Hazard Identification, Risk Assessment & Risk Control (HIRARC)

Company : M-CUBE ENGINEERING SDN BHD Conducted by: Wan S. Faris, Ahmad Faiz

Project : AHU UVGI Installation Approved by: Mr Eric Lee

Last Review : 1/1/2021 Next Review : 1/1/2021

1. Hazard Identification 2. Risk Assessment 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b.
Action Officer,
Existing Risk Control
Designation

Likelihood

Risk Level
Severity
Possible Accident / Ill
No. Work Activity Hazard Additional Risk Control
Health & Persons-at-Risk
(if any) (Follow-up date)

1 UV Light Work at height Body injury a. Ladder / scaffolding must be in 3 2 6


good condition.
UV Exposure Conjunctivitis, corneal a. Ensure PPE is worn - Face Shield 4 3 12 a. First aid treatment
inflammation or skin burn or eye protection, and limit exposure (minor)
time when UV light is on b. Send to hospital
b. Ensure that safety switch is (major)
operational c. Post safety sign at
c. Never look directly at the beam AHU
Oxygen Deficiency Worker unconscious a. Proper ventilation provided 4 2 8
b. No worker shall be working alone
(BUDDY system)
Hazard Identification, Risk Assessment & Risk Control (HIRARC)
Company : M-CUBE ENGINEERING SDN BHD Conducted by: Wan S. Faris, Ahmad Faiz
Project : Cryogenic Pipe Isolation Approved by: Mr Eric Lee
Last Review : 1/9/2019 Next Review : 1/9/2020

1. Hazard Identification 2. Risk Assessment 3. Risk Control


1a. 1b. 1c. 1d. 2a. 2b. 2c. 2d. 3a. 3b.
Action Officer,
Existing Risk Control
Designation

Likelihood

Risk Level
Severity
Possible Accident / Ill
No. Work Activity Hazard Additional Risk Control
Health & Persons-at-Risk
(if any) (Follow-up date)

2 Control Panel Live electric Electrical shock a. Isolate the power source. 4 2 8
Installation Work at height Body injury a. Ladder / scaffolding must be in
3 2 6
good condition.
Work at wet condition Body injury a. Proper safety boot
(condensation from AHU) 3 3 9
cause slippery