.
Major Problem being addressed Flooded area
203 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
204 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 2,750,000.00
Human Resources (Labor) PHP 1,500,000.00
Equipment PHP 750,000.00
Others
TOTAL PHP 5,000,000.00 (2022)
Materials PHP 2,750,000.00
Estimated
Human Resources (Labor) PHP 1,500,000.00
Costs
Equipment PHP 750,000.00
Others
TOTAL PHP 5,000,000.00 (2026)
Materials PHP 2,750,000.00
Human Resources (Labor) PHP 1,500,000.00
Equipment PHP 750,000.00
Others
205 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
206 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials PHP 275,000.00
Costs Human Resources (Labor) PHP 150,000.00
Equipment PHP 75,000.00
Others
TOTAL PHP 500,000.00
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP : To enhance inter - and intra – municipal accessibility
: To rehabilitate road shoulder with 151.4 LM x W=3.00M x THk= 0.15M by 2022
Major Problem being addressed Obstruction encroachment
What are the effects of the project to social : Rehabilitation of road shoulder increased road user, pedestrian and cyclist safety.
and economic activities? And in what : Madrid Blvd. along Municipal Compound
locations?
E. Target beneficiaries Constituents of the Municipality of Pinamalayan
F. Target Output / Success Indicator Proposed project will be completed as scheduled
G. Possible Risks : To effectively manage the risks in construction projects, it is necessary for the
207 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
208 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Estimated Materials PHP 22,000,000.00
Costs Human Resources (Labor) PHP 12,000,000.00
Equipment PHP 6,000,000.00
Others
TOTAL PHP 40,000,000.00 (2019 -2022)
Funding Source LGU
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP : Since the existing municipal equipment are already dilapidated and needs huge
amount of money for the repair, it is more advantageous to purchase brand new units
to attend the needs of the LGU, to maintain the infrastructure utilities. There is also a
need to assist each and every barangay in their needs for their developments. These
equipment will also be used during time of calamities and disasters.
: To assist in the construction and maintenance of municipal and barangay projects
Major Problem being addressed Lack of appropriate heavy equipment
What are the effects of the project to social A well-maintained infrastructure utilities and immediate transportation of products
and economic activities? And in what from different barangays through a well-maintained thorough fares.
locations?
E. Target beneficiaries All barangay in this municipality
F. Target Output / Success Indicator Achieving a sustainable infrastructure project is a key to poverty alleviation.
Furthermore, community organizing and the active participation of beneficiaries and
other stakeholders in various activities during project implementation can encourage
209 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
210 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to February 2020-preparation of plans and programs and bidding
: March 2020 to June 2021 is the construction of the project
211 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 55,000,000.00
Human Resources(Labor) PHP 30,000,000.00
Equipment PHP 15,000,000.00
Others
TOTAL PHP 100,000,000.00 (2022)
Estimated Materials PHP 27,500,000.00
Costs Human Resources(Labor) PHP 15,000,000.00
Equipment PHP 7,500,000.00
Others
TOTAL PHP 50,000,000.00( 2026)
Materials PHP 27,500,000.00
212 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
213 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 44,000,000.00
Human Resources(Labor) PHP 24,000,000.00
Estimated Equipment PHP 12,000,000.00
Costs Others
TOTAL PHP 80,000,000.00 (2022)
Materials PHP 27,500,000.00
214 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
215 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
216 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
217 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation : Monitoring will be done once every month
: Evaluation will be conducted at the start, middle, and end of the project
Materials PHP 41,250,000.00
Human Resources (Labor) PHP 22,500,000.00
Equipment PHP 11,250,000.00
Estimated Others
Costs
TOTAL PHP 75, 000,000.00 (2022)
Materials PHP 22,000,000.00
Human Resources (Labor) PHP 12,000,000.00
218 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
219 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
220 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
221 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
IF36 | Construction of Overpass in ABADA College and Nabuslot National High School
Name of Project CONSTRUCTION OF OVERPASS IN ABADA COLLEGE AND NNHS
A. Brief Description The program supports the efforts of municipality to increase economic activities and
improve public access to infrastructure and services through a participatory process,
involving various community stakeholders from the private and business sectors,
national government agencies, provincial government as well as key municipal
government department and offices.
B. Location of the project Brgy. Sta. Rita and Brgy. Nabuslot, Pinamalayan, Oriental Mindoro
C. Program Components 1.Pre-Implementation Phase
a. Site Investigation and Engineering Survey
b. Preparation of Plan and Detailed Engineering Design, Program
of Works and Cost Estimates
c. Procurement Process – Possible source of materials, Local
Suppliers and or Suppliers from other Locality
2. Implementation Phase
a. Construction of Overpass in ABADA College and NNHS
- Excavation, Masonry, Carpentry, Scaffolding, Installation of
Railings
3. Post-Implementation Phase
a. Monthly monitoring and monthly submission of report
Proponents Municipal Government - MEO
Program Term 2022, 2026, 2028
222 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
223 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
INSTITUTIONAL SECTOR
224 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
225 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Monitoring and evaluation will be observed in accordance to existing issuances
Materials : PHP 55,000,000.00
Human Resources (Labor) : PHP 30,000,000.00
Estimated
Equipment (Required Facilities) : PHP 15,000,000.00
Costs
Others
TOTAL PHP 100,000,000.00
Funding Source LGU, PGOM, DILG
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP LGU mandate to provide government facilities and services
Major Problem being addressed Concerns on limited space for employees and consequently affects their productivity.
What are the effects of the project to social : Facilitate easier and faster official public transactions.
and economic activities? And in what : Convenience to the general public and increase in economic activities
locations?
E. Target beneficiaries Government employees and agencies, NGOs, CSOs, POs and general public
F. Target Output / Success Indicator New government center constructed as per approved plan
G. Possible Risks Unavailability of funds, inability to complete the project as per approved plan
H. Expected Private Sector Response Positive response from the private sectors since they will also be benefitted
226 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
227 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
228 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
IS4 | Construction of Stockroom for accounts, reports, and records of all government offices
Name of Project CONSTRUCTION OF STOCKROOM FOR ACCOUNTS, REPORTS, AND RECORDS
OF ALL GOVERNMENT OFFICES
A. Brief Description 500 sq. m. (land area) stockroom for accounts, reports, and records of all government
offices
B. Location of the project Barangay Sta. Rita
C. Program Components Construction of stockroom
Proponents Municipal Engineering Office; General Services Division
Program Term 2019
Phasing and Timeline January 2019 to December 2019 – completion of construction of the stockroom
Requirements needed to be done to produce Feasibility Study, Program of Works and Detailed Building Plan
the desired output
229 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline January 2019 to January 2021 – completion of construction of the warehouse
Requirements needed to be done to produce Feasibility Study, Program of Works and Detailed Building Plan
the desired output
1. Bids & Awards
Steps or procedure of the project 2. Procurement of Materials
3. Construction proper of the project
4. Completion of project
Implementing Arm General Services Division, MEO
Monitoring and Evaluation personnel/group Municipal Planning & Development Office, Municipal Engineering Office and General
Services Division
Frequency of monitoring and evaluation
Monitoring and evaluation will be observed in accordance to existing issuances
Estimated Materials 8,250,000.00
Costs Human Resources (Labor) 4,500,000.00
Equipment 2,250,000.00
Others
TOTAL 15,000,000.00
Funding Source General Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP To ensure the safety of Plan, Property and Equipment of the Municipality as well as to
serve as a buffer place for construction materials to be used for future projects of the
Municipality.
Major Problem being addressed Lack of safe storage for the Municipality’s PPEs and construction materials
What are the effects of the project to social Proper management of PPEs and construction materials
and economic activities? And in what
locations?
E. Target beneficiaries Public clientele and the Local Government of Pinamalayan, General Services Division
F. Target Output / Success Indicator Newly built warehouse for PPEs and construction materials
G. Possible Risks Unavailability of funds and availability of location for construction
H. Expected Private Sector Response Trust and confidence will be built on the Local Government for prompt response to
needs; overall satisfaction for the services rendered.
230 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
231 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Steps or procedure of the project : The PGOM shoulders the manuals reproduction cost, procurement of tablets and
other equipment, Trainors’ Training expenses and others.
: The Municipal Government shoulders enumerators’ honorarium set at 45 pesos per
household, field editor/coordinators’ honorarium set at 15 pesos per household,
enumerator’s training expenses and other incidental expenses attributed to
subsequent activities such as field monitoring, validation, manual encoding (if
necessary), refinements and reproduction.
: The DILG and NAPC will provide the technical assistance and trainers for the three
(3) modules.
Implementing Arm Municipal Planning and Development Office and CBMS-TWG
Monitoring and Evaluation personnel/group MPDO
232 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
233 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Monitoring and evaluation will be observed in accordance to existing issuances
Estimated Materials 600,000.00
Costs Human Resources (Labor) 300,000.00
Equipment 100,000.00
Others
TOTAL Php 1,000,000.00
Funding Source General Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP LGU mandate to ensure safety and security of employees and properties
Major Problem being addressed Compliance to fire code
What are the effects of the project to social Secured workforce, properties and clients
and economic activities? And in what
locations?
E. Target beneficiaries Municipal employees and our constituents.
F. Target Output / Success Indicator Installation of 60 units HCFC Type Fire Extinguisher (10 lbs.), 30 units Exit Signs, 4
units Fire Exit Ladder with landing, 24 units Fire alarm bell (battery operated), and 1
unit Manual Pull Station, and 12 units smoke detector.
G. Possible Risks Unavailability of funds
H. Expected Private Sector Response Convenience to all clienteles
234 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Monitoring and evaluation will be observed in accordance to existing issuances
Estimated Materials Php 350,000.00
Costs Human Resources (Labor) Php 50,000.00
Equipment Php 560,000.00
Others Php 50,000.00
TOTAL Php 910,000.00
Funding Source General Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP To ensure adequate and conducive space for the paying public, clients, and office
personnel and staff.
Major Problem being addressed Limited and inconvenient space for transacting clients
What are the effects of the project to social Comfortable atmosphere of the paying public, and fast and effective performance of
and economic activities? And in what all office personnel
locations?
E. Target beneficiaries Taxpayers, clients and Municipal Treasury Office personnel
F. Target Output / Success Indicator Improved taxpayers lounge at Municipal Treasury Office
G. Possible Risks Lack of Funds
H. Expected Private Sector Response Public satisfaction and convenience
235 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
236 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
237 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
238 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
239 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Phasing and Timeline : January to June 2019 (6 months) – Conduct of Study Tour/Submission of
Request/MOA signing
: July to December 2019 (6 months) – Procurement of hardware &
software/Installation of System and internet/Conduct of orientation & briefing
: January to March 2020 (3 months) – encoding of entries/Operation monitoring
Requirements needed to be done to produce : Feasibility Study
the desired output : Training/Orientation of Library Staff
240 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
241 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
242 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
Frequency of monitoring and evaluation Monitoring and evaluation will be observed in accordance to existing issuances
Estimated Materials PHP 5,500,000.00
Costs Human Resources(Labor) PHP 3,000,000.00
Equipment PHP 1,500,000.00
Others
TOTAL PHP 10,000,000.00 (2022)
Funding Source LGU, PGOM, National Fund
Is the Project expected to be financially self- No
sustaining?
D. Justification of the Project
Rationale/ Objective derived from CLUP/CDP LGU mandate to provide government facilities and services
Major Problem being addressed Concerns on dilapidated facilities, limited space and unsecured public documents
What are the effects of the project to social and Convenience to the general public and proper storage of public documents
economic activities? And in what locations?
E. Target beneficiaries Municipal Employees and Clients
F. Target Output / Success Indicator All office buildings and facilities repaired and improved
G. Possible Risks The weather condition and natural calamities are considered as major risks that
could cause delay in the implementation. This may cause undue delay for project
duration and completion
H. Expected Private Sector Response An absolute positive response is expected since this will not only benefit the people
and the community but it will also contribute to the socio-economic development of
the locality
243 | P a g e
COMPREHENSIVE DEVELOPMENT PLAN OF PINAMALAYAN (2019-2028)
244 | P a g e