Professional Documents
Culture Documents
To distribute 12m lengths of district cooling pipes 500mm in diameter from the compound area
to the trench side at high level and lift into position on the sandbages at the lower level. These
will be lifted using a bow shackle and two web slings and a tag line.
V1.0 1
DETAILS OF LIFTING EQUIPMENT
Capacity and Type 14T Tonne Excavator
Radius 7.54m
Gross Weight 14400kg Coupler lifting Eye 8000kg
Boom length 4.6m
Total Arm length 3.01m Hook Eye SWL 8000kg
Safe working load 1542kg Counterbalance weight N/A
Outrigger spread N/A
Ground Conditions (CBR/Strata),
temporary works design in place and
checked off (where appropriate) N/A
Outrigger loadings N/A
Spreadmat reqs N/A
Note: where operating (jib) height equals or exceeds 10 metre at any time, the appointed person
must advise and consult with the manager from any airport/airfield within 6km of the site
Airport/Airfield Reqs
V1.0 2
SITE CONDITIONS AND HAZARDS
The following non-exhaustive list should be considered during the lift plan along with any other
factors that could affect any aspect of the lift:
1. Excavations 9. Scaffolding
2. Embankments 10. Plant and Equipment
3. Overhead/Underground Services 11. Roads
4. Obstructions 12. Rivers
5. Culverts 13. Railways
6. Drainage 14. Personnel and Public
7.Manhole/Inspection Chambers 15. Other Cranes
8. Buildings/Stationary Objects 16. Environmental Considerations
HAZARDS CONTROL
Potential trench collapse due to weigh of plant and Plant equipment will be at least 1 metre
movement close to edge of excavation away from the edge of the excavation
V1.0 3
WEATHER/ENVIRONMENTAL CONSIDERATIONS
Weather conditions will be reviewed on the day that the lift takes place. The following points
must be considered: High Winds- slung load to be kept maximum of 500mm from ground
height. Rain - excessive rain can make ground surface muddy and slippery, if this is the case on
day of lift, consideration to be taken of the route prior to any lifting. Excessive rain can also
affect excavations due to softening of sides and waterlogging of trench floor. Trench inspections
will take place prior to any lifting by the competent civils contractor and any standing water
pumped out.
ACCESS ARRANGEMENTS
Route from compound to excavation to walked prior to any lifting taking place. Any changes
that are not noted in this plan to be considered and risks/controls put in place and approved by
the appointed person. Once the lift is at the excavation, there is to be no operatives in the work
area until the pipe is safely placed on sandbags. At this point any manoeuvre required can be
done by operatives in sight of the signaller.
THIRD PARTY CONSIDERATIONS
N/A
EMERGENCY/BREAKDOWN PROCEDURES
1. Prior to any lifting, a safe zone will be agreed with the principle contractor, with access path
free of any obstructions
2. All operatives involved in lift operations to be fully briefed prior to commencement of the lift
with all actions and procedures
3. Should an emergency situation arise, operatives to move to designated safe area
SIGNALLING
1. Signaller to agree hand movements that will be used for the lift operations with the machine
driver prior to commencement.
V1.0 4
SAFE SYSTEM OF WORK - METHODOLOGY
1. The signal/slinger is to walk the route to ensure that there are no other considerations to be
reviewed for the lift plan.
2. All plant and equipment to be checked (machines, slings and shackles) and recorded by the
trained and competant person.
3.Pre Start Briefing for all operatives involved in the lift operation
5. The signal/slinger is to ensure that the correct tonnage web slings are selected for the load.
Sling using the double choice method - 2 slings at 45 degree angle equal to the load.
8. Once load is balanced, the lift can commence keeping the load as low to the ground as possibl
9. The pipes are to be lowered into position within the excavation, onto pre laid sandbags. At
this point, if necessary, operatives to enter excavation to make small adjustments whilst in sight
of the slinger/ if required a third person must be in line of sight to relay the instructions from
the signal/slinger to the machine driver.
10. Once the pipe is in the required position, the slings can be removed from the pipe and the
slinger can exit the trench via the access ladder provided or stepped trench.
V1.0 5
LIFT TEAM
The details of this lift plan, along with any other associated risk assessment, method statement
or safe system of work, have been brought to the attention of, and explained to, the persons
listed below, who acknowledged that they understand the contents, hazards and associated
control measures.
OTHER RELEVANT DOCUMENTATION
Certification for Slinger/Singnaller and Machine Operator
V1.0 6