JOB SAFETY & ENVIRONMENTAL ANALYSIS WORKSHEET

Country Office / Project: JGC PENTHOUSE EXTENSION BLDG. Tools and or Equipment required: JSA No:
Crane, rigging equipment,
Job Location & Details: Setting up for crane operation ( All locations) outrigger pads delineation tape. Date Prepared:

JSA Participants:
Approved by: HSE Manager

Responsible Supervisor:
Date:
JOB STEP HAZARDS IDENTIFIED CONTROLS REQUIRED (Eg. Remove overhead cable or ACTION BY/RECORD
(Eg. Electrocution from isolate/sheath overhead or monitor with spotter) Training PPE
(Eg. Set Up Crane) (Eg. Supervisor)
11Kv Cables) Needs
Setting up the crane Unstable ground conditions 1. Select solid ground conditions All works to be monitored and
(trenches excavations backfilled 2. Place weight distribution timbers parallel for outrigger pads supervised at all times by
without compaction, underground 3. Extend outriggers ensuring area is clear of personnel Engineer, Superintendent,
pipes loose sandy soil) Electrical 4. Level crane ( tires to be clear of ground) Supervisor, Safety Engineer
shock, trips falls, contact with 5. Place delineation around crane perimeter
counterweight and outriggers , 6. Extend boom to working length ensuring there are no
crushing injuries. electrical wires overhead.
7. Check all weight lifting gauges
8. Check anti 2 block is working
9. When lifting loads ensure that level is checked and there is
no sinking of weight distribution timbers / pads
10. Ensure radio communication system is working.
11. Always keep crane outriggers and carrier body clean and
free of grease, oil, and unwanted materials.
12. Under no circumstances should any crane operation take
place unless all outriggers are fully extended and the crane
is level.