Professional Documents
Culture Documents
HU1.03.0004en E
HU1.03.0004en E
MAINTENANCE
HU 1.03.0004 En 1 ( 11 ) INSTRUCTION 1
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
3. ERECTION AREA
Reserve an area large enough for the crane parts, transportation vehicles and mobile cranes. This
area is to be fenced in to ensure the safety of personnel not involved with the erection of the
crane. Refer to figure 5 for the space above the crane rails required. Verify that the clearance
between the crane and the ceiling is sufficient. If the clearance is insufficient, the crane must be
erected before the ceiling is laid, or an opening for the mobile crane jib must be left in the ceiling.
3.1 Loads on the erection area
The erection area must be inspected prior to the erection of the crane to verify that the loads
caused by the crane parts, transportation vehicles and mobile cranes are acceptable. Note that
there is a considerable peak load caused by the support legs of the mobile crane.
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
Figure 5: The space required above the crane track level for a mobile crane jib, hook
and lifting ropes
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
Figure 6: Use one mobile crane to lift the main girder and rotate it to
the proper position
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
Figure 8: Pull the main girders together into the docking position to fasten the end
carriage joints
1. Roller block or roll
2. Ratchet lever
3. Jack or suitable support
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
5. ELECTRICAL CONNECTIONS
The cranes are delivered from the factory completely wired. To prepare the crane for shipping,
remove the conduits at the terminals. The cables and the conduits are marked according to the
wiring diagrams. Follow the wiring diagrams to rewire the controls. Cut the cables to the proper
length when needed and relabel them.
6. INSTALLATION TESTING
6.1 Inspection prior to electrical connection
6.1.1 Mechanical parts
− Inspect the mechanical structures for damage or cracks which may have occurred during
shipping or erection.
− Pay special attention to the flanges of the gears, brakes and motors.
− Check the ropes for damage.
− Check the bolted joints and tighten all loose bolts.
− Check the fastening of all rope clamps.
− Check the adjustment of the brakes.
− Check the adjustment of the hoisting limit switches and travelling/traversing limit switches.
− Remove the temporary corrosion protection from surfaces such as the brake, clutch and trolley
rails.
MAINTENANCE INSTRUCTION PAGE FILE
MAINTENANCE
HU 1.03.0004 En 9 ( 11 ) INSTRUCTION 1
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
6.1.2 Lubrication
− Verify the fluid levels in all gear boxes. If necessary, fill to the proper level with the fluid
recommended in the maintenance manual.
− Check grease lubrication of rail wheels, rope pulleys and other moving parts.
− Lubricate all open gears, gliding surfaces, ropes etc.
6.1.3 Inspection of electrical equipment
Inspect the mounting of electrical equipment. Tighten all loose screws. Open all junction boxes,
limit switches etc. to check for damage from corrosion or moisture. If necessary, clean and dry
the equipment. Check all wire connections. Tighten all loose connections. Place all switches in
the OPEN position.
6.1.4 Insulation resistance test
Open the motor terminal strips. Measure the insulation resistance of all motors, brakes and
electrical circuits between each phase and ground using a voltage of 1000 V. All resistance
readings must be at least 5 MΩ. If the reading is less, the wiring equipment etc. must be checked
and corrected to obtain a reading of 5 MΩ.
6.2 Temporary power supply
If the permanent power supply line to the crane is not ready for testing, a temporary power supply
cable may be used. The permanent power supply cable is normally connected to the incoming
terminal of the crane's main switch. The grounding conduit is then connected to the grounding
strip in the same cubicle.
The temporary power supply cable must be protected with fuses with the same rating as the main
fuses on the crane. The temporary cable must have the same current rating as the fuses. If the
cable supplied is long, adjust it such that the initial voltage drop does not exceed 5 % of the
nominal voltage when measured at the main switch terminals.
6.3 Powering up
Verify that all switches are in the OPEN position before turning the power on. Verify that the
main line disconnect switch is protected by the proper fuses. Verify that the proper supply voltage
is used. Verify that the system has been properly grounded. Check that the power comes to the
main switch.
6.4 Testing the electrical circuits
6.4.1 Lighting and heating circuits
Turn on the power for the lighting and heating. Verify that all devices in the circuits are func-
tioning properly.
6.4.2 Control circuits
If a test switch is provided with the crane, switch it on. If a main current safety switch is supplied
with the crane, switch it to the OPEN position. If neither of these safety switches have been
provided, press the STOP button. Switch all controls to the zero position. Turn the power on.
MAINTENANCE INSTRUCTION PAGE FILE
MAINTENANCE
HU 1.03.0004 En 10 ( 11 ) INSTRUCTION 1
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E
Check the relay functions in the cubicles when adjusting the controls. Test the limit switches by
adjusting them by hand and verifying that the correct relays are functioning in the cubicles.
6.5 No-load test
Release the stop push-button and press the start push-button. The main contact should activate. If
it does not activate, verify that all of the limit switches are off and check the wiring.
Test drive each speed. Begin driving at the slowest speed and check that there are no mechanical
obstacles in the path.
When testing the hoist, make sure that the hook block does not touch the steel construction of the
trolley. If the hook block is already reeved, set the hoist limit switches.
Prior to testing travelling, remove any mechanical obstacles (i.e. steel bars on the rails, air
conditioning tubes or devices, low hanging lamps etc.). When driving to the end limits for the
first time, drive slowly to check the function. Gradually raise the speed.
6.6 Reeving the bottom block
If the bottom block is not reeved, it is to be done after the no-load testing. First, reeve the hoist
rope with a suitable fiber rope as shown in the diagram. Connect the rope to the hoist rope and
then pull it by using the hoisting machinery. After connecting the hoist rope, check and reset the
hoist limit switches if necessary.
6.7 Load test
The crane must be load tested prior to operation. Prepare a report to indicate the test results. After
adjusting the test load, make sure that the load is secure and properly balanced. Raise the load
gradually to specific intervals (such as 1, 2, 4 and 8 feet). Drive downwards and press the stop to
test the stopping and the holding of the hoist brakes.
6.7.1 Overload tests
Test the hoist brakes prior to performing the overload tests. To perform the overload tests, drive
all motions by overload. If static loading is required, lift the test load only a few inches. Maintain
the load at that height for 10 minutes. Lower the test load. If the hoist brakes glide, reset the brake
torque according to maintenance instructions.
SWL/tons
0 <? 5 1.25 x SWL 1.25 x SWL 1.25 x SWL 1.25 x SWL + 1.20 x SWL
0.25 x load dyn.
5 < ? 20 1.25 x SWL 1.20 x SWL 1.25 x SWL handling device,
if its weight
exceeds 5 % of 1.40 x SWL
SWL
MAINTENANCE INSTRUCTION PAGE FILE
MAINTENANCE
HU 1.03.0004 En 11 ( 11 ) INSTRUCTION 1
KCI Konecranes DEPT./HANDLED BY: APPROVED BY: DATE: SOFTW./VERS. LANG. ISSUE
International Plc NVA/ CHD/
J. Kalmi R. Räikkönen 13.01.2001 Word 97/Vertex En E